Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
1. Contract Valuations (CV) and Forecasting
-
b. Does the original budget within the forecasting system reflect and align with the approved and signed off tender green sheet?
-
a. Is there an acceptable financial forecasting & reporting system and does it appropriately reflect the type of project being delivered?
-
c. Does the team demonstrate an understanding of the financial forecasting & reporting system and are they able to explain the difference/changes between the previous months forecast or P&L sheet, current months forecast and budget (costs, commitments, revenue and profit)?
-
d. Are changes to the budget for each cost code managed using budget transfers and variations?
-
e. Are gains and losses being shown for each code as they are made and not being transferred to later codes?
-
f. Does the team demonstrate an understanding of and are they able to explain differences between a committed cost forecast system and a cost basis forecast system?
-
g. Does the team demonstrate an understanding of each budget and its make up and exclusions within each cost code?
-
h. Does the team demonstrate an understanding of the effect of head contract and subcontract variations on the forecast and are they able to explain claim/variation take up to budget in the current forecast?
-
i. There is a manageable and conservative level of unapproved variations that have been taken up to the budget and no unapproved claims have been taken up?
-
j. Does the forecast cost to complete reflect the forecast and current contract completion dates on the program?
-
k. Does the team demonstrate an understanding of and are they able to explain differences in % cost & revenue to date compared to % time to date?
-
l. Does the team demonstrate an understanding of and are they able to calculate under/overclaims accurately?
-
m. Is there an understanding of the differences between cost/paid/accruals to date and work completed to date [earned value] vs claimed/invoiced to date and Planned Value?
-
n. Does the team demonstrate an understanding of, and are they able to calculate and forecast pain/gain on share of savings projects or risk-reward share or abatement penalties?
-
o. Does the team demonstrate an understanding of, is there a risk of exposure to and are they able to calculate and forecast liquidated damages under the head contract? Consider the status against the current contract program. Is there a need for a register of liquidated damages?
-
p. Does the team demonstrate an understanding of, and are they able to calculate rise and fall (escalation) in relation to revenue and cost?
-
q. Is the team able to manage, understand and explain what contingencies are made in the forecast/CV, any changes in contingency amounts and any available or non available contingency amounts?
-
r. Is the team able to record and understand productivity to date and forecast?
-
s. Is there an understanding of what bank guarantees, insurance bonds or retentions are being held by the client and their forecast to be returned?
-
t. Is the project cash positive?
-
u. Is the cashflow position relatively reflective of the forecast financial position and can the team demonstrate why there are differences?
2. Risk and Opportunities
-
a. Is there an acceptable risk and opportunity register in place and does it appropriately reflect the type of project being delivered?
-
b. Is there an acceptable process and procedure around identifying, managing and updating risk and opportunity and does it appropriately reflect the type of project being delivered?
-
c. Is there are copy of the tender R&O register and does the current R&O register include the risks and opportunities identified during the tender period and are the mitigation treatments (identified during tender) being carried out?
-
d. Are the identified risks appropriate to the project being delivered?
-
e. Is there adequate mitigation treatment or treatment plans identified for each of the risks and are the treatments or plans being carried out?
-
f. Does the mitigation treatment or treatment plans reduce the risk to an acceptable level?
-
g. Does the team demonstrate an understanding of and are they able to calculate appropriate contingency amounts for risk & opportunity where applicable?
-
h. The contingency amounts listed within the R&O register are being managed separately (not within each cost code) and match the amounts within the forecast, P&L sheet and/or CV reporting?
3. Head Contract / Alliance Agreement (Deed)
Generally
-
a. There is a copy of the head contract / alliance agreement and it has been correctly executed?
-
b. Have the Approval limits - Australia TM-F&A-PT-001-ADM been complied with in regard to contract execution?
-
c. There is a completed Rights and Obligations Summary (TP-LEG-FO-007) clearly reflecting the requirements of the head contract / alliance agreement?
Progress Claims / Tax Invoices
-
d. The team can demonstrate an understanding of and manage the conditions precedent to submission of a progress claims/invoices?
-
e. There is an accurate register of progress claims & tax invoices identifying submitted, certified and paid?
-
f. The client is making payments in accordance with the contractual timeframes?
Variations / Scope Changes
-
g. The team can demonstrate an understanding of what gives us or does not give us an entitlement to a variation / scope change under the head contract?
-
h. The team can demonstrate an understanding of how errors, ambiguities or inconsistencies are dealt with under the contract?
-
i. There is an appropriate variation register being kept for the project indicating variation claim number, variation order number, description, status, value submitted and approved, amount taken up to budget, relevant submitted and approved dates?
-
j. The variation register aligns with the variations / orders within the financial reporting system (JDE)?
-
k. The team can demonstrate an understanding of and manage the conditions precedent (including content and timing) to submission of a variation?
-
l. Variations are being submitted and approved by the client in a timely manner?
Extension of Time or Relief Events
-
m. The team can demonstrate an understanding of what gives us or does not give us an entitlement to an Extension of Time (EOT) / Relief Event under the head contract?
