Title Page

Site Details and Job Information

  • VIN.Q.

  • Site Address
  • Client / Site

  • Job Title_QVIN

  • Conducted on

  • Engineers and PM

  • Prepared by

Installation

NOTE: Please read carefully before completing and signing this form. The following document will ensure that all necessary tasks that are the responsibility of the installer are completed by the Vindex Technician. Upon arrival at the site, the Commissioning Engineer will inspect the installation and set up parameters to certify that the work completed meets factory standards. This document will form part of the commissioning and handover process.

MicroPoint II Cable Installation

  • MicroPoint cable installed on the fence line in accordance with Chapter 4 of the MicroPoint II Installation Manual.

  • MicroPoint cable installed on swing gates in accordance with Chapter 4 of the MicroPoint II Installation Manual.

  • MicroPoint cable properly terminated to ALL modules and dielectric grease applied in accordance with Chapter 5 of the MicroPoint II Installation Manual.

  • Distance between cable ties securing the MicroPoint cable on the fence fabric does not exceed 9 inch (229mm) intervals.

  • Each individual MicroPoint cable is calibrated per Section 4.2.4 of the Universal Installation Service Tool II (UIST II) Technical Manual.

Module Installation

  • Processor Module II’s (PM II) are installed in accordance with Chapter 4 of the MicroPoint II Manual and site specific requirements.

  • Link Unit II’s (LU II) are installed in accordance with Chapter 4 of the MicroPoint II Manual and site specific requirements.

  • Termination Unit II’s (TU II) are installed in accordance with Chapter 4 of the MicroPoint II Manual and site specific requirements.

  • Splice Units (SU) are installed in accordance with Chapters 4 and 5 of the MicroPoint™ II Manual and site specific requirements.

  • A controller (RCM II, CM II, CM II-N, GCM II-HD, PSM, RPM II or SDK) are installed in accordance with job specific requirements.

  • Relay Output Module II’s (ROM II) are installed in accordance with site specific requirements.

  • Alarm Input Module II’s (AIM II) are installed in accordance with site specific requirements.

  • The Communications line is grounded at the JB70A (which has an earth ground), in accordance with Chapter 4 the MicroPoint II Installation Manual.

Power and Communication Wiring

  • Power Supplies are mounted and wired per job specific instructions.

  • Wiring for DC power terminated at the feed point PM II(s) and/or any AIM II and ROM II per site specific requirements.

  • RS422 communication cable is terminated at the feed point PM II and/or any AIM II and ROM II per site specific requirements.

  • RS422 communication cable is terminated at the Controller per site specific requirements.

  • All wiring from microwaves or auxiliary sensors to PM II(s) and/or AIM II’s Properly terminated per site specific requirements.

Control Room Equipment

  • AC power available for the GCM II-HD, monitor, printer, power supplies and UPS system.

  • Controller, AIM II's and/or ROM II's, UPS and/or other peripheral hardware mounted to end user's satisfaction.

  • Universal Installation Service Tool II (UIST II) software installed on customer supplied computer.

  • Printer connected to the GCM II-HD and paper installed.

  • Cabling for the controller, monitor and printer, properly dressed to the end user’s satisfaction.

Commissioning

MicroPoint II Commissioning Information

  • Processor Module II’s (PM II’s) are properly addressed per Section 5.2.4 of the MicroPoint™ II Manual and per site specific requirements.

  • All cables have been calibrated.

  • All Processor Module II’s (PM II’s) are communicating with the controller.

  • All Relay Output assignments are made per site specific requirements.

  • All auxiliary inputs have been assigned to the proper PM II, or AIM II per site specific requirements.

Enter the following Final Site Data values on the chart below for each PM II in the system.

  • Processor Module II

  • PM II
  • Processor Module II No.

  • Volts DC at PMII - VDC

System Sign Off

System Sign Off

Discrepancies/Notes

Sign Off

  • By signing this document I certify that all the above tasks have been completed in accordance with the installation specification and a fully functional commissioning, inspection and testing have been completed.

  • Vindex Systems Representative

  • Customer

PIDS System Installation

PIDS System Installation Information

  • Date

  • PIDS System

GCM-II

  • IP Address

  • Subnet Mask

  • Default Gateway

  • Passwords

Volts DC

  • PM

  • PM

ROM-II x 3

  • IP Address

  • Subnet Mask

  • Default Gateway

  • Passwords

Volts DC

  • PM

  • PM

PM-11 x 8

  • IP Address

  • Subnet Mask

  • Default Gateway

  • Passwords

Volts DC

  • PM

  • PM

LUX-II x &

  • IP Address

  • Subnet Mask

  • Default Gateway

  • Passwords

Volts DC

  • PM

  • PM

TU X 0

  • IP Address

  • Subnet Mask

  • Default Gateway

  • Passwords

Volts DC

  • PM

  • PM

PIDS Zone List

  • Zones

  • Zone
  • PM No.

  • Cable

  • Cell To/From or Beam

  • Beam Information

Zone Input/Output Test

  • Zones

  • Zone
  • Alarm Activation

  • Relay Activation

  • CCTV Activation

Commissioning Sign Off

  • Engineer

  • Customer

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.