Information

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by:

  • Location
  • Personnel

1. LAYOUT

  • Floor:

  • Area/Unit/Room

  • Element
  • Area/Unit #/Room#

  • 1.1 Plans reviewed for changes to date:

  • Select date

  • Comment:

  • Add media

  • Select date

  • 1.2 Layout preformed by control lines/bench mark supplied by the General Contractor:

  • Select date

  • Comment:

  • Select date

  • 1.3 Wall types labeled on floor:

  • Select date

  • Comment:

  • Select date

  • 1.4 Correct rough opening for doors (Length and Width):

  • Select date

  • Comment:

  • Select date

  • 1.5 Rough opening labeled on floor:

  • Select date

  • Comment:

  • Select date

  • 1.6 Panels, lights, access panels, etc. laid out by Electrician:

  • Select date

  • Comment:

  • Select date

  • 1.7 Duct penetrations, grills, access panels, etc. laid out by MEP:

  • Select date

  • Comment:

  • Select date

  • 1.8 Area cleaned and ready for framing:

  • Select date

  • Comment:

  • Select date

2. WALL FRAMING:

  • Floor:

  • Area/Unit/Room

  • Element
  • Area/Unit #/Room#

  • 2.1 Plans reviewed for changes to date:

  • Select date

  • Comment:

  • Select date

  • 2.2 Top and bottom track fastened per specs/code:

  • Select date

  • Comment:

  • Select date

  • 2.3 Double studs or wide flange studs at all door openings:

  • Select date

  • Comment:

  • Select date

  • 2.4 Door openings corrected for width and height:

  • Select date

  • Comment:

  • Select date

  • 2.5 Stud gage and spacing correct:

  • Select date

  • Comment:

  • Select date

  • 2.6 Studs facing direction of layout, punch outs aligned"

  • Select date

  • Comment:

  • Select date

  • 2.7 Walls plumb/square within tolerance:

  • Select date

  • Comment:

  • Select date

  • 2.8 All slider studs installed:

  • Select date

  • Comment:

  • Select date

  • 2.9 All framing components complete per wall type ( backing, CRC, RC, etc.)

  • Select date

  • Comment:

  • Select date

  • 2.10 Access door opening framed:

  • Select date

  • Comment:

  • Select date

  • 2.11 Top out completed at full height walls ( screws removed from top track):

  • Select date

  • Comment:

  • Select date

  • 2.12 Framing inspection completed and accepted (Include copy with report):

  • Select date

  • Comment:

  • Select date

  • 2.13 Picture/Video documentation completed:

  • Select date

  • Comment:

  • Select date

  • 2.14 (GC) QC Log completed:

  • Select date

  • Comment:

  • Select date

  • 2.15 Area is clean, destocked from excess materials an ready for framing:

  • Select date

  • Comment:

  • Select date

3. CEILING FRAMING:

  • Floor:

  • Area/Unit/Room

  • Element
  • Area/Unit #/Room#

  • 3.1 Plans reviewed for changes to date:

  • Select date

  • Comment:

  • Select date

  • 3.2 Ceiling level within tolerance:

  • Select date

  • Comment:

  • Select date

  • 3.3 Wires installed correctly and at 4" maximum spacing:

  • Select date

  • Comment:

  • Select date

  • 3.4 Framing inspection complete and accepted (Include copy of report):

  • Select date

  • Comment:

  • Select date

  • 3.5 (GC) QC log completed:

  • Select date

  • Comment:

  • Select date

  • 3.6 Area is clean, destocked from excess materials an ready for drywall:

  • Select date

  • Comment:

  • Select date

4. INSULATION/FIRESTOP:

  • Floor:

  • Area/Unit/Room

  • Element
  • Area/Unit #/Room#

  • 4.1 Plans reviewed for changes to date:

  • Select date

  • Comment:

  • Select date

  • 4.2 Thermal insulation installed (No gaps and insulation away from precast):

  • Select date

  • Comment:

