Welcome
-
Project number
-
Site Address.
-
Location.
-
Installation carried out by?
-
Audit Carried out by?
-
Add signature
-
Audit conducted on:
-
General photo of site
Sections
1.0 Rack installation
-
1.1. Has rack Been installed as per manufactures specification
-
1.2. Has the racks been labelled according to the latest label manual
-
1.3. Does the cabling to the racks match what was on the design
-
1.4. Compliant?
-
Comments!
-
Add media
2.0 cable tray installation
-
2.1. Has the cable tray been installed as per equipment layout drawing of design?<br>
-
2.2. Has cold creep protection being installed?
-
2.3. Has the cable tray been labelled with cable tray stickers indicating weight per metre?
-
2.4 Has all sharp edges been eliminated from tray and iron work
-
2.5. Does the tray and superstructure meet TM 100 requirements
-
2.6. Is all fixings, channel, threaded rod and accessories are passivated.
-
2.7. Is the work area clean and safe?
-
2.8. Compliant?
-
Comments!
-
Add media
2A.0. Batteries
-
2A.01. Have the batteries been installed as per manufacture and Telstra requirements
-
2A.02. All battery leads and links connection bolts/nuts been crossed indicating that they have been torqued twice
-
2A.03. Battery post covers installed ensuring that there are are no exposed live parts?
-
2A.04. All Battery cells labelled with the cell number of that battery string?
-
2A.05. Battery books been left on site
-
2A.06. Battery books have been fully filled out. This includes all battery information
-
2A.07. 20 minute discharge or site load test recorded in battery books
-
2A.08. Battery BMP rating matches the value on the installed pocket label
-
2A.09 battery cabling installed neatly?
-
2A.11. Is the area neat and clean?
-
2A.12. Compliant?
-
Comments?
-
Add media
3.0. Power system
-
3.1. Power system installed as per equipment layout drawing
-
3.2. Power system labelled as per latest labelling manual
-
3.3. Power system has no alarms present?
-
3.4. Rectifiers installed match the design requirements
-
3.5. Rectifiers positioned evenly across AC phases
-
3.6. Power system rack isolated from iron work and any other IBN?
-
3.7. AC supply had been installed according to AS 3000
-
3.8. AC supply isolators labelled correctly
-
3.9. SPC bar installed in an accessible location as close to the power system as possible?
-
3.10. Pyrolam used on side and back of cabinet?
-
3.11 Does the no load zone match the structural engineers report?
-
3.12. Is the area clean and safe?
-
3.13 Compliant?
-
Comments!
-
Add media
4.0 DC cabling
-
4.1 The quantity of cable installed matches design.
-
4.2. Is the cable route subject to crushing pressures or sharp edges?
-
4.3. Does the cable route minimise bends and excessive tension?
-
4.4. Is the cable suitably protected in exposed areas?
-
4.5. Is the cable secured every 500mm in exposed areas?
-
4.8. Compliant?
-
4.7 All cable ties been cut flush with cable tie block to ensure no sharp edges are present?
-
Comments?
-
Add media
6.0. As built and commissioning.
-
6.1. We're there any issues with the overall design?
-
6.2. Have all the installation works been carried out to a high standard?
-
Comments?
-
Add media