Information

  • Site

  • Alpha Code

  • Select date

  • Location
  • For this assessment the following applies

    Safe -
    At Risk -
    Fail -

Section 1.0 - Site planning and mangement

Site Management and Planning

  • Is the site access information correct and up to date?

  • Is the Health and Safety plan on site, accessible and legible?

  • Has a hazard and risk assessment been undertaken for the site?

  • Outline areas to improve the Health and Safety plan with dates for completion

  • Select date

  • All contractors (including sub contractors) have been provided with information relating to health and safety for the work they are undertaking?

  • Is the time allowed suitable for the scope of work to be undertaken?

Summary

  • Site Management and Planning

Safety Gear

  • Hi Viz

  • Safety Helmet

  • Safety glasses

  • Appropriate clothing for the environmental conditions

  • Safety boots (or appropriate footwear for working on roofs)

  • Hearing protectors of the appropriate class

Summary

  • Safety Gear appropriate to the task is in being worn and is in good condition?

  • Principal Contractor Network Requirements

  • Vodafone Sites

  • Workers on roofs with proprietary anchor systems in place have completed US23229 and have a copy of their current certification on site?

  • Workers on communication towers, poles and roofs have completed US 23229, 15757 and 17025 and have a copy of their current certificate on site?

  • Are all persons on site competent and trained to undertake the tasks on site?

  • Work should cease until persons competent to undertake the required tasks are on site. An incident report should also be sent to the relevant Principal Contractor

Summary

  • Competency

Emergency planning and equipment

  • Is the site able to call for emergency assistance - Fire, Police Ambulance?

  • Are appropriate Fire Extinguishers on site?

  • Emergency assembly point identified?

  • Are first aid kits, current, we'll stocked and readily available?

Summary

  • Emergency planning

Environmental

  • Working hours restrictions are being adhered to?

  • Noise and vibration are kept to acceptable levels?

  • All site areas are kept tidy with litter removed from site appropriately?

Summary

  • Environmental

General

  • Have all visitors signed the visitor log?

  • Are hazards, risks and controls discussed with visitors prior to entering the site?

  • Incident report register on site and up to date?

  • Is the work site (including footpaths and roadways) clear and free from debris, rubbish and obstructions?

  • Are slip and trip hazards being adequately managed?

  • Is lighting adequate for carrying out tasks and and/or safe access?

Summary:

  • General

Section 2.0 Access to Roofs, Brittle Roofs and RF

Roof Access

  • Are persons on site working on the roof of a building?

  • An assessment has been made of any internal ladders used to gain access to the roof to ensure they are structurally sound?

  • Handrails are in place for ladders if required?

  • Ladders extends 1 metre above the landing platform?

  • Portable ladders meet AS/NZS 1892?

  • Portable ladders are secured at the top and the bottom?

Summary

  • Access to Roof

Brittle Roofs (Skylights, Asbestos Roofs, Openings, Roofs in Poor Condition)

  • Is the roof surface brittle, in poor condition or has skylights?

  • An assessment of the roof has been made to ensure it is strong enough to support the work activities being carried out. (Asbestos roofs are the majority of brittle roofs).

  • Are areas such as skylights, roof openings designated as no go zones and barricaded off or covered if required?

  • Are walkways with guardrails provided when work on fragile roofs cannot be avoided?

  • If walkways are not provided is a fall arrest system being used?

  • Work on the roof must stop until safe work methods are in place.

Summary

  • Brittle Roofs

RF

  • Are there RF hazards on site?

  • RF warning signs are in place at access points?

  • Ensure that a report is made to the Mobile Company concerned that signs are not present.

  • Are persons trained/competent/certified in RF Awareness

  • On co location sites, other mobile company antennae have been considered when planning the work?

  • Have adjacent buildings be assessed as a possible source of RF?

  • Are RF monitors calibrated?

  • Are appropriate RF monitors available and being used?

  • RF procedures and monitoring practices have been followed?

  • Spark RF Shutdown Procedure ND4027 Ver 6.0 has been followed?

