Section 1 General

  • 1.1 CVIS program in place and completed daily with craft engagement?

  • 1.2 Project safety plan is updated and correct?

  • 1.3 The crisis plan utilizes the Corp. communications model and is updated?

  • 1.4 Competent persons for the project are identified and listed?

  • 1.5 Operators are qualified and have card with with them?

  • 1.6 Utility Map is located in the office with all utilities color coded and updated?

  • 1.7 Overhead and underground utilities are properly marked/signed?

  • 1.8 Job is following job specific respirator plan?

  • 1.9 TCSD chart is updated with proper signatures?

  • 1.10 Safety indoctrination process is being followed with new hires?

  • 1.11 Management is engaged with craft?

  • 1.12 Construction manager visits job every month?

  • 1.13 Extreme housekeeping in the office?

  • 1.14 "Nobody gets Hurt" culture is obvious and visible in the office?

  • 1.15 Company vehicles are kept clean and free from hazards?

  • 1.16 All drivers have completed driver training?

  • 1.17b Safety is visible in immediate office area?

  • 1.18 Why I Work Safe posters are up and to date?

  • 1.19 Safety Commitment board is in place and signed by job team?

  • 1.20 The job has a safety recognition program?

  • 1.21 Job management has completed OSHA inspection training?

  • 1.22The project has key personnel hands-on training in first aid and CPR?

  • 1.23 The project has an active craft engagement program?

  • 1.24 Subcontractors are included in craft engagement program?

  • 1.25 The project is following the documentation process on the OCC site/KieTrac?

  • 1.26 The Hazcom program and MSDS/SDS binder are up to date?

  • 1.26.1Employees have been trained in new SDS system?

  • 1.27 Work Zone incident files are complete with TCP plan and MOT drawings specific to the scene?

  • 1.28 Daily traffic reports are fully completed and signed by management?

  • 1.29 MOT is videotaped at least weekly, when it changes, and after a traffic incidents?

  • 1.30 Monthly safety meeting are utilizing hands on training?

Section 2 General Site

  • 2.1 Foreman's work plan-specific to the operation, comprehensive and followed?

  • 2.2 - High Risk operations identifed?

  • 2.3 Red Book complted- Step by step following the work plan, pictures, reviewed by superintendent and craft?

  • 2.4 Toolbox Meetings-all sections completed, crew comments, hands on training?

  • 2.5 Fall protection plan-accurate (equip/rescue/sketch/anchors), signed by crew?<br>

  • 2.6 Overhead Power Line Permit - used, correct, in JHA, signs, spotter, air horn and signed by crew?

  • 2.7 Trench Inspection - Competent person, completed prior to each shift completely filled out?

  • 2.8 Excavation Permit - At the operation, specific, verified with map, signed off?

  • 2.9 Daily Crane inspections - completed prior to putting to work each shift?

  • 2.10 On The Spot Lift Plan - weight known, Accurate, Signed, set up matches plan?

  • 2.11 Critical Lift Plan- Use as required, pull tape to verify radius, proper signatures?

  • 2.12 Rigging Inspections - At purchase, before each use, tags in place, condition and storage?

  • 2.13 TSCD/Falsework - Calculations in the field, built per plan, inspections, documents?

  • 2.14 Safety Visibility - proper signs in strategic locations, understood by craft?

  • 2.15 Listen up/Speak up - Craft buy-in, Positive attitude, open communication at all levels?

  • 2.16 Craft are engaged with safety on the project?

Section 3 Operations

  • 3.1 PPE - Correct for the task, Called out in the hazard analysis?

  • 3.2 Access- Pathways clear, free from slips, trips & falls, over 18" change has access?

  • 3.3 Work area - Planned out, level working area, free from slips, trips & falls?

  • 3.4 Stairs - Level, each same height & depth, stair rail with 3 or more steps?

  • 3.5 Ladders, General - Face the ladder, not carrying anything in hands, hips within rails?

  • 3.6 Extension Ladders - 4:1 angle, secured, 36" above landing, walk through ladder access?

  • 3.7 Step Ladder - Open and locked not on top 2 steps?

  • 3.8 Job Built ladders - Built to specifications and maintained?

