Construction Details
-
Quilpie Shire Council, PO Box 50 Quilpie QLD 4480, Phone 07 4656 0500, ABN:53 680 434 639
-
Principal Contractor
- Quilpie Shire Council
- Contractor
- Sub-contractor
- Other
-
Details if QSC is not the Principal Contractor
-
Document Number:
-
Work Location
-
Select High Risk Construction Work
- Risk of a person falling more than two metres (Note: in some jurisdictions this is 3 metres)
- Likely to involve disturbing asbestos
- Working in a shaft or trench deeper than 1.5m or a tunnel
- Work on or near chemical, fuel or refrigerant lines
- Tilt-up or precast concrete elements
- Work in areas with artificial extremes of temperature
- Work on a telecommunication tower
- Temporary load-bearing support for structural alterations or repairs
- Use of explosives
- Work on or near energised electrical installations or services
- Work on, in or adjacent to a road, railway, shipping lane or other traffic corridor on use by traffic other than pedestrians
- Work in or near water or other liquid that involves a risk of drowning
- Demolition of load-bearing structure
- Work in or near a confined space
- Work on or near pressurised gas mains or piping
- Work in an area that may have contaminated or flammable atmosphere
- Work in an area with movement of powered mobile plant
- Diving work
- Other
-
Select Construction Work Activity
-
Select Road Maintenance Work Activities
-
Select Concrete Work Activities
-
Select Town Services Activities
-
Select Sign Crew Activities
-
Do you require a spotter - working in an exclusion zone
-
Person responsible for SWMS:
-
Date SWMS created:
-
Prepared by
Inspection
-
What measures are in place to ensure compliance with the SWMS?
- Policies
- Procedures
- SOP's
- Induction Training
- Toolbox Talks
- Pre Start Meetings
- SWMS provided & discussed with all workers at the worked and have signed the SWMS
- Supervision by experienced supervisor
- Other (list in notes)
Risk Management
-
Selecting control measures
1. Eliminate the risks, so far as is reasonable practicable.
2. If this is not reasonably practicable, minimise them so far as reasonably practicable by:
• substituting the hazard
• isolating the hazard
• implementing engineering controls.
3. If the risk still remains, minimise it further by implementing administrative controls.
4. If the risk still remains, minimise it by ensuring the provision and use of suitable personal protective equipment (PPE). -
Select High Risk powered mobile plant used.
-
Are all operators Licenced or competent to operate the required plant?
-
List any hazardous chemicals if used on site
-
Are SDS (Safety Data Sheets) available
-
Are supervision arrangements organised for inexperienced and young workers?
-
List the work tasks/process in a logical order
-
Select the hazards and risks (Identify & list the hazards and risks that may cause harm to workers or the public) Add additional hazards/risk in notes
-
List any other hazards and risks
-
List the control measures to control the hazards & risks? (Describe what will be done to control the risk. What will you do to make the activity as safe as possible?)
-
If required select the appropriate PPE
-
Rate the likelyhood of exposure
-
Rate the risk level with controls in place
-
Is it safe to proceed?
-
Date SWMS received by workers:
Review: all workers involved in this high-risk construction work have been provided with the relevant information and instruction that will assist them to understand and implement the revised SWMS
This SWMS has been reviewed for this particular construction project. (Add all worker's names & signatures below)
-
Manager/Supervisor
-
Select name of workers
-
Signatures
-
Date
-
Name of contractors
-
Signatures
-
Name of person completing this SWMS
-
Reviewed by:
-
Review date:
-
Additional Notes: