Foundation check
-
Are piles driven into correct embedment? (25% of above ground height)
-
Are the piles free from damage?
-
Have the top of piles been painted with galv after piling to ensure corrosion resistance?
-
Have piles been installed with the correct orientation?
-
Are the mounting holes free from damage?
-
Are X-anchor rods fully embedded into the ground?
-
Are X-anchor rods free from damage after being driven into the ground?
-
Has ballast plate been installed on flat ground? (no voids or soft ground under plate)
-
Have nyloc nuts and square plate washers been used for the ballast plate installation?
-
Have blocks been stacked (brick bonded) correctly?
-
Any additional notes?
-
Sign off on foundation check
Frame check
-
Has frame been installed at the correct angle? ( ±1° )
-
What is the true angle?
-
Is framework free from damage?
-
Is frame square between bays?
-
Are the uprights level? (± 3°)?
-
All M12 bolts installed with washers and nuts?
-
All M12's torqued to 80Nm?
-
Take picture of tables with loose fasteners
-
Do purlins have correct gap of 10mm? (110mm if using extender joiner)
-
Reset joiners installed in correct position to drawing?
-
Has 4mm tension wire been tightened and tension lock has been applied?
-
Has cross bracing been installed correctly? (Positions inline with STA drawing)
-
Any additional notes?
-
Sign off on frame check
Paneling check
-
Are panel all square to frame?
-
Are panel clamps done up to guided torque setting (Nm)?
-
Take pictures of panels with with loose clamps
-
Have the panels been clamped in the correct clamping zone?
-
Have the panels been installed with fully engaged coverage of panel frame? (± 2mm)
-
Are the sliding clamps fully engaged with purlin return?
-
Do panels have correct N-S spacing of between 10mm - 20mm?
-
Any additional notes?
-
Sign off on paneling check