Information
-
Site Inspection Title:
-
Report Serial Number:
-
Client:
-
Conducted On:
-
Report Prepared By:
-
Site Address:
-
Contractors On Site:
WORK IN PROGRESS
-
The following works are currently in progress:
PREVIOUS SITE INSPECTION
-
Has the site received a previous site inspection?
-
Have all non compliances been rectified
-
Additional comments on the section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
TRAINING
-
Does the Site Manager hold SMSTS or equivalent?
-
Have any toolbox talks been carried out?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
SECURITY
-
Is security in place to prevent site access?
-
Is the site secure from access from unauthorised persons?
-
Does the site have a signing in book for operatives and visitors?
-
Is the signing in book enforced?
-
Are id badges / company hi vis worn?
-
Additional comments on the section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
PERFORMANCE BEYOND COMPLIANCE
-
Are there any examples of innovation in health and safety management and best practice?
-
Are there any examples of measures / incentives to promote and improve safety on site?
-
Is there any evidence of consulting with the workforce?
-
Do internal health and safety inspections get carried out and are senior management tours conducted?
-
Is there a regular housekeeping schedule?
-
Additional comments on the section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
INDUCTION
-
Have inductions been carried out?
-
Does it cover adequate topics, are records retained and does it cater for non English speakers?
-
Have visitors, including Client staff / Project Team received an induction?
-
Are copies of competency tickets available or a record of serial numbers retained?
-
Does the site have any non English speaking operatives present and have they been appropriately inducted?
-
Additional comments on the section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
SITE DOCUMENTATION AND DISPLAY NOTICES
-
Is the contractor aware of Client minimal safety standards and is a copy available on site?
-
Is there a version of the Construction Phase Plan in place on site?
-
Is the F10 displayed and on site (where project us 'notifiable')?
-
Is there a current completed Health and Safety Law Poster ('what you should know') on display?
-
Is there an emergency first aid notice displayed identifying site first aides and contact numbers?
-
Are insurance certificates on display Employee / Public liability?
-
Is there a copy of the Company Environmental Policy on display, signed and dated?
-
Is there an up to date PUWER register held on site?
-
Is there an up to date LOLER register held on site?
-
Is there the appropriate test certification for hired and fixed plant held on site?
-
Is there a current Traffic Management Plan in place?
-
Is there a copy of the Company Health and Safety Policy on display, signed and dated?
-
Additional comments on the section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
FIRE PLAN AND EMERGENCY PROCEDURES
-
Is there an Emergency Evacuation Plan in place and on display, are operatives aware of it, does it take account of existing systems?
-
Is there a means of raising the alarm and is it audible in all parts of the site?
-
Is the fire Marshall and muster point identified?
-
Are there adequate fire escape routes are they signed and kept clear?
-
Are flammable a stored appropriately (incl LPG) and flammable waste removed in a timely fashion?
-
Are naked flames and smoking prohibited in these areas?
-
Does a certified person control hot works permits, and are controls adequate?
-
Are appropriate and sufficient site fire extinguishers in available?
-
Have fire extinguishers been inspected within last 12 months?
-
Has a site fire risk assessment been carried out?
-
Do contractors have fire extinguishers to hand where hot works are being carried out?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
ASBESTOS MANAGEMENT
-
Is an asbestos survey report / register / clearance certificate available!
-
Is a management procedure in place?
-
Is this covered in the site induction?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
RISK ASSESSMENTS
-
Are they on site, current, suitable and sufficient?
-
Are they signed by a competent person?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
METHOD STATEMENTS
-
Are they site specific, suitable and sufficient, complied with, received in good time, and is there a procedure to approve them before use?
-
Are they communicated to operatives, and countersigned as confirmation of being understood?
-
Are site operations conducted safely and in line with the method statement?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
COSHH
-
Have all harmful substances been identified on site?
-
Are hazardous substances properly stored, and controls for safe use been put in place?
-
Are Material Safety Data Sheets, and COSHH Assessments on site to accompany substances being used?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
NOISE AND VIBRATION
-
Have noises operations been identified?
-
Are exclusion zones required?
-
Is hearing protection provided an used?
-
Have operations involving hazardous levels of vibration been identified?
-
Are appropriate control measures implemented?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
PERMITS TO WORK
-
Have activities requiring PTW been identified?
-
Are they retained on site?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
PROTECTING THE PUBLIC
-
Is the general public segregated from the working area by suitable and robust hoardings, barriers or fencing?
-
Is signage suitable and sufficient?
-
Is traffic management suitable and sufficient?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
SITE WELFARE FACILITIES
-
Are there adequate seating arrangements provided?
-
Is there a suitable canteen / rest area?
-
Is the canteen clean and tidy?
-
Are facilities provided for the heating of food?
-
Is there the means to heat water?
-
Is there an adequate drying / changing room?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
FIRST AID PROVISION
-
Has a qualified first aides been identified?
-
Are there adequate first aid provision and is it well stocked and clean?
-
Is there an accident book on site or head office reporting?
-
Are all accidents, near misses and incidents recorded?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
PERSONAL PROTECTIVE EQUIPMENT
-
Has suitable PPE been provided for activities being carried out?
-
Is the PPE being worn fit for purpose?
-
Is PPE in good condition?
-
Are all site personnel compliant with the site required PPE?
-
Is the wearing of PPE enforced?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
SAFE PLACE OF WORK
-
Can the working area be reached safely?
-
Are temporary and permanent structures stable?
-
Are temporary structures designed and certified by a competent person?
