Document No.
-
Site Location
-
Conducted on
-
Prepared by
-
Accompanied by
Your Own Safety
-
Have you read and are you able to comply with your Site Visit SWMS?
-
Do you know what PPE you need? and do you have it available for your visit?
-
Did you participate in a relevant Site Induction and Pre Work Brief (PWB) when you reached the Contractor's site?
-
Do you have the local site contract persons contact details? Have they been informed?
Site Safety
All Work Places including Offices
-
Knowledge of & access to PSMP (or relevant Contractors SSSMP)
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
Emergency Evacuation Procedure posted and legible
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
Fire Equipment available, signposted, good condition, tagged
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
Emergency Egress clear
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
Wardens appointed/ signposted
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
Electrical leads checked/tagged (every 3 months on construction sites)
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
Waste segregated
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
Lighting adequate
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
Amenities clean and hygienic (Toilets, lunchrooms etc)
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
Hazardous substance register and MSDSs
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
Safe Stacking and Storage
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
Walkways, floors and aisles clear
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
General housekeeping and cleanliness
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
First Aid facilities available & First Aid officer signposted
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
If Manual handling - SWMS available and followed
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
Fencing & Security adequate, good condition.
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
Community contact/ helpline available
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
Additional Checklist for Construction Sites
-
Pre Work Brief recorded and signed by all workers.
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
Construction work SWMS available and being followed.
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
PPE requirements signposted, and PPE compliance, PPE branded
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
Plant movement on site safe and controlled
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
Work Permits in use for Construction Speace, Hotwork, Excavation, Work at Height.
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
Plant operations. Licenses. Pre use checks recorded. Condition of plant.
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
Lifting equipment. Up to date Tagging; in good condition.
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
Scaffolding Inspected and Tagged. Condition, toe boards, mesh etc.
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
Ladders in good condition. Non metallic for electrical work.
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)
-
Work at Height SWMS, PPE harness appropriately attached.
-
Closed (on=closed, off=open)
-
Risk Level
-
Actions to close out
-
Traffic Management Plan in place and working.
-
Risk Level
-
Actions to close out
-
Closed (on=closed, off=open)