Information
-
Audit Title
-
Document No.
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Customer Service Area
-
Viscore/ Job Number
-
Responsible Manager
-
Auditee
-
Company
Service Order
-
3.006 Records updated or confirmed correct
-
3.007 WMS Trouble Ticket receipted by service company and clearly defines the problem
-
3.008 WMS Trouble Ticket event log clearly describes action taken to fix fault
4 Codes
-
4.004 Correct Statement of Work codes used
5 Fault
-
5.001 NTS test result (Good Line)
-
5.002 Records - Customer information & cable pairs correct, changes updated
-
5.004 OUT Fault Ticket text field completed - first name, surname initial, fault cause, fault resolution, location of repair incl. street no., name of end customer if contacted. If applicable: reason for uneconomic repair, billing information S&S doc no., PDR no., NFF NVF no.
-
5.005 First Time Fix principles applied. Fault repaired but there was another service affecting issue that could have been fixed and wasnt.
-
5.009 Escalation procedure followed (Defect Referral)
7 Exchange Equipment
-
7.001 Equipment positioned & installed correctly, ventilation unimpeded
-
7.002 Equipment anchored / mounted compliant with seismic needs
-
7.003 Equip secure; Fastenings, Isolation, Earthing, Masking, Covers
-
7.004 Equipment & racks labelled correctly. Node name visible. TLRD system name visible.
-
7.005 Static straps fitted where required
-
7.006 Alarms connected & tested. Commissioning info confirmed
-
7.007 DF components secure, labelled, jumper management correct
-
7.008 Conduits and pipework adequately routed & anchored
-
7.009 Cable tray earthing & isolation correct
-
7.01 Cable type & size and labelled OK. Installation neat and tidy
-
7.011 Cable and jumper terminations tidy & to required standard
-
7.012 UTP cables are supported and routed securely
-
7.013 Structured Cabling supported and routed securely, not tight bends, Velcro ties used
-
7.014 Circuit breakers / fuses correct type & size & labelled
-
7.015 Equipment area tidy, task waste removed
-
7.016 Air conditioning functioning and temperature OK
-
7.017 Trunking manages fibre cords within maximum capacity limits; drop off position OK, flexitube anchored at equip, fibre slack managed.
-
7.018 Fire & Smoke stopping around wall cable access holes
-
7.019 Replacement equipment correct
-
7.02 Replacement equipment programmed correctly
-
7.021 Faulty equipment sent for repair
8 UCLL CoLocation
-
8.001 Customer owned copper / fibre cables labelled every metre with owner name
-
8.002 Fibre cable tails coiled on top of Customer footprint or feed direct into footprint (no excess)
-
8.003 Trunking manages fibre cords within maximum capacity limits; drop off position OK, flexitube anchored at equip
-
8.004 Customer equipment secured compliant to seismic standards
-
8.005 MDF cabling installation & testing confirmed
-
8.006 50 Volt End Of Row feeds clearly labelled for each Customer
-
8.007 Customer equipment earthed (6mm cable green sheath) connected to Telecom earth bar
-
8.008 NetMAP, Floor and Rack Layout & Record Systems represent Customer information correctly
-
8.009 Previous QA and/or Build activity completed, no outstanding actions
9 MDF (7535, NDF-100A, NDF-100B, ND0066)
-
9.001 MDF Block secure (installation, earthing)
-
9.002 MDF Block Labelling correct (Cable Number, Pair range)
-
9.003 MDF Area cable entry duct sealed
-
9.004 VESDA in working condition
-
9.005 Jumper routing via frame guides
-
9.006 Jumper type correct (OR/WH) with required (175mm - 225mm) slack left
-
9.007 IDC jumper terminations correct (full insertion to IDC, excess trimmed)
-
9.008 Solder jumper terminations correct (wire strip & wrap, no excess solder)
-
9.009 Old jumpers removed
-
9.01 Lightning protection (where fitted) earth to common earth
-
9.011 Cable pair records updated
-
9.012 Sign off codes correct (specify here)
-
9.013 Site tidy, rubbish bins, jumpers, floor
10 Pride & Logs
-
10.003 Equipment Room Log completed in exchange
-
10.004 Cabinet Log completed
11 OFDF & Exchange Fibre
-
11.001 All optical cables 100% support on horizontal & managed on vertical
-
11.002 OFDF hardware secure: OFDF Drawer-Cable Trough-Guides-Rack
-
11.003 Network labelling correct at OFDF (OFDF Designation, Jumper to/from label)
-
11.004 Optical cables & cords adequately managed within racks and shelves
-
11.005 OFDF Single Fibre Organiser not overfilled (<1.5mtr tails)
-
11.006 Fibre splicing within design tolerance
-
11.007 30mm bending radius unconditionally observed at all locations
-
11.008 Fibre pigtail label records 'from' OFDF ID and SFO number
-
11.009 Trunking manages fibre cords within maximum capacity limits; drop off position OK, flexitube anchored at equip
-
11.01 Protective caps on all unterminated connectors
-
11.012 Laser Safety labels (1M Safety) at OFDF (inside and front panel)
-
11.013 No fibre task waste on site, all optical (glass) ends safely contained (H&S)
29 Active Cabinet Internal LHS
-
29.001 Outer Door lock works smoothly and door closes without jamming
-
29.002 Door stays are in place and all work well
30 Active Cabinet Equipment
-
30.005 Earth and wrist strap installed
-
30.007 Fibre cable entry to Cabinet secured with cable gland, managed to OFDF OK
-
30.008 OFDF in a CNSP approved enclosure, netmap label on OFDF lid
-
30.009 Laser Safety labels (1M Safety) at OFDF (inside and front panel)
-
30.01 Cable entry to OFDF secured with cable gland
-
30.011 Fibre managed within OFDF OK
-
30.012 Protective caps on all unterminated connectors
-
30.014 30mm bending radius unconditionally observed at all locations
-
30.015 Fibre pigtail labels fitted with OFDF number and position designation
-
30.016 Site tidy, no fibre or task waste, all optical (glass) ends safely contained (H&S)
55 Network Records
-
55.085 FRE generated to capture faults (where appropriate)