Information
-
Well Site
-
Audit Activity
- Facility Layout & Grading
- Containment Install
- Facility Hook-Up
- Flowline Install
- Low Pressure Test & Pad Commissioning
- Misc. Roustabout Work
-
Personnel/Crew(s) on Site
- Sheckler's Excavating
- Albert's Spray Solutions
- Falcon Technologies
- Crown Oilfield Services
- Advanced Oilfield Services
- Renegade Well Services
- SEI Oilfield Services
- Other
-
Conducted on
-
Prepared by
-
Site Address
PAD SITE
-
Lease road in working condition
-
Pad fence/gate in working condition
-
Pad in clean and working condition
-
Pad drain in open position after Completions activity
-
Security camera in place
-
All facilities painted/coated
WELLHEADS
-
Well cellar covers assembled & installed with custom hatch covers
-
Cellar clear of debris & in working condition
-
6" PVC well cellar suction piping & 57 washed gravel installed
-
Locking 5K ball valve on dry gas bottle and locked with zip tie in open position
-
Intermediate casing piping installed with 5000# ball valve minimum (6000# fittings & XXH pipe)
-
Surface casing piping installed with 3000# ball valve minimum (3000# fittings & schedule 80 piping)
-
Flanges have been checked for proper gaskets, torqued, tagged, & initialed
-
Valves are installed w/ handles accessible, allowing full operation & left in closed position
-
Plugs are installed on all bleed points & open ended valves
-
Pipe support(s)/bracing are properly installed
SAND TRAP(S)
-
XXH Bull Plugs installed where applicable
-
Water dump line out of bottom of vessel(s) had Bull Plug/Tee installed and not a single elbow
-
Check valves are installed in the proper direction
-
Flanges have been checked for proper gaskets, torqued, tagged, & initialed
-
PSVs are correctly sized for vessel(s), ball valves are locked/tied open, weep holes drilled in vent piping elbow, & rain caps are in place
-
Valves are installed w/ handles accessible, allowing full operation & left in closed position
-
Hammer unions are flagged/tight
-
Plugs are installed on all bleed points & open ended valves
-
Pipe support(s)/bracing are properly installed
LINE HEATER(S)
-
Line Heater Fuel Gas supply linked to the respective GPU, tied to the GPU fuel gas scrubber @ top, isolated with a 1/2" ball valve. 3/8" SS tubing used, tie wrapped to line heater outlet piping
-
Dump installed off scrubber pot with ball valve & check valve, routed to water dump piping in pipe rack with ball valve to isolate. 1/2" SS tubing used, tie wrapped to the line heater outlet piping
-
Enardo vent has all part installed & undamaged; correct spring is installed (???? oz)
-
Line Heater full of Glycol mix
-
If rental iron is being used; is it banded & within service date
-
Check valves are installed in the proper direction
-
Flanges have been checked for proper gaskets, torqued, tagged, & initialed
-
PSVs are correctly sized for vessel(s), ball valves are locked/tied open, weep holes drilled in vent piping elbow, & rain caps are in place
-
Valves are installed w/ handles accessible, allowing full operation & left in closed position
-
Hammer unions are flagged/tight
-
Plugs are installed on all bleed points & open ended valves
-
Pipe support(s)/bracing are properly installed
GPU(S)
-
Verify oil and water safety high/low level switches installed properly
-
GPU(s) full of Glycol mix
-
MicroMotion Meter installed and spool piece/blinds removed
-
Check valves are installed in the proper direction (Example: 1/2" tubing check valve in proper flow direction for fuel gas scrubber drain)
-
Flanges have been checked for proper gaskets, torqued, tagged, & initialed
-
PSVs are correctly sized for vessel(s), ball valves are locked/tied open, weep holes drilled in vent piping elbow, & rain caps are in place
-
Valves are installed w/ handles accessible, allowing full operation & left in closed position
-
Hammer unions are flagged/tight
-
Plugs are installed on all bleed points & open ended valves
-
Pipe support(s)/bracing are properly installed
PAD FUEL SCRUBBER
-
Proper regulators installed & in proper direction of flow
-
Manual dump installed off bottom of vessel & routed to production tanks
-
Positive shutoff installed in top of scrubber ob fuel gas outlet
-
Check valves are installed in the proper direction
-
Flanges have been checked for proper gaskets, torqued, tagged, & initialed
-
