Waterproofing ITP Pacific Stone Pty Ltd

  • Site conducted

  • Conducted on

  • Prepared by

  • Location: Internal wet areas, Balcony or precast?

  • Do the products being used vary from those specified in the project contract supplied to PC?

Inspection Questions

  • Site Specific Location: Eg unit number and floor

  • Are the falls correct for the substrate?

  • Is the substrate suitable for waterproofing to commence?

  • Are there any actions required by other trades prior to commencing?

  • Has the Principal Contractor been notified of any defects or concerns?

  • Has the manufacturers SDS been reviewed prior to installation of products?

  • Has the primer and bond breaker been applied correctly in accordance with manufacturers specification?

  • Has the membrane cured to move onto the next step of the checklist?

  • Was the flood test carried out?

  • If the flood test was carried out, what was the result?

  • Date of epoxy primer?

  • Date of 1st coat under (under screed)?

  • Date of 2nd coat (above screed)?

Pacific Stone Representative sign off

  • Do you deem the above information to be true and accurate?

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.