Information
-
Audit Title
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Customer Service Area
-
Viscore/ Job Number
-
Responsible Manager
-
Auditee
-
Company
1.000 Design
-
1.004 NetMAP ND0381 3 Network to be relinquished (in NetMAP) removed <br>
-
1.006 NetMAP ND0381 3 Historical records impacted by new design rectified, connectivity & integrity ok. <br>
-
1.010 Consents 3 Consents: Permits received, eg RMA, RON, Bridge etc. All Fees Paid <br>
-
1.012 Financials 3 Work priced correctly using Template, FS codes / quotes as applicable. <br>
-
1.018 Proactive Design 2 Hessian/known faulty cable along direct route of any lay/thrust considered for replacement. <br>
-
1.019 Proactive Design 2 Replacement cables outside construction zone meet current Proactive Guidelines <br>
-
1.020 Proactive Design 2 Any effecting multiples within joints being accessed are to be demultipled. <br>
-
1.022 Costs 2 Billed tasks actually done <br>
2.000 Handover & Collateral Delivered to Chorus
-
2.001 Procedure 5641 3 Handover procedure followed, WATCH form applied <br>
-
2.002 Commissioning 5641 2 Commissioning information meets specified requirements <br>
-
2.003 RFS and DDC 5641 1 Timing correct for RFS and DDC. Recommits meet business rules <br>
-
2.004 Compliance Certificates 5641 1 Compliance certificates available (RMA, PTW, RON, TMP, Electrical) <br>
-
2.005 Codes 2 Deployment codes & Template pricing applied correctly <br>
-
2.006 Work Plan 4501 1 Work Plan / H&S /Technical Procedure / PTTN Accreditation approved / Access Card current <br>
-
2.007 Spares 2 Spares visible and appropriate when required <br>
-
2.008 Records Integrity 2 TLRD/NetMAP updated, integrity checked & confirmed <br>
-
2.009 Records Integrity 2 Bearer connectivity confirmed "end to end" <br>
-
2.010 Records Integrity 2 Graphical Records & Databases identified & updated <br>
-
2.011 Records Integrity 2 ICMS updated <br>
-
2.012 Records Integrity 2 Have transmission limits been met. (Wireline tool) <br>
-
2.013 Records Integrity 2 Traid updated <br>
-
2.014 Records Integrity 3 Does the NMR record match equipment on site. (NMR move/add/change captured and updated when appropriate). <br>
-
2.015 Records Integrity 7388 2 OTDR traces (all cable fibres @ 1310 & 1550nm wavelength) confirmed delivered to Chorus <br>
-
2.019 CNSP 2 <br>All network items defined within the Chorus Network Specified Product (CNSP) process are used in the network. No non approved items used<br>
-
2.020 Records Integrity 3 Plant Damage Report (PDR) form completed <br>
-
2.020 Records Integrity 3 Plant Damage Report (PDR) form completed <br>
-
2.021 Records Integrity 2 Cable Network Alteration (CNA) form completed <br>
-
2.022 Records Integrity 2 Cable Plant Alteration (CPA) forms completed <br>
4 Codes
-
4.001 TFD 3 Correct TFD code used <br>
-
4.002 CSE 3 Correct CSE code used <br>
-
4.003 ACT 3 Correct ACT code used <br>
-
4.004 Correct Statement of Work codes used
5 Fault
-
5.001 NTS test result (Good Line)
-
5.002 Records - Customer information & cable pairs correct, changes updated
-
5.003 Any Pair change meets current rules
-
5.004 OUT Fault Ticket text field completed - first name, surname initial, fault cause, fault resolution, location of repair incl. street no., name of end customer if contacted. If applicable: reason for uneconomic repair, billing information S&S doc no., PDR no., NFF NVF no.
-
5.005 First Time Fix principles applied. Fault repaired but there was another service affecting issue that could have been fixed and wasnt.
-
5.009 Escalation procedure followed (Defect Referral)
-
5.010 Desktop Check 2 <br>Spares levels maintained, faulty spares referred for repair, faulty card description accurate, local spares used replaced from national holdings.<br>
6.000 Work Areas & Safety
-
6.001 Site 1 Personal and site safety procedures observed <br>
-
6.002 Hazards 1 Hazards identified & recorded - Worksite audit form completed / Hazard Notices in place <br>
-
6.003 Traffic 1 Transit TMP provided <br>
-
6.004 Services 1 Services located <br>
-
6.005 Clearances 1 Power and Gas clearances correct <br>
-
6.006 Confined Space 1 Gas Detector - within current calibration certificate <br>
-
6.007 Confined Space 1 Gas Detector - measures for O2, Flammable, Carbon Monoxide (& Hydrogen Sulphide in volcanic areas) <br>
-
6.008 Network 2 Network security correct (Exchange) <br>
-
6.009 Confined Space 2 Joint Chamber / Manhole lids closed and secure <br>
-
6.012 Temporary Work 2 Temporary work clearly labelled and contains name, contact details, job ID of person involved. <br>
10 Pride & Logs
-
10.002 MDF Log completed in exchange
-
10.004 Cabinet 3 Cabinet Log completed <br>
13 Cable Haul (7476, 7475, 7474)
-
13.001 Correct cable installed as per project pack
-
13.002 Cable drum managed on site safely
-
13.003 Correct duct used, always use adjacent duct at through manholes if possible
-
13.004 Pulling in cable guide used
-
13.005 Cable lubricated prior to pulling
-
13.006 Is the winch capable of controlling haul tension within 2KN for fibre
-
13.007 Ducts cleaned and tested
-
13.008 Correct method used blow / suck
-
13.009 Communication method adequate (H&S of staff)
-
13.010 Cable Haul 7416 2 Subduct (to be used) cut correctly and reamed <br>
-
13.011 Cable Haul 7416 2 Subducts in manholes/joint chambers managed/not obstructing manhole plant <br>
-
13.012 Cable Haul 7416 2 Grouped PE subducts anchored at entry to MH <br>
-
13.013 Cable Haul 7416 2 Spare PE subducts capped <br>
-
13.014 Cable Haul 7416 3 Subduct with cables labelled <br>
-
13.015 Cable Haul 7416 2 Correct subduct joiner used <br>
-
13.016 Cable Haul 7416 2 ALL cable ends sealed with Heatshrink, coiled and secured ready for use <br>
-
13.017 Cable Haul 7416 1 400pr cable and above pressurised (pre pull 70kpa/ post pull 70kpa) <br>
-
13.018 Copper cable sufficient slack left for manhole management & jointing
-
13.019 Cables identified / labelled
-
13.02 Fibre cables at intermediate manholes secured with split PE subduct to MH wall
-
13.021 MaxCell installation only between adjacent MH. MH working area not impeded
-
13.022 Fibre cable prepared for joint correctly in manholes (cable management tidy to cable loop brackets)
-
13.023 Manhole / joint chamber lids free of material / Bung in lifting hole / lid locked
-
13.025 RMA: Contaminated manhole water collected for disposal
14 Cable Removal
-
14.001 Correct cables identified
-
14.002 Withdrawing method correct
-
14.003 Cable recovered for disposal (Scrap process) correct
15 Cable & Duct Lay
-
15.001 Duct 6471 2 Ducts laid or directional drilled at least 1000mm in State Highway <br>
-
15.002 Duct 6471 2 Ducts laid or directional drilled between 450mm and 1000mm in footway <br>
-
15.003 Duct 6471 2 Ducts laid or directional drilled between 600mm and 1000mm in roadway <br>
-
15.004 Duct 6471 2 Duct alignment and configuration correct <br>
-
15.005 Route position to plan
-
15.006 Cable 6471 2 Correct cables identified and installed <br>
-
15.007 Cable 6471 2 Cable ends sealed with heatshrink <br>
