Welcome
-
Division
-
Community
-
Address or Homesite
-
Take photo of home from street
-
Installation Contractor
-
Date and Time
-
Audit Performed By
Sections
To be inspected on the roof prior to module installation
Flashings
-
Installed to reach the second course of shingles?
-
Layout matches Solar Plot Plans?
-
Proper sealant used?
-
Take Photo
Rail/Racking
-
Layout matches Solar Plot Plans?
-
All structural hardware present and secure?
-
Splice Kits installed correctly?
-
Take Photo
Bonding
-
Check box if present:
-
Ground lugs
-
Bonding Jumpers
-
Grounding Electrode Conductor (GEC)
-
Take Photo
Wiring
-
Inverter cables secured with provided wire management clips?
-
Waterproof penetrations into Soladeck combiner box?
-
Soladeck flashed properly?
-
Take photo
New Items
To be inspected in the home prior to insulation and drywall
Electrical Rough
-
Romex secured at proper intervals?
-
Combiner and outlet boxes mounted securely and in correct location?<br>
-
Romex terminated with sufficient length for service and connections?
-
Wire fasteners installed correctly and not smashing Romex?
-
Nail plates installed where wire could be at risk of future damage
-
Interior boxes mounted with face 3/8" past studs to clear drywall?
Low Volt / Data Rough
-
Terminated in correct location?
-
Labeled properly?
Smart Fields
-
List any follow up required: