Information
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Does anyone on the jobsite need training on any tools?<br>
-
Is there any material on backorder?
-
Is there any material holding up progress?
-
Is the electrical service energized?
-
Is the Gas service live?<br>
-
Is the phone line ran for building occupancy?
-
Are coordination drawings complete?
-
Are coordination drawings accurate?
-
Are other trades holding up progress anywhere?
-
Are other trades costing us production?
-
Have any tradesmen been pulled without you being notified?
-
Was a full job material buyout done?
-
Have you verified equipment delivery dates work with the schedule?
-
Have you verified any equipment with water connections are coordinated for left or right side connections?
-
Have you coordinated equipment access locations to verify that they are free and clear of obstructions?
-
Have you established a sequence as to which DEEM trades need to be installed first to reach maximum production?
-
Did you use the same size pipe as indicated on the drawings to temporary the storm drains?
-
Do you have adequate manpower?
-
Can any manpower be pulled from the project?
-
Has the Superintendent for the GC impacted the job for the better?
-
Has the Superintendent for the GC impacted the job for the worse?
-
Are you keeping record drawings daily? If so, please show me.
-
Are you having the field fill out timecards daily? Please show me.
-
Are you having the field fill out sign in sheets with actual times leaving and arriving? Please show me.
-
Do you have all of the DEEM provided tools required to perform the job most efficiently?
-
Does everyone in the field have the required hand tools?
-
Is there any welding being performed on stands?
-
Are all of the welds being performed onsite position welds?
-
Are all bathroom carrier groups being constructed in the shop?
-
Did fittings come from the shop sorted?
-
Have you performed 30% of the hours on the job in the fabrication shop?
-
Have all of your RFI's been responded to?
-
Are all of your RFI's in writing?
-
Is the punch list complete?
-
Does the Project Manager attend progress meetings?
-
Have you received approved submittals for all equipment and material?
-
Are the most current drawings onsite? Verify with the PM.
-
Is your combined labor rate tracking with the estimate?
-
Do you have an equipment delivery log from the Project Manager?
-
Does the sanitary invert leaving the building match the drawing?
-
Is duct testing required?
-
Do you have the duct sealer spraying machines onsite?
-
Do all lifts have non marking tires and diapers on them if required?
-
Do all men have booties to wear to protect finished surfaces?
-
Are all finished surfaces being protected adequately?
-
Are all hangers being fabricated in the shop?
-
Is any of the pipe required to be painted?
-
Does any of the pipe require roller hangers?
-
Do you have all rental equipment onsite documented? Show me.
-
Does the job require hard hats?
-
Safety glasses?
-
Gloves?
-
High visibility uniforms(vests)?
-
Do you have the most up to date construction schedule?
-
Do we have any subcontractors on this project. If so, who are they?
-
Are you securing tools while the employees are at lunch?
-
Is the lunch time consistent with all of the DEEM trades?
-
Are you getting approval for all overtime from the project manager?
-
Are you verifying that all tools are accounted for and in the correct location in the gang boxes at the end of each working day?
-
Are you enforcing and maintaining the Jobsite clean up daily?
-
Do you have any temporary labor onsite?