-
15.008 Cable 6471 2 Warning tape installed <br>
-
15.009 Cable 6471 2 Buried cable crossings - depth and protection <br>
-
15.010 Cable 6471 2 Reduced cover - protection installed <br>
-
15.015 Manhole / joint chamber lids free of material / Bung in lifting hole / lid locked
-
15.016 Fibre 6471 2 Fibre Cable Installation: Metallic cable location cable installed <br>
-
15.017 H&S 6471 2 Location cable separated into RLG pillars either side of fibre joint location (pillar minex applied) <br>
-
15.018 Bridge 6471 2 Bridge crossing: Best on downstream side and conforms to consent specifications <br>
-
15.019 Bridge 6471 1 Bridge crossing: Cable protection secure from bird/rodent access & extends into ground each side <br>
-
15.020 Bridge 6471 2 <br>Bridge crossing: U channel, brackets, covers and pipe galvanised. All anchor bolts and fittings robust and secure<br>
-
15.021 Cable 6471 2 Route markers installed (Rural only) <br>
-
15.022 Fibre 6471 2 Rural: 1/2 round installation (fibre cable) each side of culvert/ drain crossings <br>
-
15.023 Rural: 1/2 round installation for rural fibre joint location
-
15.024 Customer 6471 2 Rural: Private property owner aware cable within property boundaries <br>
-
15.026 Duct ND0545 2 <br>Duct at customer boundary for direct install fibre sealed and buried or housed in approved enclosure (eg Pedestal)<br>
17 Manhole & Joint Chamber Installation & Ducts
-
17.001 Manhole preparation, bedding, backfill compacted OK
-
17.002 Manhole sited correctly - To plan and parallel to B/L
-
17.003 Manhole correctly sized as per Design Job Specification
-
17.004 Manhole frames flush to ground, no trip hazard
-
17.005 Manhole stripped of formwork, no protruding nails left
-
17.006 Manhole throat (where fitted) correct diameter & does not obstruct access
-
17.008 Concrete panel joints sealed to prevent silt and water ingress
-
17.009 Manhole floor level, sump hole fitted
-
17.01 All manhole duct entry grouted, duct reamed, sits flush to wall
-
17.011 Non concrete joint chamber duct entry protrudes into chamber 50mm, reamed, sealed to wall
-
17.012 Manhole cable management brackets installed to accept arms
-
17.013 Manhole cable management arms installed as required
-
17.014 Manhole / joint chamber lids are locked, in working order and rubber bung fitted
-
17.015 Ducts entry positioned close to adjacent wall for easy cable management
-
17.016 Ducts sealed where necessary to prevent the ingress of water, moisture, gas, pests into buildings and cabinets
-
17.018 Duct 7414 2 Cable or sub duct entry sealed to Feeder Duct <br>
-
17.019 Duct 7414 2 Cable exiting from sub duct sealed <br>
-
17.020 Duct 7414 2 Unused Feeder Ducts plugged/sealed <br>
18 Manhole Cable Management
-
18.001 All cables managed tidily on brackets and arms
-
18.002 Fibre cable prepared for joint correctly in manholes (cable management tidy to cable loop brackets)
-
18.003 Fibre cable protection when required-tread plate/split subduct/bandit tape
-
18.004 Fibre closure secured to MH wall with bracket
-
18.005 Pressurised cables and tails OK, no weak points of failure
20 Copper Cable Jointing
-
20.001 Cables pressure maintained
-
20.002 Cable at correct depth & sheath free from damage
-
20.004 Cable excess length sufficient
-
20.005 Correct jointing connectors & tool used
-
20.006 Cable 2 Temporary closure adequate <br>
-
20.008 No obstruction of spare ducts
-
20.009 Duct 7411, 7414 2 Spare exchange ducts sealed where necessary to prevent the ingress of water, moisture, gas, pests <br>
21 Copper Heat shrink Closure (incl PEDCAP & Radi)
-
21.001 Closure sized correct
-
21.002 Cable entry prepared; Clean, Abrade, Flame Brush, alu foil
-
21.003 Cable position at entry correct; largest on top
-
21.004 Branch Clip or SCOP use correct
-
21.005 Thermal colour change even, white line visible down SS channel
-
21.006 Sufficient glue extruding at ends
-
21.007 Pressurised closure has pressure valve fitted/test OK
-
21.008 Closure management; manhole arms or direct buried has protective slab
23.000 Pressure
-
23.001 Pressure 2 Air dryer location adequate with fresh air supply <br>
-
23.002 Pressure 2 Air dryer not bolted to floor <br>
-
23.003 Pressure 2 Polycor tubing & joints managed, no leaks evidenced <br>
-
23.004 Pressure 2 Each cable on flow panel clearly labelled <br>
-
23.005 Pressure 2 Humidity Alarm within boundaries <br>
-
23.006 Pressure 2 Service manual available on site <br>
-
23.007 Pressure 2 Main air block at cable well installation correct <br>
-
23.008 Pressure 2 XTAP (air delivery to cable) install/size OK <br>
-
23.009 Pressure 2 Air dryer alarms within boundaries (Check with NOC) <br>
-
23.010 Pressure 2 Maximum 70kpa delivered at start of network <br>
-
23.011 Pressure 2 Minimum 35kpa available at end of network <br>
-
23.012 Pressure 2 Cable transducer location min 200mtr/max 600mtr apart <br>
-
23.013 Records Integrity 3 ICMS updated with transducer cable pair details <br>
-
23.014 Records Integrity 2 Chorus Master Pressure Database updated <br>
-
23.015 Codes 2 Sign off codes (TFC 5B*) <br>
-
23.016 PTW ND0479 2 Permit To Work <br>
-
23.017 H&S HCP027 2 Dry Air Cylinder management OK (HCP027) <br>
24 SSA (7455 / 7517)
-
24.001 SSA cable binding to hardware correct
-
24.002 SSA cable erected correctly
-
24.003 SSA cable type and size correct
-
24.004 Earth 2 Earthing requirements (16mm/pipe/rod/C-Lok each end) correct when needed <br>
-
24.005 SSA 2 End terminations and cable management correct <br>
-
24.006 SSA 2 SSA tension & sag & twist (anti dancing) correct <br>
-
24.008 SSA 3 Recovered wire or SSA uses scrap process <br>
25 Poles
-
25.001 H&S 1 All mechanical aids in good working order, regular checks <br>
-
25.002 H&S 1 Vehicle transporting poles must have racks for pole security <br>
-
25.003 Pole in good condition, no splits, burs
-
25.004 Pole manufacture label in place, Pole strength minimum 6kn
-
25.005 Pole hole depth correct/Pole vertical and height correct
-
25.006 Pole positioning and spacing correct, correct face position
-
25.007 All new poles have Network pole tag installed 3mtr above ground
-
25.008 Poles 2 Breast & Heal block position correct for pull & loading on pole <br>
-
25.009 Reinstatement 2 Pole hole compacted every 150mm <br>
-
25.01 Pole safe to climb (hammer/probe/dig)
-
25.011 All metal plant hot dipped galvanised & CNSP approved
-
25.012 Plant positioned correctly and safely, plant clearances correct
-
25.013 Poles 2 Stub poles or staying lines or screw anchors installed correctly <br>
-
25.014 H&S 1 Unsafe poles labelled / marked for replacement/7 days <br>
-
25.015 H&S 1 Unsafe poles noted in Hazardous Pole Register <br>
-
25.016 Records Integrity 2 Deeded poles shown in NetMAP Pole Editor <br>
-
25.017 All tagged poles in NetMAP
-
25.018 H&S 1 Traffic Management Plan for pole install/removal <br>
-
25.021 Labels 2 Network labelling in place to suit requirements <br>
31 Active Cabinet Internal RHS
-
31.001 Cabinet 2 Outer Door lock works smoothly and door closes without jamming <br>
