Information
-
Audit Title
-
Document No.
-
Conducted on
-
Prepared By
- Ian Lochhead
- Tino Pegoraro
- Nathan Hasanknolli
- Bruce Bremner
- Other
-
Personnel
-
Location
General Condition on Day of Visit
-
GENERAL SITE SAFETY
- COMPLIANT
- NON-COMPLIANT
-
WEATHER
-
SITE CONDITIONS
- DUSTY
- DRY
- MUDDY
- WET
-
TRAFFIC MANAGEMENT
Environmental - Earthworks, Excavation.
-
Is there provision to minimize dust / mud from leaving the site.
-
Do stockpiles have adequate silt runoff protection.
-
Are environmental No Go areas fenced where required.
-
Are silt traps in place to prevent silt build up in previously installed drainage system.
UTILITY ACTIVITY ON SITE
1.0 UTILITY ACTIVITY ON SITE : SEWER, WATER, ELECTRICAL, TELSTRA / NBN.
-
Sewer Sub Contractor Onsite
-
Location of Works
-
WATER Subcontractor on Site
-
Location of Works
-
Electrical Subcontractor on Site
-
Location of Works
-
TELSTRA Subcontractor on Site
-
Location of Works
Other Activities
1.0. ACTIVITY : DEMOLITION, STRIPPING, BULK EARTHWORKS, ROAD BOXING, LOT GRADING, TOPSOILING
-
Demolition / Stripping status
-
Select date
-
LOCATION
-
Bulk Earthworks, Cut / Fill status
-
Select date
-
LOCATION
-
Road Boxing Status
-
Select date
-
LOCATION
-
Grading / Topsoiling Status
-
Select date
-
LOCATION
Drainage Works
2.0. Drainage Works - Trenching, Pipelaying, Pits & Backfill.
-
Drainage Works Status
-
Select date
-
Is the pipe drainage crew on site.
-
Name of Drainage Contractor
-
Is there pipe & pits on site.
-
Storage Location of Pit & Pipes
-
Are trench widths adequate for pipe size/ type
-
Location of Trench
-
Is the bedding material & thickness within tolerance and being compacted correctly
-
Location of Bedding
-
Are pipes being installed in accordance with design specification and manufacturers recomendations.
-
Location of Works
-
Are clearances to other services being maintained as per specification.
-
Does trench backfill material comply with standard drawings and specifications
-
Location of Works
-
Is the surface finish of pit wall & base satisfactory.
-
Location of Pit ID. Number
-
Step irons - required for all pits greater than 900mm depth. 300mm centres at 500mm below top of pit
-
Location of Works
-
Are lids / covers as per design and correct rating.
-
Location of Works
Pavement
3.0. ACTIVITY : PAVEMENT
-
Subgrade excavation - visual check of line and level<br>Measurement by tape & string line of correct set out as required
-
Location
-
Subgrade preparation - check compaction using approved vehicle to proof roll the subgrade.
-
Location
-
Subgrade has Soft spots and or areas that require rework
-
Location
-
SUBGADE HOLD POINT - subgrade layer must be approved prior to commencement of BASE LAYER
-
Location
-
Works Required
-
Base layer - Class 3 crushed rock <br>Check class 3 for compaction and level using approved vehicle to proof roll and string line.
-
Does pavement material comply with plans, standard drawings & specifications.
-
Is Class 3 at correct depth
-
Location
-
AG drain installation - check for depth below subgrade and trench width by tape<br>Check backfill material (screenings)<br>No sock on 100mm AG
-
Location
-
Service conduit installation - conduits to have min 250mm cover below pavement boxing - measurement by tape
-
Location
-
Trenches under pavement and kerb & channel back filled with class2 - visual inspection and measurement of correct depth
-
Base layer has Soft spots and or areas that require rework
-
Location
-
BASE LAYER HOLD POINT<br>Base layer must be approved prior to commencement of sub base layer
-
Location
-
Works Required
-
Sub base layer - class 2 crushed rock<br>Check class 2 for compaction and level using approved vehicle to proof roll and string line for correct level.<br>Sub base can only commence after sufficient curing of adjoining k/c and backing up of nature strip to rear of kerb.
-
Does pavement material comply with plans, standard drawings & specifications.
-
Is Class 2 at correct depth
-
Location
-
Sub Base layer has Soft spots and or areas that require rework
-
Location
-
SUB BASE LAYER HOLD POINT<br>Sub base layer must be approved prior to commencement of asphalt layer
-
Location
-
Works Required
-
Is the weather suitable for priming or placing asphalt?
-
Asphalt Base Course<br>Application of asphalt to be during temperatures above 12 degrees C and dry
-
Does pavement material comply with plans, standard drawings & specifications.
-
Is Asphalt at correct depth
-
Location
-
Wearing Course Asphalt Status<br>Application of asphalt to be during temperatures above 12 degrees C and dry
-
Does pavement material comply with plans, standard drawings & specifications.
-
Is Wearing Course at correct depth
-
Location
Concrete Works
4.0 Works - Concrete
-
Are weather conditions suitable for placing concrete.
-
Kerb & Channel base preparation - measure by tape depth as per pavement design
-
Location
-
Is boxing depth and crushed rock bedding as per specification
-
Location
-
Grade of kerb & channel - check string line for correct alignment and level
-
Location
-
Is kerb & channel type and profile correct
-
Location
-
Kerb & channel line & finish - visual inspection for compliance to Council standards and acceptable finish
-
Location
-
Are kerb markings for services being installed.
-
Location
-
Crossing Laybacks base preparation - measure by tape depth as per Knox Standard
-
Location
-
Is crushed rock bedding as per specification
-
Location
-
Layback finish - visual inspection for compliance to Council standards and acceptable finish
-
Location
-
Pit lintels - visual check of correct line & height
-
Location
Footpaths & Shared Path
5.0. Footpaths/Shared Paths
-
Base for paths - measurement by tape
-
LOCATION
-
Path preparation - visual inspection of boxing for alignment<br>Measure width of path to Knox standards, grade and crossfall
-
LOCATION
-
Path finish - visual inspection for compliance to Council standards and acceptable finish
-
Location
-
Pram crossings - visual inspection and measurement to standards
-
LOCATION
-
Pram Crossing finish - visual inspection for compliance to Council standards and acceptable finish
-
Location
-
Reinforcement mesh - visual inspection min F72 & correctly placed
-
Location
-
Footpath pour - correct expansion joint, spacing and finish
-
Location
-
Tactile paving to DDA compliance - visual inspection to design/standards
Nature Strips
6.0. Nature strips
-
Nature strip - visual inspection depth of topsoil 100mm
-
Topsoil levelled and flush with adjoining footpath
-
Nature strip seeded
Rockworks
7.0. ACTIVITY : ROCKWORK / MISCELLANEOUS
-
Rock Wall Status
-
Rock Beaching Status
-
Rock Endwall / Headwall Status
-
Porphrey Stone Paving Status
7.1. Works - Rockwork, Miscellaneous
-
Are rocks suitable for intended purpose and of appropriate size/ grading.
-
Are rocks sitting on concrete cushions over pipe ends
-
Are rocks being placed to specification and grouted as required.
-
Is reinforcing being installed as per specification.
Comments
8.0. COMMENTS / PROGRESS / INSTRUCTIONS.
-
PHOTOS