Title Page

  • Date

  • Job Number:

  • Job Name:

  • Location of Pour

1. Preparation

  • 1a. Have own set of current approved drawings (Structural, Post-Tensioning tendon placement drawings & Rebar placement drawings)

  • Corrective Action Taken:

  • Date of drawings (Structural, PT, & Rebar):

  • 1b. Have consulted with Engineer over critical inspection needs for this slab

  • Corrective Action Taken:

  • Name of Engineer

  • Engr. Tel.#

2. Formwork

  • 2a. Geometry of drop caps, drop panels, beams, soffit slopes, slab thicknesses, etc.

  • Corrective Action Taken:

  • Slab thickness:

  • 2b. Tight, clean & free of puddles

  • Corrective Action Taken:

  • 2c. Reshoring in place if required

  • Corrective Action Taken:

  • 2d. Correct slab edge geometry

  • Corrective Action Taken:

  • Slab edge installed per drawing:

  • Dated:

  • Slab edge anticipated to shorten __" after stressing.

3. Mild Steel Reinforcing

  • 3a. Reinforcing at walls and columns (sizes, lengths, spacing & staggers)

  • Corrective Action Taken:

  • 3b. Bottom mat (size & spacing)

  • Corrective Action Taken:

  • 3c. Beams (top bars, bottom bars, bar cutoff points, stirrups & spacings)

  • Corrective Action Taken:

  • 3d. Additional special locations shown on plans (corners, etc.)

  • Corrective Action Taken:

  • 3e. Cover:

  • Corrective Action Taken:

  • Cover required at top:

  • Cover required at bottom:

  • 3f. Clean

  • Corrective Action Taken:

  • 3g. Lap splice lengths (bottom mat, beams, etc.)

  • Corrective Action Taken:

  • 3h. Slab/wall dowels cast into walls & at position within slab

  • Corrective Action Taken:

  • 3i. Reinforcing & chairs securely tied

  • Corrective Action Taken:

  • 3j. Proper tools used for field bends

  • Corrective Action Taken:

  • 3k. Proper grade reinforcement

  • Corrective Action Taken:

4. Post-Tensioning

  • Is there post-tensioning on this slab?

  • 4a. Tendon condition (sheathing intact, no kinks, no tears, etc.)

  • Corrective Action Taken:

  • 4b. Number and location of tendons

  • Corrective Action Taken:

  • 4c. Tendon profiles (all high points and low points checked)

  • Corrective Action Taken:

  • Tolerance per drawings:

  • 4d. Smooth curvature of tendons (horizontally and vertically)

  • Corrective Action Taken:

  • 4e. Sweep of tendons around blockouts & openings (smooth curvature & radius per drawings)

  • Corrective Action Taken:

  • 4f. Column cap details (precedence of tendon layers, etc.)

  • Corrective Action Taken:

  • 4g. Watertight corrosion protection details

  • Corrective Action Taken:

  • 4h. Tendons, support bars and chairs securely tied at all support locations

  • Corrective Action Taken:

  • 4i. Tendons locations marked on forms for future reference

  • Corrective Action Taken:

  • 4j. Anchorages

  • Corrective Action Taken:

  • 4j-1. Special reinforcing details

  • Corrective Action Taken:

  • 4j-2. Live ends secured tightly to formwork

  • Corrective Action Taken:

  • 4j-3. Dead ends chaired to appropriate profile

  • Corrective Action Taken:

  • 4j-4. Anchors to bear against solid concrete (not near conduit, etc.)

  • Corrective Action Taken:

  • 4j-5. Spacing, stagger, & orientation of anchors

  • Corrective Action Taken:

  • 4j-6. Tendon straight into anchor (per placement drawings)

  • Corrective Action Taken:

  • 4j-7. Adequate tails for stressing

  • Corrective Action Taken:

  • 4j-8. Adequate clearance for stressing equipment

  • Corrective Action Taken:

  • 4k. Sweep bars installed per Structural drawings (detail 24/S-408 states: required for cable sweeps tighter than 1" in 12", clear distance between cables = 2", and #4 U-bars installed 12" on center over length of curved section for each bundle)

  • Corrective Action Taken:

  • 4l. Backup bars installed at groups of 6 or more cables

  • Corrective Action Taken:

  • Backup bar to be placed 3/8 of the slab thickness away from the anchors (ex: 3" for 8" slab, 3.75" for 10" slab, 4.5" for 12" slabs)

  • 4m. Backup bars installed at dead ends at beams

  • Corrective Action Taken:

  • Backup bar to be placed 3/8 of the slab thickness away from the anchors (ex: 3" for 8" slab, 3.75" for 10" slab, 4.5" for 12" slabs)

  • 4n. When tendons are placed through the column, do at least two tendons in both directions pass through the column vertical reinforcement?

  • Corrective Action Taken:

5. Embedments

  • 5a. Embedments near anchorages approved by engineer

  • Corrective Action Taken:

5b. Conduit

  • 5b-1. Engineer approval (if not shown on engineer-approved plans)

  • Corrective Action Taken:

  • 5b-2. Maximum approved size

  • 5b-3. Approved material

  • 5b-4. Locations and congestion

  • Corrective Action Taken:

  • 5b-5. Special reinforcing details

  • Corrective Action Taken:

5c. Plumbing and other blockouts:

  • 5c-1. Engineer approval (if not shown on engineer-approved plans)

  • Corrective Action Taken:

  • 5c-2. Maximum approved size

  • 5c-3. Locations (specific engineer approval if in drop caps or highly reinforced areas)

  • Corrective Action Taken:

  • 5c-4. Special reinforcing details

  • Corrective Action Taken:

  • 5d. Anchor bolts and Hand-Downs secured in place

  • Corrective Action Taken:

  • 5e. Embeds Installed:

  • Drawing #s and Dates of embed drawings used:

6. Blockouts & Closure Strips

  • 6a. Geometry and location

  • Corrective Action Taken:

  • 6b. Special reinforcing details

  • Corrective Action Taken:

  • 6c. Special shear key details (if required)

  • Corrective Action Taken:

  • 6d. Adequate clearance for stressing equipment (if required)

  • Corrective Action Taken:

7. Other

  • 7a. All details shown on drawings (Structural, Post-Tensioning tendons & Rebar) applied appropriately

  • Corrective Action Taken:

  • 7b. Typical details applied appropriately

  • Corrective Action Taken:

  • 7c. Projections of walls & columns into slab within tolerance

  • Corrective Action Taken:

  • 7d. Special release/slip details applied appropriately

  • Corrective Action Taken:

  • 7e. Engineer notified of any conflicts that required modifications

  • Corrective Action Taken:

  • 7f. Engineer notified of pour date and of any changes to pour date

  • Corrective Action Taken:

  • 7g. Stud rails installed correctly (straight, correct cover, etc.)

  • Corrective Action Taken:

  • Completed by: McHugh Concrete Team

  • Date Completed:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.