-
31.002 Door stays are in place and all work well
-
31.004 Soft foam seal plate secured. Cable entry prevents vermin/insect entry.
-
31.006 MDF; Correct Modules installed
-
31.007 MDF; Module Labelling correct
-
31.008 MDF; Data card for jumper running data (laminated or in a card holder attached to the inside of door)
-
31.009 MDF; Cabinet E-side Termination data card in door.
-
31.01 MDF; Jumper correct type (BL/WH)
-
31.011 MDF; Jumper run correctly (50mm slack & no excess)
-
31.016 Bottom LHS Earth bar strapped to each MDF vertical and the base of the cabinet
-
31.020 MDF 2 MDF; Jumper terminated correctly <br>
-
31.021 Security 2 Door seals in good condition <br>
-
31.023 Reinstatement 3 MDF: All dead jumpers removed <br>
37 Passive Copper Cabinet
-
37.001 Outer Door lock works smoothly and door closes without jamming
-
37.002 Door stays are in place and all work well
-
37.003 Cabling run correctly
-
37.004 Distribution Frame: Correct Modules installed
-
37.005 Distribution Frame: Module Labelling correct
-
37.006 Distribution Frame: Data card (laminated or in a card holder attached to the inside of CCC door)
-
37.007 Distribution Frame: Cabinet Laminated E-side Termination data card in door.
-
37.008 MDF; Jumper correct type (BL/WH)
-
37.009 MDF; Jumper run correctly (50mm slack & no excess)
-
37.01 MDF: All dead jumpers removed
-
37.011 Module support bars, separators and cover in place
-
37.013 Lightning protection installed (when specified) or reinstated after testing
-
37.014 All duct seals in place
-
37.015 Concrete around ducts in base of cabinet
-
37.016 Locks & hinges OK
-
37.017 Door seals in good condition
-
37.019 MDF 2 MDF; Jumper terminated correctly <br>
38.000 UFB Fibre Flexibility Point (FFP)
-
38.001 Security 2 Outer Door lock works smoothly and door closes without jamming <br>
-
38.002 Security 2 Door stays are in place and all work well <br>
-
38.003 Cable 2 Cabling run correctly <br>
-
38.004 OFDF 2 Distribution Frame: Correct Trays installed <br>
-
38.005 Records Integrity 2 Distribution Frame: Drawer Labelling correct <br>
-
38.006 Records Integrity 2 Distribution Frame: Data card inside of drawer <br>
-
38.008 Earth 2 All microducts earth terminated <br>
-
38.009 Earth 2 All microduct earths labelled <br>
-
38.010 Security 2 All duct seals in place for cable entry (100mm) <br>
-
38.011 Duct 2 Concrete around ducts in base of cabinet <br>
-
38.012 Security 2 Locks & hinges OK <br>
-
38.013 Security 2 Door seals in good condition <br>
-
38.016 OFDF 2 Splitter installed and labelled <br>
-
38.017 OFDF 1 All unused connectors capped <br>
-
38.018 OFDF 2 Splitter leg parking bay <br>
-
38.019 Cabinet 2 All micro ducts sealed <br>
-
38.020 Cabinet 2 All micro ducts labelled <br>
-
38.021 Cabinet 2 Fixed fibre strain relief installed <br>
39 Aerial Terminal
-
39.001 Correct terminal used
-
39.002 Terminal mounted and secured correctly
-
39.003 Quiet Front terminal has sufficient gel
-
39.004 Terminal lid secure
-
39.005 Terminal label on lid or plate on pole
-
39.006 Lead-in entry correct
-
39.007 Lead-in terminated correctly
-
39.008 Plastic bag on multi-pair lead-in cable unused pairs
-
39.009 Cable shield installed
-
39.010 Terminal 2 Non working pairs capped <br>
-
39.011 Terminal 2 Sufficient slack length <br>
40 Pillar Terminal
-
40.001 Pillar - vertical, firm, depth
-
40.002 Pillar ID correct
-
40.003 Lid secure
-
40.004 Lead-in thru base only
-
40.005 Plastic bags installed & secure
-
40.006 Foam bung fitted
