General Information

  • Client / Developer

  • Project reference name and Job Number
  • Date

  • Prepared by

  • Location

Substation Details

  • Substation Name

  • DNO / IDNO

  • LV network owner

Sub station Base

  • Is substation base correct to design

  • Is Base in correct location

  • Does base sit above finished ground level to prevent water ingress

  • Does substation base have GRP grating down and cut correctly

  • Is GRP grating support bar in place

  • Is base Level ( Photo with spirit Level )

  • Has all cable entry points into base been foam filled / capped to prevent gas entering the substation

  • Has Cable entry pit inside sub station been filled with sand

  • Has base bolt locating holes been filled with foam and grout

  • Has base joints been filled with foam and grey silicone

Substation Housing

  • GRP - Make and Model

  • Brick Built

  • Is all external signage in place

  • Are all external locks in place

  • Are all metal structures bonded and connected to earth

  • Has GRP anchor bolts been installed in all areas not just corners

  • Has GRP had silicone bead around to prevent water ingress

  • Installation/Mounting of RTU (complete ready for commissioning)

  • Has SMPL been installed

Earthing

  • Is it a hot or cold site

  • Installation of external earthing around S/S to design

  • Has all corners of substation had earth rods installed

  • Does HV Earth run out with the HV cable

  • Installation of internal earthing (as per design LV Cabinet, TX & HV RMU / RTU Earthed connected)

  • If Brick built are all door frames and vents bonded

  • Are all Earths labelled at earth bar

  • Earth test complete (results recorded / photos provided)

  • Are all HV earths connected

  • Is Earthing Combined or seperate

HV

  • Are HV terminations complete and how many HV cables enter TX

  • Sheath Test 5kV (please note and add photo)

  • Are all insulated boots installed

  • Are end terms Torqued to correct spec

  • Are Cable protection boxes bolted in place

  • Are all phases correct

  • TX tap setting

LV

  • LV terminations (confirm number installed)

  • Standard / Nonstandard rotation

  • Installation of LV SWA from LV cabinet into SL and RTU if required cut-out

  • LV dead tests complete (please note results in comments)

  • Voltages

  • LV protection settings entered

  • Live Testing ELI result in ohms

As Laids

  • Are As Laids complete - LV

  • Are As Laids complete - HV

General

  • Comments

  • Is Sub Station Compliant

  • Completed by

  • Signature

  • Company

  • Date

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.