  • 2 Degrees

  • Vodafone

Summary

  • RF

Section 3.0 - Equipment used for Working at Heights on Towers, Poles and Roofs

Machinery for working at Heights on Towers, Roofs and Structures

  • MEWP, Crane Scaffold or Guardrails being used on Site?

  • Move to the next section

  • Are workers on the ground wearing appropriate PPE e.g. Safety Helmets, Safety Boots, High Viz Vests and Eye Protection?

  • Have exclusion zones been implemented and sufficient for the tasks being carried out?

  • Do the exclusion zones prevent members of the public accessing the site?

  • Assess any of the following equipment on site

  • Mobile Elevated Work Platfrom

  • Has the operator carried out a carried out a pre start inspection of the MEWP that includes functional and visual tests (required each day)?

  • Is the MEWP clearly marked with the rated lifting capacity

  • Weight of lift?

  • Essential operating and maintenance instructions permanently displayed or stored in a conspicuous place on the MEWP?

  • Is the six monthly inspection certificate displayed?

  • Operator is trained and competent (US 23966 v1) and the corresponding unit for the type of MEWP being used?

  • Hazards associated with power lines are appropriately controlled (no closer than 6.4 metres, or between 4 - 6.4 metres with appropriate controls in place. No work can be carried out within 4 metres of a power line without the written consent of line owner and this consent must remain on site at all times?

  • Weather conditions are suitable for using the MEWP?

  • Are harnesses, lanyard and attachment points available to all workers undertaking tasks from the MEWP?

  • Is the MEWP set up on firm and level ground?

Summary

  • MEWP

  • Crane

  • Is the plan and information provided by the crane supplier signed and accepted by the contractor on site?

  • Is the crane set up on firm, level ground with barriers in place?

  • Safe working distances are maintained from overhead power lines?

  • No persons are standing under suspended loads?

  • Tag lines are used where there could be load spin?

  • The load does not exceed the lifting capacity of the crane

  • Lifting capacity of the crane

  • Weight of lift

  • Clear lines of communication exist between the dogman/persons in bucket and the crane operator?

  • Weather conditions suitable for the use of a crane?

Summary

  • Crane

  • Scaffold or Mobile Scaffold

  • Are the surface conditions suitable for scaffold access and stability - e.g level and safe to work on?

  • Is there a health and safety management plan on site that clearly identifies those responsible for implementing control measures for the scaffold?

  • Are site specific hazards e.g proximity to power lines and control measures included in the Safe Work Method Statement or JSA?

  • The scaffold was erected, altered or dismantled by a person(s) who have been trained and have suitable experience with the type of scaffold being used?

  • Are the wheels locked and turned out on mobile scaffolds?

  • If a portion of the scaffold is above 5 metres above the ground the following conditions must be met

  • The person assembling, altering or dismantling the scaffold have a certificate of competence

  • Scaffold inspection card/register (Safety Tag) clearly visible in place by the access ladder and checked weekly?

  • Notification has been sent to WorkSafe NZ

  • The maximum load (weight of workers and materials) has been determined and the scaffold is capable of supporting the weight

  • Edge protection provided where a person could fall 2 or more metres

  • Scaffold protected from passing vehicles or plant

  • Ladders are secured top and bottom.

  • Ladder extended 900-1000 mm above the landing platform.

  • Planks are in good condition, 3 planks minimum and butted and secured.

Summary

  • Scaffolds

  • Edge Protection?

  • Designed and constructed to by a competent person?

  • Positioned appropriately?

  • Will barriers and guard rails be regularly inspected

  • Includes a toe board or mesh infill to prevent tools, materials and debris falling from the roof?

  • Not used on a roof with greater than 35 degree slope (In this instance a MEWP, or Fall Restraint/Arrest system must be used)

Summary

  • Edge protection

Section 4.0 - Fall Restraint and Fall Arrest

Fall restraint and fall arrest systems

  • Are fall restraint or fall arrest systems being used on site?

  • Move to the next section

  • All personnel trained and certified for working at height?

  • Has the rigger undertaken a visual inspection of the structure, pole etc prior to work commencing?

  • Is each person familiar with the work plan?

  • Are personnel attached at all times while working at height?

  • Has a drop zone been implemented and sufficient for the tasks being carried out?

  • Is all equipment secure to prevent a fall from height?

