Information
-
Audit Title
-
Document No.
-
Wates / Hoxton Press
-
Conducted on
-
Prepared by
-
Penn Street, Hoxton, London
-
All Site Team
-
Raised by
- Darren Madigan
- gabreil Tatar
- Simon Thayer
- Emil
-
Tower
- Tower 1
- Tower 2
-
Level
- level 1
- level 2
- level 3
- level 4
- level 5
- level 6
- level 7
- level 8
- level 9
- level 10
- level 11
- roof
-
Description of Inspection
-
Items Included in this Inspection
- 1st fix frame and board
- fire tape
- electrical back box & straps
- noggings
- insulation
- head track & fire seal
- fire batt to all voids & holes
- 2nd fix board
- pod head infill
- window jambs
- window cill
- 1st tape & Joint
- vapour barrier
- m&E cupboard wings & noggings
- apartment remaining walls
- pocket door inset
-
Photos
-
Once completed signed by the sub contracting manager
-
Confirmed by a Wates manager