Information

  • The version control will be maintained by the SHEQ team and is controlled via the Safety Equipment Inspections Document 2073838157-15.

  • Station No

  • Station No

  • Document No.

  • Conducted on

  • Prepared by

  • Location
  • Personnel

The version control will be maintained by the SHEQ team and is controlled via the Safety Equipment Inspections Document 2073838157-15.

Pump Foot Step Bend Arrangement / Snor Level

  • Inspected?

  • Height to the Snor level from the bottom of the floor (mm) (Show on the sketch))

  • Draw sketch of well

  • Any Specific Observations / Comments

Suction Safety Level

  • Adjusted During Project?

  • Commissioned Trip Point - Unit 1

  • Commissioned Trip Point - Unit 2

Pump 1

  • Running Current

  • Snor Current

Pump 2

  • Running Current

  • Snor Current

  • Comments

Station Pumping Duty Set Up

Commissioned Duties (A)

  • Duty Cut In

  • Duty Cut Out

Commissioned Duties (B)

  • Duty Cut In

  • Duty Cut Out

  • Comments

Flush Valve (Record Information if not completed during Phase 1)

  • Flush Valve Present?

  • Inspected?

  • Time flush valve remained open (Seconds)

  • Does it function properly?

  • Any Specific Observations / Comments

Pressure Gauging

  • If all pressures were recorded on initial inspection please indicate below

  • Pressure Gauged?

  • Were all pressures recorded on initial inspection?

  • If 'Yes', disregard the following.

When Unit 1 Running

  • Pressure at rising main (down stream side of reflux valve) for single unit running

  • Pressure at discharge pipe work (pump side of reflux valve) for single unit running

When Unit 2 Running

  • Pressure at rising main (down stream side of reflux valve) for single unit running

  • Pressure at discharge pipe work (pump side of reflux valve) for single unit running

When Both Units Running

  • Pressure at rising main (down stream side of reflux valve on common rising main) for both units running

  • Unit 1 - Pressure at rising main (down stream side of reflux valve) for both units running

  • Unit 2 - Pressure at discharge pipe work (pump side of reflux valve) for both units running

Additional Information

  • Any other Observations / Comments / Defects

  • Take multiple photos (if required)

  • Sign

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.