Information
-
Site Address
-
Job No.
-
Conducted on
-
Prepared by
Pre-commencement Report
1.01 Rubbish/Debris
-
Has all Rubbish/debris been removed?
-
Contacr council or relevant authority to report illegal dumping
1.02 Grass/vegetation
-
Has all Grass/vegetation been cut prior to starting work?
1.03 Trees
-
Have all trees on site been removed prior to starting work?
1.04 Footpath
-
Is footpath free of Damage? (take photographs to note)
-
Please photograph damage
1.05 Kerb & Gutter
-
Is the kerb & gutter free of damage? (take photographs to note)
-
Please photograph damage
1.06 Boundary Fence
-
Is the boundary fence free of damage? (take pic to note)
-
If No, Please photograph damage
1.07 Fill
-
Does site require extra fill to be imported?
-
Please note approx loads
1.08 Cranes
-
Extra cranes required?
-
State reason(s) for extra crane?
-
Which deliveries would require extra cranes?
1.09 Power lines
-
Power lines-tiger tail insulation required?(If unsure notify WHS Manager for safety assessment)
-
WHS Manager to assess, please ensure clear wide angle photographs are taken of area of concern.
-
If Yes, please select of area cable insulation.<br>
1.10 Traffic Control
-
Is traffic control required
-
Give reasons why traffic control may be required?
1.11 Retaining Walls
-
Is a retaining wall required following site excavation?
COMMENTS
-
Comments/recommendations
Site Manager Sign off
-
I the Site Manager of above mentioned site certify items raised in this report are true and correct as of date stated on report.
Pre-commencement Report
2.00 Internal Use Only
-
Is site within 1km of the ocean or non surf coast?
-
Is site classified as tight site?(if Yes what trades will be affected?)
-
Sewer affected? (supervisor to check plans, if Yes ensure all plans are correct)
-
Are all pegs in place?
-
Is Tree protection zone required? (refer to DA condition)
-
Acquire appropriate signage from WHS Manager, ensure you sketch on Fence/barricade layout.
-
Is existing boundary fencing 1.8m high?
-
Fencing ordered?
-
Sketch boundary where temporary fence is required, please note if shade clothe is required
-
All weather access on site ordered?
-
Water on site?
-
Have you organized Safety Signage, Padlock and WHS Management Plan for site? (advise WHS Manager)
-
Have you organised Villa World promotional signage/shade clothe?
-
Is site in close proximity to school or park?(if Yes notify WHS Manager)
-
Is traffic management plan required? (refer to DA condition)
-
Will scaffold require shade cloth?(if Yes notify scaffolder)
-
Would normal deliveries be affected due to site conditions? (internal note: if Yes, supervisor to contact transport company prior to frame, brick, steel and sand deliveries)
-
Does set back requirement require pinning of slab for brickwork? (pinning required when boundary setback is less than 950, allowance for render to be made on site)
-
I have read and understood all items on DA or CDC conditions
-
General Comments, regarding DA/CDC conditions.