Information

  • Conducted on

  • Audit No

  • Auditee

  • Add signature

  • Auditor

  • Add signature

  • Audit Type

  • Survey Type

  • Building type and brief description

  • Site Address

Survey Planning

  • Has the job been set up on tracker prior to the Survey taking place ?

  • Has a pre survey planning document been created by the project manager ?

  • Has any of the requested desk top study information requested by the PM I.e building plans ,any previous asbestos history, permit to works been provided ? Auditor to check for evidence the PM has attempted to find the relevant info

  • Is the scope for the project accurately described ?

  • Where required has the PM organised isolations , building contractors , lift engineers or any access equipment where required ?

  • Does the pre survey planning document contain the name of the client agreeing the project and if so is there evidence that the client has actually agreed the scope of works ?

  • Has a suitable risk assessment been created and issued ? Where extra risks have been identified by the surveyor have suitable control measures been organised by the PM / Surveyor

  • Is the audited suitably competent / trained for all aspects of work being undertaken , from WAH to surveying skill set

  • In the opinion of the auditor is the scope of works suitable for the planned works ? Ie level of consultation

Health and Safety

  • Has a risk assessment been completed ,signed , reviewed and updated where required

  • Is the RPE in good condition , clean and suitably identified as the surveyors mask ? Is the surveyor clean shaven and can demonstrate a good face fit ?

  • Has the surveyor filled in his monthly exposure sheet and equipment records / ladder checks and are they up to date ?

  • Is all required PPE on site ie Hard hats ,Boots, Gloves, HI Viz jacket, goggles ear defenders and disposable overalls and booties if required ?

  • Does the surveyor have copies of all relevant training records available and are they in date ? P402 ,CSS ,face fits and WAH etc

Site Equipment

  • Suitable kit box and sample container to segregate tools and samples ?

  • Step ladders - Are they referenced , in good condition and has it been checked by someone competent in the past 6 months ?

  • Any other access equipment checked and documented as safe to use ? Ie MEWPS or Scaffolding

  • Digital camera or camera on tablet ?

  • Tablet available or data sheets being used ?

  • Suitable torch and spare batteries available ?

  • Pens , pencils , ruler , and correction fluid available ( fluid for diagrams only ) ?

  • Resealable sample bags - various sizes available ?

  • Core borers / core samplers available ?

  • Tape and sealant for repairing sample points ?

  • Pliers ( Flat nosed and non serrated ideally ) ?

  • Hammer ?

  • Hand held sprayer ( with PVA or surfactant ) ?

  • Knife with spare blades ?

  • Screw drivers both pos and flat head ?

  • Chisels ?

  • Magnet ?

  • Polythene sheet and / or Asbestos waste bags of approached type ?

  • Wet wipes ?

  • Sample point stickers and labels ?

  • Asbestos warning stickers ?

  • Is a tool belt available ?

  • Warning signs ?

  • Any additional required equipment I.e lanterns and crawl boards or hype where required ?

  • Hsg 264 and other relevant guidance documents ?

  • Refurb / Demo - Sledge hammer / lump hammer ?

  • Refurb / Demo - H type vacuum ?

  • Refurb / Demo - Crowbar ?

  • Refurb / Demo - Plasterboard saw ?

Surveying methodology

  • Logical planning of survey ( walk round , site plans and info review )?

  • Has the surveyor understood the scope and reviewed / amended it where required ?

  • Was sampling conducted correctly ?

  • Was the size of samples taken and frequency adequate for the materials being sampled ?

  • Have any samples that have been cross referenced been done so correctly and without compromising the integrity of the survey ?

  • Correct labelling of sample bags ? Include check of previous samples

  • Have all suspect materials been identified , Surveyor to have strong evidence a material isn't likely to contain asbestos to not sample or reference it ?

  • Digital photographs of all sample points taken and of suitable clear quality ?

  • Has a front photo been taken and has the building description been detailed correctly ?

  • Tracker - Has the survey been conducted on a room by room basis and all have individual room numbers ?

  • Envacs - Has the survey been conducted on a room by room basis and are all item points referenced correctly in order ?

  • Has the survey been conducted in logical systematic manor ie top to bottom , walls amd them floors , prodding and knocking of materials routinely carried out ?

  • Has the surveyor accessed all relevant areas for the survey type or scope ? Breaking in frequency or accessing all areas for a management survey

  • Have any genuine non accessed areas been recorded correctly and the reason justified in the notes . Quizz whethr the PM or client has been contacted to arrange access ?

  • Has site been left in a good tidy state where required and fit for reoccupation ?

  • Have the building plans been marked up correctly with sample points , room numbers , material extents and relevant site description info ?

  • Have material assessments been assessed correctly ?

  • Are recommendations made by the surveyor suitable ?

  • Rest of data inputted correctly ?

  • Is any applicable priority scoring correct ? What details are in place to ensure done accurately

Types of materials sampled

  • Boards

  • Thermal insulation

  • Spray coatings

  • Composites

  • Textile ,rope and yarns

  • Papers, cardboard and gaskets

  • Decorative Coatings

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.