Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Traffic Management
-
Traffic management plan on site
-
Are signs appropriate
-
Are traffic signs in good condition
-
Are traffic controllers wearing appropriate P.P.E
-
Is pedestrian traffic managed correctly and well signed
-
Is work site we'll protected (people, plant, equipment)
-
Are signs well located and visible
-
Are sufficient cones used
-
Traffic controllers vehicle(s) in good order, flashing lights used
-
Is level 2 traffic controller on site
-
Jewellery, watches, rings or other body adornments removed
Personal Protective Equipment
-
Hard hats, footwear, safety glasses, gloves and sunscreen worn where appropriate
-
Approved work clothing with sleeves down
-
Pole belt/ safety harness in test and fit for use. Worn as per Thiess Work Practice
Equipment Testing
-
Plant and machinery in test date where appropriate
-
Gloves and sleeves within test date
-
Insulation cover within test date
-
Lifting gear within test date
-
Testing equipment within test date
-
Are 240v tools and leads within test
-
Ladders within test date
-
Vehicle/Plant/trailer log books completed EMFRs completed and submitted (if applicable)
-
Fire extinguisher in date and available
Environment
-
Spill kits available and complete
-
Are environmental risks identified and appropriate controls in place
-
MSDS sheets accessible
-
Are fire ant precautions in place if applicable
First Aid
-
First aid kit available and location clearly labeled
-
Is first aid kit complete, in test and in good order
Work planning
-
Tailgate talk conducted
-
DYBD on site if applicable
-
On site risk assessment been conducted and filled out correctly
Work practices
-
Effective safety observer
-
Pole top rescue kit located easily to perform a rescue if required
-
Construction sign erected, poles inspected where required and vehicles and plant located safely
-
Drop zones clearly identified
-
Workers clear of drop zone - clear communication when entering drop zone.
-
Appropriate tests carried out (De energised, polarity, phase rotation, pole inspection etc.)
-
Working live Work Practice followed
-
Access permit/ De energisation permit conditions met
-
Exclusion zones followed
-
Conductors adequately controlled
Work Quality
-
Cross arms horizontal, poles vertical, sags even
-
Work completed as per works plan/ changes noted on works plan
-
Worksites left clean and tidy
General comments
-
Comments
-
Add signature
-
Add media