Page 1: Initial questions
-
Conducted on
-
Depot Name
-
Location
-
Corridor
-
Date of Maintenance Shut Down
-
Scope of Work
-
Name of Person Monitoring Compliance
-
Designation
-
Cellphone
Page 2: Main checklist
COMMUNICATION PLATFORMS
-
Service Level Agreement Meetings:Are there records of periodic SLA meetings and appropriate actions taken in terms of any applicable corrective actions raised by Transnet?
-
Verify whether the progress meetings are conducted in terms of agreed schedule and minutes kept
-
Verify if there is proof of communication relating to the TIMS aspects of the contract and have these been communicated to the contractor /sub-contractor employees
-
Verify if there is adequate representation by the Service Provider at all required meetings scheduled by Transnet e.g. monthly SHEQ Committee Meetings, etc.
CONTRACTOR MANAGEMENT
-
Contractor Execution Plan (CEP) approved by the Project Manager and implemented by the Contractor - Work carried out in terms of the Contractor Execution Plan including TIMS requirements
-
Method statement:Verify if written safe work procedures for high risk tasks complied with
-
Safe working procedures:Verify if written safe work procedures for high risk tasks complied with
-
Verify if task specific observations have been appropriately planned and effectively carried out and if corrective action is taken to address any identified non-conformances
RISK ASSESSMENTS
-
Verify whether the recommendations from the Health Risk Assessment have been implemented
-
Verify if traces of asbestos exist
-
If yes , verify whether relevant stakeholders have been notified e.g. (Occupational Health and Hygiene, Medical Practitioner and Risk Management)
-
If traces of asbestos exist verify whether exposed employees were subjected to medical surveillance
-
Was the site declared safe by the approved inspection authority post asbestos clean up
-
Verify whether the recommendations from the Ergonomics assessment have been implemented
-
Horticulture:Verify whether the recommendations from the Fauna Flora assessment for Fencing have been implemented
-
Verify whether the recommendations from the Fauna Flora assessment for Service Roads have been implemented
-
Verify whether the recommendations from the Fauna Flora assessment for Bush and Weed Control have been implemented
EQUIPMENT MAINTENANCE,MACHINERY AND WORKFORCE
-
Maintenance and control of equipment. (Cranes, welding, grinding, blasting, pressure vessels): Verify if the equipment is maintained as per manufacturer’s schedule / Original External Manufacturer’s Manual
-
SHE Representatives: Verify visibility of SHE Reps including effective performance of SHE Reps functions
-
Personal Protective equipment: Verify if all employees / personnel on site are wearing using PPE appropriately
-
Verify if general housekeeping is adequate
-
SITE AUDITS/INSPECTIONS
-
Site specific audits and internal inspections arrangements. Verify if the internal audits are conducted as per agreed frequencies
-
Verify if the equipment is maintained on an impervious surface or within a bunded area
-
Verify the monthly performance report produced, which includes the TIMS monitoring criteria
-
Verify if the formal non- conformances are actioned and closed out
INCIDENT MANAGEMENT ( RECORDING AND REPORTING)
-
Accident / incident reporting and investigation
ERMERGENCY SERVICES
-
Verify if the names of the first aiders are displayed
-
Verify if there were first aid cases and recorded on first aid box log-sheets.
-
Verify if the names of the fire teams are displayed
-
Verify if the fire- fighting equipment is accessible (fire extinguishers, hose-reels, fire trolleys and vehicles)
-
Verify if symbolic signs positioned to be visible
-
Verify if the security staff is familiar with incident reporting system and emergency procedures<br>
BALLAST
-
Is the ballast waste managed in accordance with the NEM: Waste Act,2008
MAINTENANCE ACTIVITIES
-
On track maintenance: Verify if contamination resulting from the on track machines is addressed by relevant contractors
-
Verify if drip trays are placed beneath leaking points under the on track machines
-
Verify if oil drums are stored in <br>designated areas
-
Sleeper replacement: Verify if the wooden sleepers are placed in the designated storage area far from the reserve
-
Verify if cement sleepers are used for fencing purposes
-
Culverts cleaning:Verify whether all removed material are stored neatly at the designed areas (and away from drains and culverts) within rail reserves
RAIL MAINTENANCE
-
Welding and Grinding of Rails:Verify whether burnable materials are placed and stored away from sites
-
Verify that Welder is trained and certificates are valid
-
Verify whether employees are wearing appropriate PPE<br>
-
Verify whether: Safety talks have been conducted <br>
-
Verify whether: Site Risk assessment done <br>
-
Verify whether: The work is done according to the approved Safe working Procedure <br>
-
Rail Lubrication:Verify if caution is exercised when filling the greased pot
-
Rail Lubrication: Verify usage of the approved safe working procedure for this activity adhered to
BALLAST SCREENING
-
Ballast screening: Is the ballast waste managed in accordance with the NEM: Waste Act,2008
-
Fencing: Verify if the Fauna Flora Assessment is conducted by the Rail Network Horticulture-Technical office
-
Verify if the recommendations from the Fauna Flora assessment have been implemented
-
Verify if the Fauna Flora Assessment is conducted by the Rail Network Horticulture-Technical office
WASTE MANAGEMENT
-
Verify if the waste management is undertaken in accordance with the requirements of NEM: Waste Act,2008
COVID19 PREVENTENTION
-
Verify if employees are issued with masks
-
Verify if site is provisioned with saunters
-
Verify if employees declared their Covid status