Title Page
-
Audit Title
-
Conducted on
-
Prepared by
Peer Superintendent and Project Manager
-
undefined
CCC Punch list created Date (should be generated and distributed at 3 weeks prior is Substantial Completion)
-
Select date
Project Dates
-
Early Fixture Set Date
-
Contract Completion
-
Refrigeration Soft Start Date
-
Refrigeration Actual Start Date
1. Cleanliness
-
Overall Site (material organized, connex's removed, job trailer removed)
-
Overall Building (material organized - Final clean scheduled)
1. Fuel Station
-
Over All Slab Condition (cleanliness)
-
Exterior Slabs
-
Tank pad
-
Glass/Glazing
-
Sales Floor walls
-
Restroom
-
Exterior Block and Paint
-
Exterior Joint Sealants
-
Canopy erected
-
Dispensers Set
-
Permanent Power
-
30 day Pre-Turnover Inspection Scheduled
-
Programming and Calibration Date Set
-
Fuel Drop Date Set
2. Owner Provided Items Missing
-
Steel/HVAC/Lighting/Vendor issues
3. Utilities
-
Permanent Power
-
Gas
-
Water
-
Sewer
4. Onsite/Offsite
-
Offsite signal/roadwork
-
Landscaping/Irrigation
-
Easements Outstanding
5. Exterior of Building
-
Truck Turn around and Truck Well access
-
Parking Lot
-
Striping
-
Site Lighting
-
Exterior Signage
-
Roof Clean & Finished/Skylights/Smoke Vents
-
Exterior Joint Sealants
-
Exterior Block Work and Paint
-
Exterior concrete (i.e. sidewalks, ADA ramps)
6. Interior of Building
-
Restrooms
-
Millwork
-
Fire Protection
-
Refrigeration Start-Up/NOVAR
-
Electrical
-
HVAC
-
Plumbing
-
Pharmacy/Pharmacy Drive Thru
-
Vision Center
-
Tenant Spaces
-
Offices
-
Breakroom
-
Deli/Bakery
-
Sales Floor Walls
-
Floors: Joint Sealants, Polish
-
Glass/Glazing
-
Auto Entrances
-
Receiving Area
-
TLE/TMA
6. Support Team
-
Alarm
-
Cabling
-
Telecom
-
Cameras
-
SUP Tenant Issues
7. Occupancy/Licensing
-
TCO or C of O status
-
Stocking Permit