PSVs are correctly sized for vessel(s), ball valves are locked/tied open, weep holes drilled in vent piping elbow, & rain caps are in place
-
Valves are installed w/ handles accessible, allowing full operation & left in closed position
-
Hammer unions are flagged/tight
-
Plugs are installed on all bleed points & open ended valves
-
Pipe support(s)/bracing are properly installed
HEATER TREATER(S)
-
Verify 1/2" ball valve & check valves installed on fuel gas scrubber drain
-
Verify all low pressure threaded caps have been replaced on 2" threaded inlet & outlet piping with high pressure caps
-
Verify the Kimray valve on the 1" piping from the vertical gas vessel to the 2" water dump piping of the treater is installed ( 112 Kimray on the 125# unit) (130 Kimray on the 150# units)
-
Pressure gauge installed on vessel and scrubber pot
-
Verify 212 SGT BP regulator installed on flash gas between heater treater & pipe rack to compressor
-
Sight-glass & protectors installed & undamaged
-
Verify 2" blowdown tee is downstream of check valve & upstream of ball valve on existing inlet to heater treater
-
Verify 1/2" liquid blowdown & drain points downstream of 2" check valves & upstream of ball valves are at the 4:30 position
-
Verify 1/2" gas blowdown points downstream of 2" check valves & upstream of ball valves are at the 12:00 position
-
Check valves are installed in the proper direction
-
Flanges have been checked for proper gaskets, torqued, tagged, & initialed
-
PSVs are correctly sized for vessel(s), ball valves are locked/tied open, weep holes drilled in vent piping elbow, & rain caps are in place
-
Valves are installed w/ handles accessible, allowing full operation & left in closed position
-
Hammer unions are flagged/tight
-
Plugs are installed on all bleed points & open ended valves
-
Pipe support(s)/bracing are properly installed
COMPRESSOR
-
Exhaust positioned outside of compressor
-
Verify automatic dump piping installed to inlet of heater treater (with no stabilizer & bullet tanks) (installed to agreed sequence of valving)
-
Verify automatic dump piping installed (with manifold); upper to inlet of heater treater, lower to oil outlet of heater treater to stabilizer & bullet tanks (installed to agreed sequence of valving)
-
Verify a double diaphragm pump installed on the compressor suction c-scrubber automatic dump to heater treater
-
Verify manual dump piping to tanks (installed to agreed sequence of valving)
-
Compressor cover/shed is installed & undamaged
-
Check valves are installed in the proper direction
-
Flanges have been checked for proper gaskets, torqued, tagged, & initialed
-
PSVs are correctly sized for vessel(s), ball valves are locked/tied open, weep holes drilled in vent piping elbow, & rain caps are in place. Vent lines are routed through cover/shed roof & holes are sealed
-
Valves are installed w/ handles accessible, allowing full operation & left in closed position
-
Hammer unions are flagged/tight
-
Plugs are installed on all bleed points & open ended valves
-
Pipe support(s)/bracing are properly installed
LOW PRESSURE TOWER
-
Check valves are installed in the proper direction
-
Flanges have been checked for proper gaskets, torqued, tagged, & initialed
-
PSVs are correctly sized for vessel(s), ball valves are locked/tied open, weep holes drilled in vent piping elbow, & rain caps are in place
-
Valves are installed w/ handles accessible, allowing full operation & left in closed position
-
Hammer unions are flagged/tight
-
Plugs are installed on all bleed points & open ended valves
-
Pipe support(s)/bracing are properly installed
TANKS
-
Containment wall/liner installed and undamaged
-
EPRV and Enardo 660 valves installed allowing full operational range
-
Truck loadout and vent line installed, all parts included & undamaged
-
2' "Fuzzy Balls" installed to proper specifications as shown on listing for 6 tanks (10) or 8 tanks (12)
-
3' "Fuzzy Balls" installed to proper specifications as shown on listing for 2 tank packages (3 with Fuzzy Windsock)
-
Truck loadout grounding/bonding installed
-
Windsock installed below elevation of "Fuzzy Balls" on walkway
-
Enardos installed for tank setup with correct weights/springs (940s @ 10oz; 950s @ 9.5oz; 660s @ 12oz pink spring)
-
Check valves are installed in the proper direction
-
Flanges have been checked for proper gaskets, torqued, tagged, & initialed
-