  • Select date

  • 4.3 Vapor retarder installed (joints and holes completely sealed):

  • Select date

  • Comment:

  • Select date

  • 4.4 Sound insulation installed (No gaps and no compression around boxes):

  • Select date

  • Comment:

  • Select date

  • 4.5 Head of wall fire stop complete:

  • Select date

  • Comment:

  • Select date

  • 4.6 Picture/Video documentation complete:

  • Select date

  • Comment:

  • Select date

  • 4.7 Penetration fire stop complete:

  • Select date

  • Comment:

  • Select date

  • 4.8 Destructive testing:

  • Select date

  • Comment:

  • Select date

  • 4.9 (GC) QC log completed:

  • Select date

  • Comment:

  • Select date

  • 4.10 Area is clean, destocked from excess materials an ready for drywall:

  • Select date

  • Comment:

  • Select date

5. BACKING:

  • Floor:

  • Area/Unit/Room

  • Element
  • Area/Unit #/Room#

  • 5.1 Correct gauge (20ga for fixtures, 14ga for handrails:

  • Select date

  • Comment:

  • Select date

  • 5.2 All locations installed with correct height and width:

  • Select date

  • Comment:

  • Select date

  • 5.3 Photo documentation complete:

  • Select date

  • Comment:

  • Select date

  • 5.4 (GC) QC log completed:

  • Select date

  • Comment:

  • Select date

6. DRYWALL:

  • Floor:

  • Area/Unit/Room

  • Element
  • Area/Unit #/Room#

  • 6.1 Plans reviewed for changes to date:

  • Select date

  • Comment:

  • Select date

  • 6.2 Rock off floor minimum of 1/4":

  • Select date

  • Comment:

  • Select date

  • 6.3 Screw inspection complete and accepted (included copy of report)

  • Select date

  • Comment:

  • Select date

  • 6.4 All boxes have been cut out:

  • Select date

  • Comment:

  • Select date

  • 6.5 (GC) QC log completed:

  • Select date

  • Comment:

  • Select date

  • 6.6 Area is clean, destocked from excess materials and ready for finish:

  • Select date

  • Comment:

  • Select date

7. FINISHING:

  • Floor:

  • Area/Unit/Room

  • Element
  • Area/Unit #/Room#

  • 7.1 Environment within specified temperature (40 degrees Fahrenheit):

  • Select date

  • Comment:

  • Select date

  • 7.2 Level 4 finish completed:

  • Select date

  • Comment:

  • Select date

  • 7.3 Beads are plumb, level and square:

  • Select date

  • Comment:

  • Select date

  • 7.4 Sound caulk at base of wall installed:

  • Select date

  • Comment:

  • Select date

  • 7.5 (GC) QC log completed:

  • Select date

  • Comment:

  • Select date

  • 7.6 Area is clean, destocked from excess materials and ready for paint:

  • Select date

  • Comment:

  • Select date

8. AFTER PRIME TOUCH UP:

  • Floor:

  • Area/Unit/Room

  • Element
  • Area/Unit #/Room#

  • 8.1 Touch up performed and accepted by painter:

  • Select date

  • Comment:

  • Select date

  • 8.2 (GC) QC log completed:

  • Select date

  • Comment:

  • Select date

9. PUNCH:

  • Floor:

  • Area/Unit/Room

  • Element
  • Area/Unit #/Room#

  • 9.1 SSC pre-punch completed:

  • Select date

  • Comment:

  • Select date

  • 9.2 GC punch complete:

  • Select date

  • Comment:

  • Select date

  • 9.3 Owner punch completed:

  • Select date

  • Comment:

  • Select date

  • 9.4 Area signed off by GC ( Include copy of GC report)

  • Select date

  • Comment:

  • Select date

ADDITIONAL CORRECTIVE ACTIONS NEEDED:

  • COMMENTS:

  • INSPECTED BY:

  • Date and Time inspection was completed:

  • Add signature

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.