  • Does each member of the team have the required PPE?

  • Riggers gloves

  • A rescue, climbing or caving safety helmet

  • Self rescue kit carried

  • Clothing to suit the environmental conditions

  • Eye protection from glare and also flying objects/particles.

  • First aid kit?

  • Boots that are appropriate to the task ( AS 2210)

  • Is there a written rescue plan that is known to each member of the team?

  • Two certified rescue climbers are on site at all times?

  • Notification has been sent to WorkSafe NZ of the work?

  • Are all members of the team trained and competent for the tasks they are carrying out?

  • Has a SWMS or JSA been prepared for height work on site?

  • Are there established safe access pathways to the anchor points?

  • Is a certified fall restraint system available for use?

  • If using a fall arrest system are suitable certified anchor points being used?

  • Date anchor points certified to?

  • Certified load?

  • If certified anchor points are not available a Temporary Anchor Point Permit must be completed and a copy held on site

  • The temporary anchor point permit has been signed by a competent rigger?

  • Rope access work must cease until the permit is completed

  • The temporary anchor point permit has been signed by the rescue climber?

  • Rope access work must cease until the permit is completed

Summary

  • Fall restraint and fall arrest

Section 5.0 - Other Safety Critical Risks

Pedestrian and Public Safety

  • Are members of the public/pedestrians passing the site?

  • Is a spotter required on site?

  • Is safe pedestrian access maintained on site at all times?

  • Are appropriate barriers in place that create a safe zone around activities that involve working at height?

  • When plant and machinery are in operation (e.g. MEWP, Crane, Container Delivery) these are isolated from the general public?

  • Work vehicles are parked safely?

Summary

  • Pedestrian and public safety

Electrical Safety

  • Is electrical work being undertaken on site?

  • Procedures are in place for ensuring electrical equipment is de-energised before electrical work is carried out and methods in place to ensure that it cannot <br>be inadvertently re-energised (isolation, tagging and lockout)?

  • Persons conducting work on electrical equipment are appropriately trained, registered and hold a practising license for the type of work being undertaken?

  • Proven to be de-energised before work commences?

  • Only ladders constructed of timber or fibreglass are to be used for work on or near electrical apparatus?

  • All electrical equipment, extension leads and portable power tools are in good condition and regularly inspected, tested and tagged?

  • Undertaken a CPR course (within the last 12 months) and Basic First Aid course (within the last 2 years)?

Live electrical work

  • Is live electrical work being undertaken on site?

  • A risk assessment and safe work method statement has been prepared before any live work is undertaken?

  • When working on or near live electrical apparatus the following Safety Gear (PPE) is being worn

  • Clothing covers the body from neck to wrist to ankle, (cotton)

  • Sleeves rolled down and shirts tucked into trousers (protecting against entanglement and arc flash)

  • Non metallic fasteners (or fasteners are protected by a layer of the same material as that of the garment)?

  • Suitable eye protection?

Summary

  • Electrical

Traffic Management

  • Is the worksite in the road corridor or subject to frequent vehicle movements?

  • Copy of the traffic management plan signed by the contractor and maintained on site?

  • Traffic management setup is correct and according to the TMP?

  • STMS contact number listed?

  • Is there an escape route for the traffic controller?

  • Comes and barriers in good condition?

  • After hours TMP in place if necessary?

Summary

  • Traffic Management

Section 6.0 - Health and Safety Summary

Summary

  • If any of the following areas are not being managed appropriately then work at the site should be halted until the area(s) of concern are addressed.

  • Site planning and management

  • Roof access, brittle roofs and RF

  • Equipment and plant for working on towers, roofs and structures

  • Fall restraint, arrest and anchor points

  • Pedestrian, Public and Traffic Safety

  • Competency of workers on site?

  • Are any other hazards present on site, list below

  • Are these hazards and risks being appropriately controlled?

  • Were any unsafe work practices observed at the time of the assessment

  • Please describe the unsafe practice observed below

  • Comments -enter below

Agreement

  • Required corrective actions

  • Agreed date for completion of corrective actions

  • Assessor

  • Company

  • Site representative

  • Company

  • Select date

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.