-
Is housekeeping in good order and the site free from trip hazards?
-
Is the site compound and storage area in good order with waste and materials stored safely?
-
Is the working area / access adequately lit?
-
Is the temperature and weather suitable?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
LIFTING OPERATIONS AND LIFTING EQUIPMENT
-
Are operators / banksmen / slingers competent?
-
Is lifting equipment inspected weekly and records retained?
-
Does the lifting equipment have current inspection / test certificates?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
MANUAL HANDLING
-
Have manual handling assessments been carried out and being adhered to?
-
Are alternative mechanical means utilised?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
LADDERS
-
Are ladders the right equipment for the job?
-
Are they in good condition?
-
Are they tied or otherwise prevented from slipping?
-
Are they positioned to prevent over reaching?
-
Does the ladder rest against a solid surface?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
WORKNG AT HEIGHT ACCESS EQUIPMENT
-
Is scaffolding used on site?
-
Are harnesses worn during erection / dismantling?
-
Is there safe access?
-
Are standards upright and on a firm foundation?
-
Are standards / ledgers / braces / struts in correct position?
-
Are appropriate guard rails and toe boards in place?
-
If required, are brick guards / debris netting / debris fans installed and suitable?
-
Are platforms fully boarded?
-
Are materials evenly distributed?
-
Are platforms clean and free from debris?
-
Are loading bays designed and marked with loading limits?
-
Is scaffold inspected / tagged every 7 days, with reports held on site?
-
Are mobile towers / podiums in use and are they fit for purpose?
-
Are towers erected and inspected by PASMA trained personnel?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
ROOFWORK
-
Is all roof work controlled by a permit to work?
-
Is there suitable protection to prevent falls of persons / objects?
-
Are materials stored securely and safely?
-
Are roof ladders / crawling boards being used (in addition with safe working platforms)?
-
Is work on fragile roofs secure to prevent falls?
-
Have 'safe zones' been created been created below fragile roofs?
-
Have adverse weather conditions been taken into consideration?
-
Are harnesses / lanyards utilised?
-
Are safety nets / crash bags or other fall protection systems used?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
EXCAVATIONS / CONFINED SPACES
-
Are there adequate controls for any confined space working?
-
Are excavations adequately shored / battered back / ventilated and dewatered?
-
Is access into excavation safe?
-
Are there at least two means of access?
-
Are adjacent structures unaffected by the excavation!
-
Is the probability of excavation collapse unaffected by adjacent structures / spoil etc?
-
Are excavations inspected and are records retained?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
POWERED ACCESS EQUIPMENT (MEWPS)
-
Is the equipment stable?
-
Are equipment operators trained and competent?
-
Is equipment being used in a safe manner?
-
Does the access equipment have a current inspection / test certificate?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
HOISTS
-
Is the hoist operator trained and competent?
-
Is the hoist inspected weekly and records retained?
-
Does the hoist have a current inspection / test certificate?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
PORTABLE PLANT AND MACHINERY
-
Are all dangerous parts guarded?
-
Is plant and machinery being used safely?
-
Does the equipment have a current inspection / test certificate?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
TRAFFIC AND VEHICLES
-
Are there separate vehicle / pedestrian routes which are suitable and sufficient?
-
Are there adequate precautions during the use of vehicles (e.g. reversing warnings)?
-
Are drivers competent and adequately trained?
-
Are there adequate wheel washing facilities / street cleaning?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
ELECTRICAL SAFETY
-
Is live work / inspection prohibited?
-
Is the supply a maximum of 110V?
-
Are trip devices / RCDs used where mains voltage is used?
-
Are cables and leads in good condition?
-
Are trailing cables protected / routed to prevent damage?
-
Are systems inspected and tested by a competent person?
-
Are portable electrical appliances inspected and tested in accordance with the main contractors health and safety policy?
-
Have overhead power lines been considered?
-
Have underground cables been located, marked and precautions taken to dig safely?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
WORK AREAS
-
Are works areas free from congested?
-
Are work activities being managed safely?
-
Are trailing leads being managed (trip hazards) ?
-
Are suitable dust control measures in place, (I.e. dampening down during sweeping, dust extractor fitted to cutting equipment)?
-
Is the standard of housekeeping acceptable?
-
Is there adequate storage facilities for materials?
-
Are suitable and sufficient Risk Assessments and Method Statements in place for activities being carried out?
-
Are permits issued and recorded (hot works, electrical distribution board)?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
ENVIRONMENTAL
-
Does the site have a Waste Carrier Licence in place?
-
Is waste appropriately segregated on site?
-
Are waste transfer and / or consignment notes recorded on site?
-
Are the above correctly completed?
-
Are spill kits in place?
-
If applicable, are there controls to reduce run off to surface water?
-
Are paints and varnishes water based?
-
Additional comments on this section are:
-
This denotes the highest level of non-compliance within this section of the audit and the period by which it is to be rectified.
- Imminent danger - Immediately
- Total omission - 1 day
- Concern - 3 days
- Minor omission - 7 days
- Compliant no issues
- Not applicable to this site
Report Summary
Report Summary
-
Site Inspector
-
Site Inspectors Comments
-
Site Manager / Representative
-
Site Manager / Representative Comments
COMPLETION ON NON-COMPLIANCES
-
The Site Manager is confirm that the non-compliances raised have been appropriately dealt within the time frame specified by: 1. Signing and writing the date next to the non-compliance item. THE COMPLETED AUDIT IS TO BE RETURNED TO THE OFFICE FOR REVIEW AND ARCHIVE WITH PROJECT FILES