-
40.007 Minimum sheath height 50mm (30mm if in concrete and/or uneconomic to repair, 80mm for V3)
-
40.008 Coloured zip ties to 25 pair groups (not too tight)
-
40.009 Correct cable used
-
40.01 Correct connectors used
-
40.011 Circuit dedicated
-
40.012 Service Lead labelled correctly
-
40.013 Unused pairs capped
-
40.014 Damaged conductors repaired
-
40.015 Faulty connectors replaced
-
40.016 Encapsulated loop resealed correctly
-
40.017 V3: Lead-in customer and network labels OK
-
40.018 Green cable tie on exchange side
-
40.019 Customer 2 Service Lead - flying leads installed and correct <br>
-
40.020 Cable 3 Unused pairs connected through <br>
-
40.021 Pillar 2 Connectors >50mm from ring cut <br>
41 BDD Terminal
-
41.001 Pit lids secure/locked, with bung fitted where appropriate
-
41.002 Pit installed correctly
-
41.003 Radi: Base & lid clean, O ring seated correctly, O ring replaced upon entry
-
41.004 O/J lid labelled
-
41.005 Radi is correctly installed, thermal change and lead in
-
41.006 2m loops at BDD pits
-
41.007 2m insulated tail installed at last BDD
-
41.008 Plastic bags installed & secure
-
41.009 Coloured ties to 25 pair groups
-
41.01 Correct cable used
-
41.011 Correct connectors used
-
41.012 Circuit dedicated
-
41.013 Service Lead labelled correctly
-
41.014 Unused pairs capped
-
41.015 Damaged conductors repaired
-
41.016 Faulty connectors replaced
-
41.017 Cable 3 All cables, including lead-in cables, shall be zip-tied or taped together in a tidy loop within BDD pit. <br>
-
41.018 BDD 2 Minimum sheath height 50mm <br>
-
41.019 Customer 2 Service Lead - flying leads installed and correct <br>
-
41.020 Cable 3 Unused pairs connected through <br>
-
41.022 BDD 2 Connectors >50mm from ring cut <br>
42 PDS Terminal
-
42.001 Pedestal - vertical, firm, depth
-
42.002 Correct size pedestal used
-
42.003 Lid secure
-
42.004 PDS network labelled correctly
-
42.005 Designed pair arrangement correct
-
42.006 QF terminal labelling correct
-
42.007 QF terminal secured to backing plate
-
42.008 Foam bung fitted
-
42.009 Adequate gel in quiet front
-
42.01 Service Leads installed correctly
-
42.011 Service Lead labelled correctly
-
42.012 Customer 2 Service Lead terminated correctly <br>
-
42.013 PDS 3 Unused pairs capped <br>
43 Aerial Service Lead
-
43.001 Correct Service Lead used
-
43.002 No In span joints
-
43.003 Tension, sag and twist correct
-
43.004 Correct pole fittings used and installed (screw eyes, sash clamps)
-
43.005 Lead-ins enter terminal correctly
-
43.006 White pipe down poles
-
43.007 600mm saddle spacing or 1500mm bandit spacing
-
43.008 Roadway crossing min 5.5m height, elsewhere 4.25 metre height
-
43.009 Loops on poles tied
-
43.011 Lightning protection runs >500 metres
-
43.012 Correct building fittings used (screw eyes, sash clamps)
-
43.013 Pole 2 Servi seal secured in upright position and Gel Snap secured horizontally <br>
-
43.014 Service Lead 3 Unused pairs capped <br>
44 Buried Service Lead
-
44.001 Service Lead terminated correctly
-
44.002 20mm pipe connected at Pedestal correctly - (bend into pedestal)
-
44.003 20mm pipe connected at BDD correctly (50mm into BDD pit, 450mm deep)
-
44.004 20mm pipe connected at RLG correctly (at base of DP, bend if room)
-
44.005 Individual pipe & cable for installs of <100 metre
-
44.006 Direct buried cable option (no pipe) for > 100 metre
-
44.007 Green 20mm installed in trench
-
44.008 White pipe above ground level
-
44.009 Depth correct (450mm cover)
-