-
n. There is an appropriate Extension of Time or Relief Events register being kept for the project indicating EOT claim number, EOT approval number, description, status, time submitted and approved, relevant submitted and approved dates?
-
o. The team can demonstrate an understanding of and manage the conditions precedent (including content and timing) to submission of an Extension of Time or Relief Event?
-
p. Extensions of Time or Relief Events are being submitted and approved by the client in a timely manner?
Performance Incentives and Liquidated Damages
-
q. If there are performance incentives, KPIs, abatement schemes, liquidated damages and term extensions applicable to the contract, are the relevant measures in place to track, record and measure these?
-
r. Is the team able to understand and implement the performance incentives, KPIs, abatement schemes, liquidated damages and term extensions under the head contract?
Insurances
-
a. Relevant insurances have been obtained and put in place for the project?
4. Procurement & Subcontract / Consultancy / Supply Agreements
Generally
-
a. There is a procurement & letting schedule in place in which progress is being tracked and monitored. These may be separate documents. These schedules track at a minimum cost codes, package descriptions, key milestones/dates, lead time dates, tender dates (target & actual), award dates (target & actual), contract execution dates (target & actual), budgets/SORs, target budgets/SORs, actual committed/let values, gain/losses against budgets/SORs. There may also be a procurement plan.
-
b. Are packages being competitively tendered with an appropriate quantity of competitors?
-
c. Is an appropriate comparison being completed on the tender pricing to ensure inclusions are apples for apples against relevant budget / SOR items?
-
d. Correct entities have been contracted with in subcontract agreements, supply agreements and consultant agreement by checking ABR/ASIC websites for correct ABN/ACN & name)?
-
e. Have the Approval limits - Australia TM-F&A-PT-001-ADM been complied with in regard to purchasing?
-
f. If the National Code of Practice for the Construction Industry is applicable to the project, the Invitation to tender TP-LEG-CO-016 has been used and the appropriate undertakings and declarations have been executed and returned (including copies of DEEWR and Fair Work Australia letters) prior to awarding the contract?
-
g. If subcontractors, consultants or suppliers are working on the project, agreements are in place and have been correctly executed?
-
h. Thiess standard forms of agreement TP-PRO-PT-001are being used?
-
a. Subcontract, Consultancy and Supply Agreements reflect the relevant requirements of the head contract that need to be flowed on?
-
b. Agreements are adequately drafted and include a concise scope of works?
Security
-
b. Is there a register to obtain, manage and release security (bank guarantees or retention)?
Progress Claims / Tax Invoices
-
c. Is there an accurate register of progress claims & tax invoices for each subcontract, consultancy and supply agreement identifying submitted, certified and paid amounts?
-
d. Are progress claims being correctly assessed and signed off?
-
e. Are payment schedules under the security of payment legislation being correctly issued in the correct format and timeframes?
Variations / Scope Changes
-
c. The team can demonstrate an understanding of what gives or does not give each subcontractor, consultant or supplier an entitlement to a variation / scope change under the relevant agreement?
-
d. The team can demonstrate an understanding of how errors, ambiguities or inconsistencies are dealt with under the agreements?
-
e. There is an appropriate variation register being kept for each subcontractor, consultant or supplier indicating variation claim number, variation order number, description, status, value submitted and approved, amount forecast, relevant submitted and approved dates?
-
f. The variation registers align with the variations / orders within the financial reporting system (JDE)?
-
g. The team can demonstrate an understanding of and manage the conditions precedent (including content and timing) to submission & approval of a variation?
-
h. Variations are being assessed and approved in a timely manner?
-
i. Variations are being flowed through and linked to head contract variations where appropriate?
Extension of Time or Relief Events
-
j. The team can demonstrate an understanding of what gives or does not give each subcontractor, consultant or supplier an entitlement to an Extension of Time (EOT) / Relief Event under the agreement?
-
k. There is an appropriate Extension of Time or Relief Events register being kept for each subcontractor, consultant or supplier indicating EOT claim number, EOT approval number, description, status, time submitted and approved, relevant submitted and approved dates?
-
l. The team can demonstrate an understanding of and manage the conditions precedent (including content and timing) to submission of an Extension of Time or Relief Event?
-
m. Extensions of Time or Relief Events are being assessed and approved in a timely manner?
Performance Incentives and Liquidated Damages
-
n. If there are performance incentives, KPIs, abatement schemes, liquidated damages and term extensions applicable to the agreements, are the relevant measures in place to track, record and measure these?
-
o. Is the team able to understand and implement the performance incentives, KPIs, abatement schemes, liquidated damages and term extensions under the head contract?
-
p. There is a calculation of liquidated damages on file which is the basis of the amount included within relevant agreements?
Insurances
-
q. Relevant insurance certificate of currencies have been obtained from each subcontractor and consultant?
-
Lead Auditor to sign off at completion
-
Area Manager to sign off at the completion of the audit
-
Select date