Safe systems of work - RAMS
-
Daily pre-start briefing
-
Emergency arrangements (including arrangements for dealing with bites, stings etc. Check if any persons in team are at risk of anaphylaxis)
-
Welfare facilities
-
Adequate measures for working in all weathers (warm clothing, waterproofs, sun cream etc.)
-
Hand-held powered machines, e.g. strimmers, chain-saws, hedge trimmers, mowers and water pressure cleaners maintained and in good condition.
-
Drivable machines, e.g. sit-on mowing machines, tractors and dumper trucks maintained and in good condition.
-
Static machines, e.g. mulchers and shredders maintained and in good condition with adequate guarding in place and emergency stops etc. functional
-
Hand tools, e.g. spades, forks, picks, shovels, rakes, shears, loppers, secateurs, screwdrivers, knives and hand saws in good condition.
-
Lifting equipment, e.g. lift trucks and lifting slings LOLER certified.
-
Other equipment, e.g. ladders in good condition.
-
Safe use, handling, storage and transport of substances that may be hazardous to health, eg pesticides, weed killers and fertilisers
-
Training e.g. LANTRA, BALI, BPCA, chainsaw, rope access, plant use, application of pesticides and herbicides, water safety
-
Safe access and egress
-
All persons working within 3m of unguarded water wearing self-inflating lifejackets
-
All persons working in water wearing water-safe PPE
-
Water rescue arrangements adequate
-
Waste handling and disposal
-
Work at height, e.g. cutting hedges
-
Specialist tree work at height (rope work)
-
General PPE
-
Warning signage
-
Protection of the public
-
Grounds maintenance next to traffic routes is adequately controlled
-
Noise levels
-
Vibration control
-
RPE
-
Specialist PPE for chainsaw works
-
Safe use of specialist plant including ride-on mowers and chippers
-
Ride-on plant not being used on slopes in excess of manufacturers maximum permitted slope angle
-
Grass cutting - Pre-cut inspection of areas to be cut for obstructions, cables, holes etc.
-
Team has access to suitable expertise and specialist knowledge, including environmental regulations
-
Sub-contractors working to Stonbury standards