Information
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
Principal Contractor
-
Principal contractor?
Previous inspection signed off
-
Has the previous inspection points raised been signed off<br>
-
Actions outstanding are now
General site conditions
-
Are work areas secure and have barriers to secure the work area from unauthorised access
-
Are the works areas clear of slip trip falls, debris, protruding nails.<br>
-
Is house keeping good, clean and tidy.
Plant and equipment
-
All driven plant was used correctly. Keys removed if not in use. Seat belts were worn. Parked or driven in a safe manner, in accordance with the traffic management plan.
-
Equipment being used is in sound condition and fit for purpose.
-
Unsafe actions.
Emergency arrangements
-
There were First aiders on site relative to the risk. First notice displayed and up to date.
-
There was fire fighting equipment on site. Fire assembly point was displayed. Smoke detectors in canteen, fire blanket in the canteen.
Management procedures.
-
Safety signs and poster including F10 where applicable
-
Training certificates were on site for operatives using plant and equipment.
-
Site inductions and tool box talks have been completed for operatives on site.
-
Site registers, are up to date and completed according to the CDM REGS 2007
-
Permits required for current works on site.
-
Copies of services are on site and marked up.
-
Certificates for plant were on site, including chains etc.
-
Management procedures are in place to reduce the risk of HAVS.<br>PRE Selection of equipment below 10 ms, details recorded on ACS HAV record sheet .
Environmental
-
Environmental procedures in place.
-
Spill kits and drip trays on site .
Personal Protective Equipment
-
All operatives on site were wearing Head Protection, in good order, the correct way round.
-
Operatives were observed wearing hearing protection correctly. They understood the requirement to wear them and dangers if not worn whilst working in noisy environment.
-
Operatives were observed wearing RPE. Correct type for the works, FFP3 for silica. Face fit tested and clean shaven.
-
Safety googles or glasses were being worn for the correct operation.
-
Gloves fit for the task were worn. <br>Where mandatory requirement of the principal contractor.
Traffic Management
-
Traffic management plan is in place, displayed and being followed
Welfare on site
-
Is the welfare compliant with CDM 2007 ACOP L144 schedule 2<br>Hot and cold running water, means for heating food, seats with backs, drinking water,
-
Is there sufficient toilets for the number of operatives on site, with means for washing, soap, barrier creams and drying hands.
-
Is the drying room clean and tidy, heaters obstructed or covered, pegs for hanging wet clothes.
Work at height
-
Is work platforms compliant with Work At Height Regulations 2005
-
Has work platform been signed off by a designer if applicable.
-
Has work platforms been signed off inspected once in seven days
-
Is there good access and egress from work platforms, including for emergencies ?
-
Are ladders secured, tied off, in good condition, at correct angle ?
-
Are ladders used
Lifting operation
-
Is there a lift plan in place, signed onto by all involved.
-
Has the crane been checked before use?
-
Is the remote control secure and or under supervision of crane operator?
-
Are lifting operations being completed as per plan?
-
Is there good communication between signaller and crane operator?
Other work activities.
-
Are other works being completed in a safe manner?
Signatures.
-
Signed by site supervisor
-
Signed by Martin Lawrie, Safety Manager
-
Remedial action to be completed by
-
Add drawing