  • 3.9 Housekeeping - is Extreme, waist containers utilized?

  • 3.10 Hazardous Materials - HAVE MSDS/SDS with JHA, properly labled?

  • 3.11 Material Handling - well planned, square to the world, nothing touched ground?

  • 3.12 Material Handling - Using proper tools/equipment, stacked properly and secured?

  • 3.13 Material Handling - Proper lifting, not lifting more than 50 lb. by one person?

  • 3.14 Trailer Loading/Unloading - Flagging system being used, properly loaded and secured?

  • 3.15 Tools- Good condition, trigger locks removed?

  • 3.16 Tool Storage - Proper storage, bits removed, housekeeping, blades hung up, right RPM blade for tool?

  • 3.17 Tool Use - Proper tool for the job, unplugged/disconnected when changing bit/blade?

  • 3.18 Tools General - Mushroomed heads, using correct hammer, damaged tools?

  • 3.18.1 Proper use of guards, handle used on tools?

  • 3.19 Electrical - GFCI/assured grounding-cords in good condition, good cord management, cord covers correct size cords?

  • 3.20 Fire Extinguishers - In correct locations, Serviced annually, training on correct use completed?

  • 3.21 Welding - PPE, Fire extinguisher, hot work permit if required, leads, stinger in good condition?

  • 3.22 Cutting Torch- PPE, Fire Extinguisher, hot work permit if required?

  • 3.23 Cutting Torch - Hoses in good condition, flashback arrestors, proper cart, proper storage?

  • 3.24 Equipment - Authorized operators, visuals, seatbelts, lights on, turned off when out of cab?

  • 3.25 Access Roads - Maintained, smmoth, dust control, proper signage, berms?

  • 3.26 Cranes (operator) - Authorized, daily inspection,On The Spot Lift Plan completed?

  • 3.27 Cranes (Set Up) - Level, swing radius up, Pads correct, proper handling of pads, overhead utilities?

  • 3.28 Riggers - Properly trained and qualified?

  • 3.29 Signal Persons - Properly trained and qualified?

  • 3.30 Trenches - Sloped 1.5:1, shielded or shored properly, access every 25 feet?

  • 3.31 Trenches - Spoils and equipment 2' back, fall protection in place?

  • 3.32 Scaffolding/Stair Towers - Inspected daily, Competent person signed off, tagged, secured?

  • 3.33 Fall Protection - Engineered sysem, trained workers, 100% correct, 100% tied off?

  • 3.34 Dropped Objects - Area below barricaded, tool lanyards used, trained in dropped object prevention?

  • 3.35 LOTO - Tagged properly, all energy sources locked out, everyone has own lock, trained in LOTO?

  • 3.36 Night Operations - Class 3 vest near traffic, proper lighting, headlamps?

  • 3.37 First Aid - Kits stocked, eye wash stations in place at work area?

  • 3.38 MOT - Properly set up to TCP/MUTCD, inspected daily, documentation signed?

  • 3.39 MOT - Employees are trained for being in work zone, proper protection in place ( attenuator/Blocking vehicle)?

  • 3.40 MOT - Traffic control supervisors ASSTA training is up to date?

  • 3.41 General - Implement hazards addressed, proper gas cans labeling?

  • 3.42 General - All cans, sprayers etc. properly labeled?

  • 3.43 Management Visibility - Foreman are with crews, craft superintendents with operations?

  • 3.44 Subcontractors - Following our safety program?

  • 3.45 Field Operations - Following all district Standard Operating Procedures?

Section 4 Marine

  • 4.1 Barge Vessel inspections complete?

  • 4.2 Personal flotation devises being worn?

  • 4.3 Proper signage in place?

  • 4.4 Proper access to and from barge or vessel?

  • 4.5 Rescue plan (man overboard) and rescue equipment in place, boat, life rings etc.

  • 4.6 confine space addressed on entering hull of barge?

  • 4.7 Equipment on barge has been designed?

Section 5 Overall Opinion of the project

  • Do you feel the project is following the basics that make for a good job?

  • Does the project have enough management support?

  • Do you feel the job has owner issues that are taking focus away from building a successful project?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.