Title Page
-
Site Address -
-
Conducted on
-
Prepared by
Site Inspection
-
Temporary fencing installed around site?
-
Construction site sign legible and displayed<br>on front fence?
-
Toilet on site clean and in good working<br>order?
-
Site office installed and setup?
-
Cool drinking water available?
-
Site induction training completed for all new trades on<br>site?
-
Construction Induction training completed?<br>(Red card or equivalent)
-
SWMS's completed for medium/high risk trades on site?
Excavation
-
Is site adequately protected from public access?
-
Is site benched to correct level?<br>
-
Has land surveyor pegged the site?
-
Has the base been passed by the building surveyor?
-
Has the concreter used the surveyors set out pegs?<br>
Building surveyor inspections
-
Have the piers been approved?<br>
-
Has the base inspection been approved?
-
Has steel inspection been approved?
-
Has building surveyor approved slab for pouring?
-
Has sewer/stormwater services been checked by camera pre pour?
Preslab
-
Are all porches and columns included in set out?
-
Are slab elevations all as per drawings?
-
Are all edge beams at correct depth?
-
Are all edge beams as per engineers design?
-
Are deepened rebates as per engineers design?
-
Are step downs per engineers design?
-
Are garage step downs as per plans and engineers design?
-
Are trenches clear of debris?
-
Are internal beams located as per engineers design?
-
Are all plumbing waste pipes as per working drawings?
-
Are upper level stack pipes as per working drawings?
-
Are all waste pipes sewer grade pipes? (Eg 100mm)
-
Are all sewer pipes and breather pipes located as per working drawings?
-
Does all pipe work have adequate concrete coverage?
-
Does all pipe work have adequate lagging?
-
Is service conduit installed for kitchen sewer?
-
Are shower recesses boxed out in the correct location?
-
Is all plastic membrane laid and adequately tapped and joined? (200mm lap)
-
Is plastic membrane adequately tapped and joined around sewer pipes?
-
Is trench mesh as per engineers drawings?
-
Is trench mesh adequately overlapped and tied at joins?
-
Is all reinforcement fabric adequately overlapped and tied?
-
Is all reinforcement fabric adequately tied to corner bars as designed by engineers?
-
Is all reinforcement fabric installed on correct bar chairs?<br>
-
Is all additional reinforcement for load points installed as per engineers design?
-
Has the under slab termite treatment been installed
Post pour
-
Have all boxing / stakes etc been removed?
-
Finish of the completed slab?
-
Check slab for flatness with 2m level and mark up as required.
Construction foreman sign off
-
Add signature