Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by:
- BOBBY YELINSKI
- BRYAN LEWIS
- RON THOMPSON
- SCOTT MANSFIELD
- REUBEN TRUJILLO (TJ)
- KEVIN EMERSON
- LARRY CHILDS
- JESUS VALADEZ
-
Location
-
Personnel
1. LAYOUT
-
Floor:
-
Area/Unit/Room
Element
-
Area/Unit #/Room#
-
1.1 Plans reviewed for changes to date:
-
Select date
-
Comment:
-
Add media
-
Select date
-
1.2 Layout preformed by control lines/bench mark supplied by the General Contractor:
-
Select date
-
Comment:
-
Select date
-
1.3 Wall types labeled on floor:
-
Select date
-
Comment:
-
Select date
-
1.4 Correct rough opening for doors (Length and Width):
-
Select date
-
Comment:
-
Select date
-
1.5 Rough opening labeled on floor:
-
Select date
-
Comment:
-
Select date
-
1.6 Panels, lights, access panels, etc. laid out by Electrician:
-
Select date
-
Comment:
-
Select date
-
1.7 Duct penetrations, grills, access panels, etc. laid out by MEP:
-
Select date
-
Comment:
-
Select date
-
1.8 Area cleaned and ready for framing:
-
Select date
-
Comment:
-
Select date
2. WALL FRAMING:
-
Floor:
-
Area/Unit/Room
Element
-
Area/Unit #/Room#
-
2.1 Plans reviewed for changes to date:
-
Select date
-
Comment:
-
Select date
-
2.2 Top and bottom track fastened per specs/code:
-
Select date
-
Comment:
-
Select date
-
2.3 Double studs or wide flange studs at all door openings:
-
Select date
-
Comment:
-
Select date
-
2.4 Door openings corrected for width and height:
-
Select date
-
Comment:
-
Select date
-
2.5 Stud gage and spacing correct:
-
Select date
-
Comment:
-
Select date
-
2.6 Studs facing direction of layout, punch outs aligned"
-
Select date
-
Comment:
-
Select date
-
2.7 Walls plumb/square within tolerance:
-
Select date
-
Comment:
-
Select date
-
2.8 All slider studs installed:
-
Select date
-
Comment:
-
Select date
-
2.9 All framing components complete per wall type ( backing, CRC, RC, etc.)
-
Select date
-
Comment:
-
Select date
-
2.10 Access door opening framed:
-
Select date
-
Comment:
-
Select date
-
2.11 Top out completed at full height walls ( screws removed from top track):
-
Select date
-
Comment:
-
Select date
-
2.12 Framing inspection completed and accepted (Include copy with report):
-
Select date
-
Comment:
-
Select date
-
2.13 Picture/Video documentation completed:
-
Select date
-
Comment:
-
Select date
-
2.14 (GC) QC Log completed:
-
Select date
-
Comment:
-
Select date
-
2.15 Area is clean, destocked from excess materials an ready for framing:
-
Select date
-
Comment:
-
Select date
3. CEILING FRAMING:
-
Floor:
-
Area/Unit/Room
Element
-
Area/Unit #/Room#
-
3.1 Plans reviewed for changes to date:
-
Select date
-
Comment:
-
Select date
-
3.2 Ceiling level within tolerance:
-
Select date
-
Comment:
-
Select date
-
3.3 Wires installed correctly and at 4" maximum spacing:
-
Select date
-
Comment:
-
Select date
-
3.4 Framing inspection complete and accepted (Include copy of report):
-
Select date
-
Comment:
-
Select date
-
3.5 (GC) QC log completed:
-
Select date
-
Comment:
-
Select date
-
3.6 Area is clean, destocked from excess materials an ready for drywall:
-
Select date
-
Comment:
-
Select date
4. INSULATION/FIRESTOP:
-
Floor:
-
Area/Unit/Room
Element
-
Area/Unit #/Room#
-
4.1 Plans reviewed for changes to date:
-
Select date
-
Comment:
-
Select date
