Title Page

  • Conducted on

  • Prepared by

  • Location
  • To view our Loss Prevention Standard that supports this checklist, please view the following link : https://broker.aviva.co.uk/documents/view/aviva_temporary_shutdown_mothballing_construction_sites_lps.pdf

Temporary Shutdown and Mothballing of Construction Sites

Planning to Shutdown/Mothball

  • 1. Have you notified your insurer and insurance broker that the site will cease operations for an extended period?

  • 2. Have you updated your Project/Site risk assessment to reflect that the site is beiing shutdown or mothballed?

  • 3. Has the Project/Site Emergency Response Plan been updated?

  • 4. Has a Project Recommencement Plan been prepared?

  • 5. Are reviews/updates of the Project Risk Register being completed as required?

Security Aspects

  • 6. Will the project/site remain securely enclosed by an adequate and robust security fence throughout the period of shutdown/mothballing?

  • 7. Are you providing remotely monitored CCTV systems covering the site perimeter and any critical/vulnerable internal areas that are connected to an approved 24hr manned remote monitoring facility/Alarm Receiving Centre?

  • 7.1 Do CCTV systems feature PIR movement sensors supported by a "voice challenge" facility provided from the CCTV control room.

General Housekeeping & Storage

  • 8. Are areas used for materials/equipment storage away from areas of the site that are at risk from flooding?

  • 9. Have you been able to raise/elevate equipment and materials off the ground?

  • 10. Have you removed all waste materials from site?

  • 11. Have you minimised storage within all buildings wherever possible, especially combustible materials?

  • 12. Have fuel oils and gas cylinders been either removed from site or otherwise stored in an appropriate secure and external area?

  • 13. Have you been able to isolate all non-essential utilities and services?

  • 14. Will intruder alarms and any automatic fire alarm systems remain operational and connected to a 24 hr manned approved Alarm Receiving Centre?

Construction Plant and Machinery

  • 15. Has construction plant/equipment been either removed from site or been parked or stored in a secure compound outside of a flood risk zone?

  • 16. Have you removed from site any keys or batteries from large items of construction plant to prevent them from being stolen?

  • 17. Where cranes are left on site, have you ensured that jibs on mobile cranes have been lowered and that any tower cranes have been left so that they ‘free slew’?

  • 18. Are arrangements in place for the continuation of any required equipment maintenance or statutory inspections?

Installed Electrical and Mechanical Equipment

  • 19. Have any electro-mechanical installations been shutdown and/or de-energised in accordance with manufacturers instructions and recommendations?

  • 19.1. Are plant rooms competely sterile of combustible materials and secured?

  • 19.2. Will any fixed fire protection of any electro-mechanical installations remain operational?

  • Please arrange for the installation to be shutdown/de-energised as per manufacturers instructions.

  • 19.3. Are arrangements in place for any necessary/required inspection/maintenance of any installed electrical and mechnical equipment (includes Statutory Inspections)?

  • Statement: Please arrange for the installation to be shutdown/de-energised as per manufacturers instructions.

  • 19.4. Are any required supplies of fuels/utility guaranteed?

  • Statement: Please arrange for the installation to be shutdown/de-energised as per manufacturers instructions.

  • 19.5. Are plant rooms competely sterile of combustible materials and secured?

  • 20. Have you ensured any electro-mechanical equipment that is on site but not installed/commissioned is stored and preserved in accordance manufacturer’s recommendations and where possible covered in a flame resistive temporary covering materials (e.g. materials meeting LPS1207 or equivalent).

Preventing Water Damage

  • 21. Are the premises water tight?

  • 21.1. Are there benefits in using flame resisting temporary covering materials to prevent water damage to vulnerable areas, installed equipment or areas of high value? (e.g.using materials meeting LPS1207 or equivalent)

  • 22. Have you isolated and drained down water systems and supplies?

  • 22.1. Are you able to provide remotely monitored leak detection equipment?

  • 22.2. Are the locations of water shut off valves/stopcocks clearly displayed on a plan of the site that is provided at the main site entrance?

Earthworks Excavations & Storage

  • 23. Are plant rooms competely sterile of combustible materials and secured?

  • 24. Have large sections of exposed earthworks been adequately covered or protected from the elements wherever possible?

  • 25. Are all temporary and permanent drainage runs clear and flow freely, including discharge points, oil, silt and settlement traps, etc?

  • 26. Are arrangements in place to complete regular inspection and maintenance of pumps and dewatering systems?

  • 27. Where continued operation of pumping systems is critical, have remotely monitored alarms on pump operation been installed been installed?

Temporary Works

  • 28. Have structural reviews and risk assessments been completed for all temporary works?

  • 29. Are arrangements in place to conduct regular inspections and maintenance of temporary works during extended shutdown periods?

Structural Design

  • 30 Have assessments been made of the effects of wind loadings on structural integrity, including the use of any temporary covering materials?

  • 31 Are arrangments in place to review and re-assess the continued structural integrity of structures at appropriate intervals during extended periods of shutdown/mothballing?

Completion

  • Overall Comments

  • Completed by: (Name and Signature)

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.