Subdivision Daily Inspection
-
Site conducted/Subdivision
undefined
-
-
Conducted on
-
Prepared by
-
Location
-
Stage
-
Sub stage
-
Council reference
-
Inspection type
- Preliminaries
- Bulk earthworks
- Drainage
- Sewer
- Conduits
- Concrete
- Pavement - Crushed rock
- Pavement - Asphalt/Bitumen/Concrete
- rock beaching
- Practical completion
-
Preliminaries Sub Inspection
- Environmental protection measures in place prior to works commencing CHP
- Traffic management vehicle/Pedestrian guidance prior to works commencing in place CHP
- Site safety measures in place prior to works commencing CWP
- Pre-commencement meeting prior to works commencing CHP
-
Bulk Earthworks Sub Inspection
- Grubbing and clearing tree protection fencing after installation CHP
- Removal of native trees prior to removal CHP
- Boxing road formation prior to covering CHP
- Sub grade (non-expansive) Proof rolling,compaction prior to placement of construction layer test results (as required), pavement (expansive) levels and shape CHP
- Sub grade improvement treatment of soft areas prior to back filling CHP
- Capping layer proof rolling, test results, prior to placement of levels and shape pavement CHP
- Formation grading and levels prior to top soiling CHP
- Nature strips grading and levels prior to top soiling CHP
-
Drainage Sub Inspection
- Drainage pipes foundation bed prior to laying of pipes CWP
- Levels, alignment, jointing, prior to back filling and haunching 146 engineering design construction manual STAGE REQUIREMENT TIMING TYPE CHP
- Backfill after Backfilling CWP
- Pits and structures formwork, bedding and prior to pouring concrete reinforcement CHP
- Backfilling prior to pavement CHP
- Agricultural drains levels and alignment prior to back filling CHP
- Electricity pole installation during installation CWP
- House drains levels and alignment prior to backfilling CHP
- Pipe connection at outlet prior to back filling CHP
- Raingardens media material test results prior to placement of material CHP
- Culverts levels and alignment prior to placemnt CHP
-
Sewer Sub Inspections
- Sewer trench compaction test results after back filling CWP
-
Conduit Sub Inspection
- Road crossing levels and alignment prior to back filling CHP
- Footpath/nature strip levels and alignment prior to back filling CHP
-
Concrete Sub Inspection
- Concrete curing & curing method and during work compaction application CWP
- Kerb and channel proof roll bedding prior to placement of kerb and channel CHP
- Alignment prior to pouring CHP
- Backing up prior to to placement of pavement CWP
- Footpath bedding, alignment, prior to pouring concrete reinforcement, jointing CHP
- Vehicle crossings bedding, levels, prior to pouring concrete reinforcement and dowels CHP
- Thresholds and islands bedding, levels, prior to pouring concrete reinforcement and dowels, CHP
-
pavement crushed rock Sub Inspection
- Lower sub base course levels and shape, prior to to placement of upper roll and compaction test sub base course CHP
- Upper base course(s) levels and shape, proof roll prior to placement of each layer and compaction base course test CHP
- base course levels and shape, proof roll prior to placement of and compaction test asphalt/seal CHP
-
pavement asphalt Sub Inspection
- Preparation of pavement sweeping, cleaning, removal prior to placing seal or surface of loose material asphalt CHP
- Seal sweeping, paper protection prior to placement of seal CHP
- Asphalt base course depth, spread rate , during works temperature, compaction CHP
- Asphalt immediate depth, spread rate, during works course temperature, compaction CHP
- Asphalt wearing course depth, spread rate, during works temperature, compaction CHP
- Concrete pavements formwork, reinforcement prior to pouring and jointing CHP
- Linemarking spotting out prior to linemarking CHP
-
Rock beaching Sub Inspection
- 9 bedding level and compaction prior to placing rock beaching CHP
-
PC Sub Inspection
- WSUD treatments results to demonstrate prior to commencement raingardens and of defects liability period. bioretention systems built to design and functioning CHP
- Quality, access and public practical completion prior to consenting to safety inspection commencement of the defects liability period CHP
Comments
-
Comments
Attachements
-
Photos/Files
Sign off
-
Cardinia Shire Council Representative
-
Role