Title Page
-
Project
-
Water authority Auditor
-
Water Authority
-
Dual Water or Drinking Water Only
-
Conducted on
-
Prepared by
-
Document No.
-
Contractor
-
Where up to
-
Representative on site
-
O, H & S compliance – JSA active, Toolbox sessions recorded
-
Barricades, sign – protection of public
-
Plant operator licensed
-
Copies of relevant specifications and drawings kept on site
-
Minimum amount of excavation left open
-
Delivery dockets are available
-
No undermining of trees or structures
-
No conflict with other services
-
Surface restoration
-
Asset recording
-
Watermain offsets check, pegs installed
-
Fitting locations, as per plans
-
Cover to main and fittings, check against Pegs
-
Clearance to other services (gas etc)
-
Connection to live Asset Form Completed and forwarded to relevant Authority and Calibre Consulting.
-
HOLD POINT – connection to live asset witnessed by Calibre Consulting and recorded.
-
Form for Testing completed and forwarded to relevant Authority. At testing – visual inspection of all property connections. Release test for each tapping
-
Pipe bedding and backfill sources identified and quality testing of bedding & backfill sources obtained
-
Pipe bedding placed and compacted as per specification, pipes placed and jointed in accordance with requirements
-
Pipes inspected and tested by appropriate authority (eg pressure test)
-
Pipe backfill placed and compacted as per specification
-