Information
-
Site conducted
-
Person & Position of person carrying out the inspection
-
Site Address
-
Location of Scaffold (i.e Front, Side or Rear of property)
-
Conducted on
-
Client
-
Name of Company that have erected the scaffold
Design
-
Is there a permit to work in place (close working) for erection & dismantle?
-
Is there a fire extinguisher in the vehicle?
-
If present, is the fire extinguisher within it's service date?
-
If the answer is NO, a new extinguisher must be brought to site before end of audit
-
Has a POWRA been completed for the job?
-
Are there sufficient cleaning materials in the van?
-
Does the van have sufficient face masks
-
Is there a first aid kit in the van?
-
Are there TG20 Compliance sheets or design drawings available?
-
Have the Scaffolds been built in accordance with the compliance sheets or design provided?
Footings
-
Have base plates been used?<br><br>Note: base plates should typically steel base and 150mm x 150mm
-
Are sole boards in place and at the correct dimensions? <br><br>Note: 450mm x 220mm
Standards
-
Are the standards vertical and within the allowed erection tolerance?<br><br>Note: tolerance of 20mm in every 2 meters of height to a maximum overall deviation of 50mm
-
Are the joints staggered?<br><br>Note: standards should be staggered so that adjacent standards are not joined within the same lift.
Ledgers
Transoms
-
Are the transoms of the correct length and do they protrude 25mm past the coupler?
-
Are the transoms spaced correctly on boarded and non boarded lifts?
-
Is there a transom fitted within 300mm of the node point at ledger braced standards?
The scaffold
-
Does the scaffold have protection to stop falls at all openings? Such as gates or a pivoting rail
Ledger, Façade and Plan Bracing
-
Does the scaffold have a scaff tag on all access points, filled out correctly?
-
Is the scaffold tag within the required 7 day period of inspections
-
Is all bracing set at the correct intervals?<br><br>Note: Façade bracing is required on every lift, and every six bays. <br>Ledger bracing should be fitted to every third pair of standards.
-
Is all bracing connected using load bearing fittings?<br><br>Note: load bearing couplers will be manufactured to EN74 standard and marked to either Class A or B. Couplers manufactured to BS1139 are also acceptable.
Ties
-
Have all ties been set at the frequency of the compliance sheets or design drawing?<br><br>Note: Ties should be set and tested per the TG20:13 compliance sheet. All ties should be tied to the front and back standards, using load bearing couplers. Ideally ties will be fixed at ledger braced frame.
-
Have anchor ties been tagged
-
Have pull tests been carried out?
Boarded Lift
-
Are the boards in good condition with no excessive splits, or notches?<br><br>Note: all boards should be 38mm thick. No boards should show signs of ill treatment, warping, abuse or decay. All should contain a nail plate or end hoop. no slit should exceed 225mm in length. No cuts should be deeper than 2mm.
-
Is the working platform free from gaps and trip hazards?
-
Are the boards supported by at least 50mm past their last support and not exceeding 150mm?
Handrails, Toe Boards & Brick Guards
-
Are Handrails and toe boards fitted where there is a risk of persons or materials falling?
-
Are the handrails at the correct height 950mm with a gap not exceeding 470mm between the toe board and the handrails?
-
Are the handrails and toe boards correctly fixed (toe boards over 2 standards) and are the joints not in the same bay as the ledgers below?<br><br>Note: toe boards should be fixed inside of standards with a putlog coupler or a variety of proprietary clips. Guard rails should be positioned inside of guard rails, and connected to each standard with a right angle coupler. The lower guard rail should be a maximum of 470mm above the toe board, with the top rail a minimum of 950 from above the decking.
-
Are the brick guards/netting in good condition and correctly secured?
Ladder/ stair access
-
Are the ladders correctly secured with either lashing or single fittings that wrap around the stiles?
-
Do the ladders protrude at least 1 meter above the working platform? where this is not possible is there an adequate handhold provided?
-
Are the stair treads fixed securely with no movement?<br>
-
Are all the Half landings complete with Handrails and toe boards?
Housekeeping
Sign Off
-
Please list any matters of issues arising from inspection
-
Details of any further action considered necessary
-
Can work be carried out safely?
-
Who has been informed?
-
Name of person receiving report
-
Signature of person completing the report