Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

  • Date of Infection Control Construction Rounds

  • Observer

  • MGH Renovations and Construction
  • Building and room

  • Vendor

  • Building and room

  • Vendor

  • Building and room

  • Vendor

  • Building and room

  • Vendor

  • Building and room

  • Vendor

  • Building and room

  • Vendor

  • Building and room

  • Vendor

  • Building and room

  • Vendor

  • ISLM Assessment -Proper signage is displayed to include emergency contact information, proper PPE to be worn and any special procedures to follow before entering

  • The designated work area is under negative pressure to contain dust and aerosols.

  • Limited access to facility with either a key, key card or number pad entry

  • All egress routes remain unobstructed clearly lit and well marked

  • Incidents are reported promptly to project manager

  • Communication is active and ongoing between floors /areas where work is ongoing and adjacent non construction areas.

  • Noise generation complies with MGH quiet hours of 11 PM to 6 AM<br>Noise is minimized to the extent possible

  • No locks are being used to hinder the emergency exit of workers inside the work site

  • All fire and smoke barriers are maintained and penetrations are properly sealed

  • Enclosures do not lessen the corridor width to less than 48 inches (Healthcare and ambulatory occupancy as required NFPA 101 19.2.3.4. <br>44 inches business occupancy.

  • Facility doors are self closing and locking

  • Fire watches are utilized for hot work per job permit.

  • Facility is under negative pressure- air is directed into the lab and not escaping

  • One hour wall present around perimeter

  • Sprinkler heads

  • Sprinkler heads are in the down position when a drop ceiling is in place. When ceiling tiles are removed the sprinkler heads must be upturned.

  • Heat sensors present when sprinklers are not present

  • Fire extinguishers present and inspected monthly

  • 2 hour wall segregation of buildings

  • Fire proofing of any holes gaps or breaks in containment

  • Compressed gas tanks are properly secured one anchoring strap, chain or other device per tank and removed at the end of shift/day

  • Acetylene cylinders are limited to in use quantitative a plus one spare per site.<br>All other quantities must be stored off site at contractor facilities or MGH approved designated area

Openings and Confined spaces

  • Floor and stairway openings are guarded and secured from accidental entry or fall

  • Floor holes 1" - 12" are covered or guarded

  • Guard rails in place to secure and guard are capable of withstanding 200 lbs ( top rail) are 42" (top, intermediate rail) wit. 4" toe board where applicable (trash debris chute to outside dumpster.)

Overhead work

  • Traffic control below work area is in place with use of barricades and signs

Storage of construction materials and supplies

  • Vendor supplies are secured and accessible only to authorized personnel

  • Trash and debris are collected, covered and removed routinely.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.