Valves are installed w/ handles accessible, allowing full operation & left in closed position
-
Hammer unions are flagged/tight
-
Plugs are installed on all bleed points & open ended valves
-
Pipe support(s)/bracing are properly installed
COMBUSTOR
-
1/2" fuel gas tubing secured to piping (do not bury)
-
Blow Case, all parts included & undamaged
-
PSO Scrubber Pot, all parts included & undamaged
-
Check valves are installed in the proper direction
-
Flanges have been checked for proper gaskets, torqued, tagged, & initialed
-
PSVs are correctly sized for vessel(s), ball valves are locked/tied open, weep holes drilled in vent piping elbow, & rain caps are in place
-
Valves are installed w/ handles accessible, allowing full operation & left in closed position
-
Hammer unions are flagged/tight
-
Plugs are installed on all bleed points & open ended valves
-
Pipe support(s)/bracing are properly installed
STABILIZER SKID(S)
-
Gate valve installed on 3" oil inlet
-
Bleed point installed on 3" oil-in line, upstream of 3" gate valve
-
Differential gauge present on the Coalescing filter vessel
-
Line Heater full of TEG
-
Check valves are installed in the proper direction
-
Sight-glasses & protectors installed and undamaged
-
Flanges have been checked for proper gaskets, torqued, tagged, & initialed
-
PSVs are correctly sized for vessel(s), ball valves are locked/tied open, weep holes drilled in vent piping elbow, & rain caps are in place
-
Valves are installed w/ handles accessible, allowing full operation & left in closed position
-
Hammer unions are flagged/tight
-
Plugs are installed on all bleed points & open ended valves
-
Pipe support(s)/bracing are properly installed
NGL LOADOUT AND BULLET TANKS
-
ESD(s) installed within 25 ft of loadout
-
Temperature/pressure gauges installed on Bridle
-
Tuning forks on bridle located at a lower elevation than that of welding thredolet on bullet tanks
-
Crosses installed on upper & lower portions of bridle, with bleed point located on bottom
-
Grounding reel & rod installed near loadout station for NGL loadout
-
Grounding clamps installed on closest pipe nipple to loadout lines & tied into ground rods
-
Check valves are installed in the proper direction
-
Flanges have been checked for proper gaskets, torqued, tagged, & initialed
-
PSVs are correctly sized for vessel(s), ball valves are locked/tied open, weep holes drilled in vent piping elbow, & rain caps are in place
-
Valves are installed w/ handles accessible, allowing full operation & left in closed position
-
Hammer unions are flagged/tight
-
Plugs are installed on all bleed points & open ended valves
-
Pipe support(s)/bracing are properly installed
OTHER PIPING & CONNECTIONS
-
Check valves are installed in the proper direction
-
Valves are installed w/ handles accessible, allowing full operation & left in closed position
-
Flanges have been checked for proper gaskets, torqued, tagged, & initialed
-
Plugs are installed on all bleed points & open ended valves
-
Hammer unions are flagged/tight
-
Pipe support(s)/bracing are properly installed
SAFTEY
-
PJSA filled out completely and properly
-
All personnel on location are correctly wearing PPE
-
Personal gas monitor worn by at least one member of each crew
-
First aid supplies are available
-
Personnel taking precautions for heat or cold
-
Fire extinguishers are available
-
Necessary windsocks have been installed (1 located at front gate & 1 located on production talk walkway)
-
Chemical containers are properly labeled
-
LOTO is in use
-
LOTO is applied properly with proper documentation
-
One call activated 48 hours but no more than 10 days before the digging
-
Hot work permit available and completed prior to commencing hot work
-
Crosswalks utilized over open ditches
-
Adequate exit available for trenches or excavations 4' deep or greater
-
Operators are certified and have certificate available for forklift/tele-handler
-
Straps and slings have been inspected and are in proper working condition
-
Any working surface above 4' from the ground must be protected by a work platform with guardrails at 42" above platform, have an intermediate rail and toe board or personal fall arrest system
-
Fall arrest system must have a full body harness, deceleration device, a lifeline, & inspected prior to each use
-
Smoking point identified outside of gate or no less than 125' away from hydrocarbon containing vessels