Sections

To be inspected on the roof prior to module installation
Flashings

Installed to reach the second course of shingles?

Layout matches Solar Plot Plans?

Proper sealant used?

Take Photo
Rail/Racking

Layout matches Solar Plot Plans?

All structural hardware present and secure?

Splice Kits installed correctly?

Take Photo
Bonding

Check box if present:

Ground lugs

Bonding Jumpers

Grounding Electrode Conductor (GEC)

Take Photo
Wiring

Inverter cables secured with provided wire management clips?

Waterproof penetrations into Soladeck combiner box?

Soladeck flashed properly?

Take photo

New Items

To be inspected in the home prior to insulation and drywall
Electrical Rough

Romex secured at proper intervals?

Combiner and outlet boxes mounted securely and in correct location?

Romex terminated with sufficient length for service and connections?

Wire fasteners installed correctly and not smashing Romex?

Nail plates installed where wire could be at risk of future damage

Interior boxes mounted with face 3/8" past studs to clear drywall?

Low Volt / Data Rough

Terminated in correct location?

Labeled properly?

Smart Fields

Overall craftsmanship from 1 to 10

List any follow up required:

Please note that this checklist is a hypothetical example and provides basic information only. It is not intended to take the place of, among other things, workplace, health and safety advice; medical advice, diagnosis, or treatment; or other applicable laws. You should also seek your own professional advice to determine if the use of such checklist is permissible in your workplace or jurisdiction.