Information

  • Audit Title

  • Document No.

  • Conducted on

  • Prepared By

  • Personnel

  • Location

General Condition on Day of Visit

  • GENERAL SITE SAFETY

  • WEATHER

  • SITE CONDITIONS

  • TRAFFIC MANAGEMENT

Environmental - Earthworks, Excavation.

  • Is there provision to minimize dust / mud from leaving the site.

  • Do stockpiles have adequate silt runoff protection.

  • Are environmental No Go areas fenced where required.

  • Are silt traps in place to prevent silt build up in previously installed drainage system.

UTILITY ACTIVITY ON SITE

1.0 UTILITY ACTIVITY ON SITE : SEWER, WATER, ELECTRICAL, TELSTRA / NBN.

  • Sewer Sub Contractor Onsite

  • Location of Works

  • WATER Subcontractor on Site

  • Location of Works

  • Electrical Subcontractor on Site

  • Location of Works

  • TELSTRA Subcontractor on Site

  • Location of Works

Other Activities

1.0. ACTIVITY : DEMOLITION, STRIPPING, BULK EARTHWORKS, ROAD BOXING, LOT GRADING, TOPSOILING

  • Demolition / Stripping status

  • Select date

  • LOCATION

  • Bulk Earthworks, Cut / Fill status

  • Select date

  • LOCATION

  • Road Boxing Status

  • Select date

  • LOCATION

  • Grading / Topsoiling Status

  • Select date

  • LOCATION

Drainage Works

2.0. Drainage Works - Trenching, Pipelaying, Pits & Backfill.

  • Drainage Works Status

  • Select date

  • Is the pipe drainage crew on site.

  • Name of Drainage Contractor

  • Is there pipe & pits on site.

  • Storage Location of Pit & Pipes

  • Are trench widths adequate for pipe size/ type

  • Location of Trench

  • Is the bedding material & thickness within tolerance and being compacted correctly

  • Location of Bedding

  • Are pipes being installed in accordance with design specification and manufacturers recomendations.

  • Location of Works

  • Are clearances to other services being maintained as per specification.

  • Does trench backfill material comply with standard drawings and specifications

  • Location of Works

  • Is the surface finish of pit wall & base satisfactory.

  • Location of Pit ID. Number

  • Step irons - required for all pits greater than 900mm depth. 300mm centres at 500mm below top of pit

  • Location of Works

  • Are lids / covers as per design and correct rating.

  • Location of Works

Pavement

3.0. ACTIVITY : PAVEMENT

  • Subgrade excavation - visual check of line and level<br>Measurement by tape & string line of correct set out as required

  • Location

  • Subgrade preparation - check compaction using approved vehicle to proof roll the subgrade.

  • Location

  • Subgrade has Soft spots and or areas that require rework

  • Location

  • SUBGADE HOLD POINT - subgrade layer must be approved prior to commencement of BASE LAYER

  • Location

  • Works Required

  • Base layer - Class 3 crushed rock <br>Check class 3 for compaction and level using approved vehicle to proof roll and string line.

  • Does pavement material comply with plans, standard drawings & specifications.

  • Is Class 3 at correct depth

  • Location

  • AG drain installation - check for depth below subgrade and trench width by tape<br>Check backfill material (screenings)<br>No sock on 100mm AG

  • Location

  • Service conduit installation - conduits to have min 250mm cover below pavement boxing - measurement by tape

  • Location

  • Trenches under pavement and kerb & channel back filled with class2 - visual inspection and measurement of correct depth

  • Base layer has Soft spots and or areas that require rework

  • Location

  • BASE LAYER HOLD POINT<br>Base layer must be approved prior to commencement of sub base layer

  • Location

  • Works Required

  • Sub base layer - class 2 crushed rock<br>Check class 2 for compaction and level using approved vehicle to proof roll and string line for correct level.<br>Sub base can only commence after sufficient curing of adjoining k/c and backing up of nature strip to rear of kerb.

  • Does pavement material comply with plans, standard drawings & specifications.

  • Is Class 2 at correct depth

  • Location

  • Sub Base layer has Soft spots and or areas that require rework

  • Location

  • SUB BASE LAYER HOLD POINT<br>Sub base layer must be approved prior to commencement of asphalt layer

  • Location

  • Works Required

  • Is the weather suitable for priming or placing asphalt?

  • Asphalt Base Course<br>Application of asphalt to be during temperatures above 12 degrees C and dry

  • Does pavement material comply with plans, standard drawings & specifications.

  • Is Asphalt at correct depth

  • Location

  • Wearing Course Asphalt Status<br>Application of asphalt to be during temperatures above 12 degrees C and dry

  • Does pavement material comply with plans, standard drawings & specifications.

  • Is Wearing Course at correct depth

  • Location

Concrete Works

4.0 Works - Concrete

  • Are weather conditions suitable for placing concrete.

  • Kerb & Channel base preparation - measure by tape depth as per pavement design

  • Location

  • Is boxing depth and crushed rock bedding as per specification

  • Location

  • Grade of kerb & channel - check string line for correct alignment and level

  • Location

  • Is kerb & channel type and profile correct

  • Location

  • Kerb & channel line & finish - visual inspection for compliance to Council standards and acceptable finish

  • Location

  • Are kerb markings for services being installed.

  • Location

  • Crossing Laybacks base preparation - measure by tape depth as per Knox Standard

  • Location

  • Is crushed rock bedding as per specification

  • Location

  • Layback finish - visual inspection for compliance to Council standards and acceptable finish

  • Location

  • Pit lintels - visual check of correct line & height

  • Location

Footpaths & Shared Path

5.0. Footpaths/Shared Paths

  • Base for paths - measurement by tape

  • LOCATION

  • Path preparation - visual inspection of boxing for alignment<br>Measure width of path to Knox standards, grade and crossfall

  • LOCATION

  • Path finish - visual inspection for compliance to Council standards and acceptable finish

  • Location

  • Pram crossings - visual inspection and measurement to standards

  • LOCATION

  • Pram Crossing finish - visual inspection for compliance to Council standards and acceptable finish

  • Location

  • Reinforcement mesh - visual inspection min F72 & correctly placed

  • Location

  • Footpath pour - correct expansion joint, spacing and finish

  • Location

  • Tactile paving to DDA compliance - visual inspection to design/standards

Nature Strips

6.0. Nature strips

  • Nature strip - visual inspection depth of topsoil 100mm

  • Topsoil levelled and flush with adjoining footpath

  • Nature strip seeded

Rockworks

7.0. ACTIVITY : ROCKWORK / MISCELLANEOUS

  • Rock Wall Status

  • Rock Beaching Status

  • Rock Endwall / Headwall Status

  • Porphrey Stone Paving Status

7.1. Works - Rockwork, Miscellaneous

  • Are rocks suitable for intended purpose and of appropriate size/ grading.

  • Are rocks sitting on concrete cushions over pipe ends

  • Are rocks being placed to specification and grouted as required.

  • Is reinforcing being installed as per specification.

Comments

8.0. COMMENTS / PROGRESS / INSTRUCTIONS.

  • PHOTOS

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.