Information
-
Machine
Crew
-
Operator
-
Was present for the duration of the CIL?
-
Helper
-
Was present for the duration of the CIL?
-
Take off
-
Was present for the duration of the CIL?
-
Maintenance
-
Was present for the duration of the CIL?
-
Conducted on
-
Prepared by
-
Add media
-
Select date
Rollstand
-
If lubing was done, was it completed was it done correctly (No under/over lubing)
-
Was the area properly inspected and were tags written for anything that needs to be addressed?
-
Does the area of the machine frame, critical components(including under guards), and surrounding area(including tools) look clean and 5s?
Splicer
-
If lubing was done, was it completed was it done correctly (No under/over lubing)
-
Was the area properly inspected and were tags written for anything that needs to be addressed?
-
Does the area of the machine frame, critical components(including under guards), and surrounding area(including tools) look clean and 5s?
Print units
-
If lubing was done, was it completed was it done correctly (No under/over lubing)
-
Was the area properly inspected and were tags written for anything that needs to be addressed?
-
Does the area of the machine frame, critical components(including under guards), and surrounding area(including tools) look clean and 5s?
Abhesive
-
If lubing was done, was it completed was it done correctly (No under/over lubing)
-
Was the area properly inspected and were tags written for anything that needs to be addressed?
-
Does the area of the machine frame, critical components(including under guards), and surrounding area(including tools) look clean and 5s?
Cutter creaser
-
If lubing was done, was it completed was it done correctly (No under/over lubing)
-
Was the area properly inspected and were tags written for anything that needs to be addressed?
-
Does the area of the machine frame, critical components(including under guards), and surrounding area(including tools) look clean and 5s?
Delivery/Stacker
-
If lubing was done, was it completed was it done correctly (No under/over lubing)
-
Was the area properly inspected and were tags written for anything that needs to be addressed?
-
Does the area of the machine frame, critical components(including under guards), and surrounding area(including tools) look clean and 5s?
-
What grade does this CIL deserve?<br>A-100% Everything was completed and extraordinary effort was given by the crew<br>B->80% Some items missed, but priority items were completed with quality<br>C->80% Items were missed, some effort was made but lacking quality<br>D-<80% Many items misses, it is clear that the crew was not participating 100% of the time<br>F-<80% Might as well of just ran the machine. This CIL must be rescheduled with mgmt supervision
-
Add signature