Title Page
-
Name of Person performing inspection
-
Time and Date Inspection:
-
-The following Quality Checks must be performed prior to Red Tag of the UPS
-
UPS being Inspected (Site, Area, UPS)
-
UPS Serial Number
UPS Visual Inspection
-
Take Photos of the UPS rating plate
-
Take Photos of all sections (front, back and sides) of the UPS with covers on (take timestamp pictures)
-
Take Photos of all sections (front, back and sides) of the UPS with covers removed (take timestamp pictures)
-
Check the UPS iSBM section for cleanliness.
-
Take Photos of the ISBM Section
-
Check the UPM 1 section for cleanliness.
-
Take Photos of UPM 1
-
Check the UPM 2 section for cleanliness.
-
Take Photos of UPM 2
-
Check the UPM 3 section for cleanliness.
-
Take Photos of UPM 3
-
Check the UPM 4 section for cleanliness.
-
Take Photos of UPM 4
UPS Mechanical Inpsection
-
Check that the internal inter-cabinet connections have been torqued and marked.
-
Take Photos of the torqued connections
-
Check that the UPS connection fixing pack is available for the installing contractor.
-
Take a photo of the fixing pack
-
Check that the brackets connecting the sections together are fitted.
-
Take photos showing the connected brackets of the UPS
-
Place the connectivity boxes, EPO pushbutton, and any other loose items in a tool safe.
-
Take photos of the connectivity boxes, EPO pushbutton, and any other loose items in a tool safe.
Sign off
-
Representative