44.01 Power/ Gas clearances correct
-
44.011 Cable & pipe repair correct
-
44.013 Pipe connected at ETP correctly (not glued)
-
44.014 Overlay of Service Lead justified
-
44.015 Customer 2 Service Lead labelled correctly <br>
45 ETP
-
45.001 ETP physical alignment correct, all fittings secure, installation tidy
-
45.002 ETP location: (buried lead in-300-1500mm) (AE lead in on facia/under eaves)
-
45.003 ETP recessed (within cladding) location: 900-1500mm
-
45.004 Aerial lead in to ETP correct eg termination hardware, position, tidy appearance
-
45.005 20mm pipe to ETP is white only
-
45.006 20mm pipe end (within ETP) is sealed with silicone and drainage holes left clear
-
45.007 Premise cabling exit via back of ETP
-
45.008 Premise cabling exit from ETP is sealed with silicone
-
45.009 All connections via gel filled connectors
-
45.010 ETP 1 Protected ETP: Lightning arrestors fitted in areas that require protection <br>
-
45.011 ETP 1 Protected ETP: Earth wire (6mm/green coating) 100mm min. bend radius observed <br>
-
45.012 ETP 1 Protected ETP: Earth wire kept straight to Copper or Stainless Steel Earth rod <br>
-
45.013 ETP 1 Protected ETP: Earth wire connection to earth rod with C-Lok product only <br>
-
45.016 ETP 2 Unused pairs capped <br>
51.000 Open Aerial
-
51.001 H&S 1 Safety precautions (traffic mgmnt, ladders, belts, ropes, heaving lines <br>
-
51.002 H&S 1 Poles tested, firm & secure <br>
-
51.003 Open Aerial 2 Aerial wires regulated correctly <br>
-
51.004 Open Aerial 2 Open aerial terminations and bindings correct <br>
-
51.005 Open Aerial 2 Supporting hardware in good condition <br>
-
51.006 Open Aerial 2 Supporting arms in good condition <br>
72.000 Reinstatement
-
72.001 Work areas and safety 2 Property damage made good <br>
-
72.002 Poles 2 Ground reinstatement completed around poles <br>
-
72.003 Buried Service Lead 2 Reinstatement/ backfill satisfactory around Buried Service Lead <br>
-
72.006 H&S 1 Concrete surround flush with footpath or surrounding ground, no trip hazard <br>
-
72.007 Reinstatement 3 Excess vegetation removed <br>
-
72.011 Cable Haul 2 Reinstatement appropriate around cable haul <br>
-
72.018 Reinstatement 2 Ground reinstatement completed <br>
-
72.019 Reinstatement 6471 2 Backfill compacted every 150mm <br>
-
72.020 Reinstatement 6471 3 Surplus soil removed <br>
-
72.021 Reinstatement 6471 2 Reseal completed - Footway / vehicle resurfaced <br>
-
72.022 Reinstatement 6471 2 Grass reinstated and replanted <br>
-
72.023 Manholes 2 Ground reinstatement completed around manholes <br>
-
72.024 SSA 2 Ground reinstatement completed - SSA <br>
73.000 Site tidy
-
73.001 Poles 2 Site tidy, no task waste - poles <br>
-
73.002 Cabinet Internal 2 Site tidy, no task waste - Cabinet internal <br>
-
73.003 Aerial Terminal 2 Site tidy, no task waste - Aerial Terminal <br>
-
73.004 Pillar Terminal 2 Site tidy, no task waste - Pillar Terminal <br>
-
73.005 BDD Terminal 2 Site tidy, no task waste - BDD Terminal <br>
-
73.006 PDS Terminal 2 Site tidy, no task waste - PDS Terminal <br>
-
73.007 Aerial Service Lead 2 Site tidy, no task waste - Aerial Service Lead <br>
-
73.008 Buried Service Lead 2 Site tidy, no task waste - Buried Service Lead <br>
-
73.009 ETP 2 Site tidy, no task waste - ETP <br>
-
73.019 Cable & Duct Lay 2 Site tidy, no task waste - Cable & Duct Lay <br>
-
73.020 Manholes 2 Site tidy, no task waste - Manholes <br>
-
73.021 SSA 2 Site tidy, no task waste - SSA <br>
-
73.024 Site tidy 2 Site tidy, no task waste - general