-
4.2 Thermal insulation installed (No gaps and insulation away from precast):
-
Select date
-
Comment:
-
Select date
-
4.3 Vapor retarder installed (joints and holes completely sealed):
-
Select date
-
Comment:
-
Select date
-
4.4 Sound insulation installed (No gaps and no compression around boxes):
-
Select date
-
Comment:
-
Select date
-
4.5 Head of wall fire stop complete:
-
Select date
-
Comment:
-
Select date
-
4.6 Picture/Video documentation complete:
-
Select date
-
Comment:
-
Select date
-
4.7 Penetration fire stop complete:
-
Select date
-
Comment:
-
Select date
-
4.8 Destructive testing:
-
Select date
-
Comment:
-
Select date
-
4.9 (GC) QC log completed:
-
Select date
-
Comment:
-
Select date
-
4.10 Area is clean, destocked from excess materials an ready for drywall:
-
Select date
-
Comment:
-
Select date
5. BACKING:
-
Floor:
-
Area/Unit/Room
Element
-
Area/Unit #/Room#
-
5.1 Correct gauge (20ga for fixtures, 14ga for handrails:
-
Select date
-
Comment:
-
Select date
-
5.2 All locations installed with correct height and width:
-
Select date
-
Comment:
-
Select date
-
5.3 Photo documentation complete:
-
Select date
-
Comment:
-
Select date
-
5.4 (GC) QC log completed:
-
Select date
-
Comment:
-
Select date
6. DRYWALL:
-
Floor:
-
Area/Unit/Room
Element
-
Area/Unit #/Room#
-
6.1 Plans reviewed for changes to date:
-
Select date
-
Comment:
-
Select date
-
6.2 Rock off floor minimum of 1/4":
-
Select date
-
Comment:
-
Select date
-
6.3 Screw inspection complete and accepted (included copy of report)
-
Select date
-
Comment:
-
Select date
-
6.4 All boxes have been cut out:
-
Select date
-
Comment:
-
Select date
-
6.5 (GC) QC log completed:
-
Select date
-
Comment:
-
Select date
-
6.6 Area is clean, destocked from excess materials and ready for finish:
-
Select date
-
Comment:
-
Select date
7. FINISHING:
-
Floor:
-
Area/Unit/Room
Element
-
Area/Unit #/Room#
-
7.1 Environment within specified temperature (40 degrees Fahrenheit):
-
Select date
-
Comment:
-
Select date
-
7.2 Level 4 finish completed:
-
Select date
-
Comment:
-
Select date
-
7.3 Beads are plumb, level and square:
-
Select date
-
Comment:
-
Select date
-
7.4 Sound caulk at base of wall installed:
-
Select date
-
Comment:
-
Select date
-
7.5 (GC) QC log completed:
-
Select date
-
Comment:
-
Select date
-
7.6 Area is clean, destocked from excess materials and ready for paint:
-
Select date
-
Comment:
-
Select date
8. AFTER PRIME TOUCH UP:
-
Floor:
-
Area/Unit/Room
Element
-
Area/Unit #/Room#
-
8.1 Touch up performed and accepted by painter:
-
Select date
-
Comment:
-
Select date
-
8.2 (GC) QC log completed:
-
Select date
-
Comment:
-
Select date
9. PUNCH:
-
Floor:
-
Area/Unit/Room
Element
-
Area/Unit #/Room#
-
9.1 SSC pre-punch completed:
-
Select date
-
Comment:
-
Select date
-
9.2 GC punch complete:
-
Select date
-
Comment:
-
Select date
-
9.3 Owner punch completed:
-
Select date
-
Comment:
-
Select date
-
9.4 Area signed off by GC ( Include copy of GC report)
-
Select date
-
Comment:
-
Select date
ADDITIONAL CORRECTIVE ACTIONS NEEDED:
-
COMMENTS:
-
INSPECTED BY:
- BOBBY YELINSKI
- BRYAN LEWIS
- RON THOMPSON
- SCOTT MANSFIELD
- REUBEN TRUJILLO (TJ)
- KEVIN EMERSON
- LARRY CHILDS
- JESUS VALADEZ
-
Date and Time inspection was completed:
-
Add signature