Information

  • Document No.

  • Add location

Kitchen / Bathroom Upgrading Programme

  • Tenant name

  • Tenant address
  • Contact telephone number

Tenant choices

  • Kitchen Unit

  • Worktops

  • Flooring

I agree to the choices I have made and accept that no alterations can be made once tenant signature obtained.

  • I understand the process of the installation for my kitchen / bathroom.

  • I have been notified of an approximate start date and how long the process is Iikely to take.

  • I understand that it is my responsibility to remove all personal belongings and appliances prior to the installation of my kitchen / bathroom.

  • I agree to the proposed planned layout and accept the proposed design.

  • I understand that I need to return my customer satisfaction questionnaire, following which I will receive my decoration allowance.

  • I have read and understood all of the above.

  • Add signature

For office use only

  • Proposed Start Date

  • Survey Completed

  • Disclaimer obtained

KITCHEN UPGRADE

ELECTRIC

  • Install cooker unit

  • Contractor if not SPC:

  • Replace existing cooker control unit face plate

  • Contractor if not SPC:

  • Replace existing cooker control outlet face plate

  • Contractor if not SPC:

  • Relocate existing cooker control unit & outlet

  • Contractor if not SPC:

  • Install new extractor fan (inc hole cutting)

  • Contractor if not SPC:

  • Additional 2 switch socket (No)

  • Contractor if not SPC:

  • Replace existing 2 switch socket face plate (No)

  • Contractor if not SPC:

  • Relocate an existing 2 switch socket

  • Contractor if not SPC:

  • Install single switch socket with fused spur

  • Contractor if not SPC:

  • Relocate existing single switch socket & fused spur

  • Contractor if not SPC:

  • Replace single switch socket fused spur face plate

  • Contractor if not SPC:

  • Additional wiring to suit new layout (M)

  • Contractor if not SPC:

  • Renew all necessary bonding (No)

  • Contractor if not SPC:

  • Test all new & altered electrical installations (No)

  • Contractor if not SPC:

GAS

  • Provide new or extend gas supply to cooker (m)

  • Contractor if not SPC:

  • Test all new & altered gas installations (No)

  • Contractor if not SPC:

FLOORING

  • Take up existing floor (M2)

  • Contractor if not SPC:

  • Screed flooring (M2)

  • Contractor if not SPC:

  • Renew flooring (M2)

  • Contractor if not SPC:

ADDITIONAL

  • Remove wall tiles (M2)

  • Contractor if not SPC:

  • Renew wall tiles (M2)

  • Contractor if not SPC:

  • Replace taps

  • Contractor if not SPC:

  • Lever taps required?

  • Contractor if not SPC:

  • Supply & fit washing machine pipe fittings

  • Contractor if not SPC:

BATHROOM UPGRADE

  • Replace bath (Size)

  • Contractor if not SPC:

  • Bath mixer valve / Curtain / + Rail / Riser bar

  • Contractor if not SPC:

  • Lever taps required

  • Contractor if not SPC:

  • Replace WHB and Pedestal

  • Contractor if not SPC:

  • Replace WC Pan

  • Contractor if not SPC:

  • Replace WC Cistern

  • Contractor if not SPC:

  • End panel

  • Contractor if not SPC:

  • Side panel

  • Contractor if not SPC:

  • Remove wall tiles (M2)

  • Contractor if not SPC:

  • Renew wall tiles (M2)

  • Contractor if not SPC:

FLOORING

  • Take up existing floor (M2)

  • Contractor if not SPC:

  • Screed flooring (M2)

  • Contractor if not SPC:

  • Renew flooring (M2)

  • Contractor if not SPC:

ELECTRICS

  • Enclosed low energy light fitting

  • Contractor if not SPC:

  • Install new extractor fan (inc hole cutting)

  • Contractor if not SPC:

  • Provide RCBO to bathroom circuits

  • Contractor if not SPC:

  • Shower circuit

  • Contractor if not SPC:

  • Additional Notes / Special Requirements etc

  • Add media

IA-04-07

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.