Title Page

  • Document No.

  • Audit Title

  • Client / Site

  • Conducted on

  • Prepared by

  • Location
  • Personnel

Wet Season Readiness (WSR) Plan Development

  • Has the Strategic Operational Water Plan (SOWP) been reviewed and updated?<br>Including updates from:<br>- Site Water Balance<br>- Water reticulation and storage plan<br>- Flood modeling<br>- Clean/Dirty water separation<br>- TARPs

  • Select your level of control with the requirement.

  • Attach links for Relevant Documents

  • When was the last update to the SOWP?

  • Comments/Actions

  • Comments/Actions

  • Responsible Person

  • Has the Pit Protection Plan been established, reviewed and updated?<br> - Is your flood modeling current and includes any dump and pit progressions?<br> - Has your clean/dirty water diversion system been maximised?

  • Select your level of control with the requirement.

  • When was the last update to the PPP?

  • Attach links for Relevant Documents

  • Comments/Actions

  • Comments/Actions

  • Responsible Person

  • Has the Equipment and Facility Protection Plan been established, reviewed and updated? (MIA/CHPP/mobile buildings etc.)<br>Facility Protection - Is any fixed infrastructure affected by flooding? - Ref Flood model.

  • Select your level of control with the requirement.

  • When was the last update Equipment and Facility Protection Plan?

  • When was the last update to the Flood Model?

  • Attach links for Relevant Documents

  • Comments/Actions

  • Comments/Actions

  • Responsible Person

  • Has the Rainy Day Plan and TARPs been established, reviewed and updated?<br>- Consider the outcomes of the water balance and any flood modelling<br>- What are the plans to maintain production in the plant during rain events?

  • Select your level of control with the requirement.

  • Attach links for Relevant Documents

  • When was the last update to the TARP?

  • Comments/Actions

  • Comments/Actions

  • Responsible Person

  • Has the Environmental Authority - Water Management Plan and referenced procedures been reviewed and updated?<br>Does this align with the SOWP and Water Balance?

  • Select your level of control with the requirement.

  • Attach links for Relevant Documents

  • When was the last update to the WMP?

  • Comments/Actions

  • Comments/Actions

  • Responsible Person

  • Have emergency management protocols, including site evacuation and access, related to wet weather events been reviewed, updated, documented and communicated?<br>- What early warning triggers do you have to advise on cut access?

  • Select your level of control with the requirement.

  • Attach links for Relevant Documents

  • Comments/Actions

  • Comments/Actions

  • Responsible Person

WSR Plan Implemented – Communication

  • Are water management team meetings including all key stakeholders (Mine Planning, Environmental, Engineering and appropriate operations representatives) being conducted on a regular basis? <br>- What frequency?

  • Select your level of control with the requirement.

  • Attach links for Relevant Documents

  • Comments/Actions

  • Comments/Actions

  • Responsible Person

  • Are water release (or water retention) procedures communicated and understood especially by Management, Superintendents and Principals?<br>- How is this communicated?<br>- Who owns the water strategy and the communication of it?

  • Select your level of control with the requirement.

  • Attach links for Relevant Documents

  • Comments/Actions

  • Comments/Actions

  • Responsible Person

  • Are training packages prepared and available for supervisors to deliver on wet days? <br>- Environmental training, SOPs, Risk assessments etc.

  • Responsible Person

  • Attach links for Relevant Documents

  • Comments/Actions

  • Has the wet season rainfall outlook been communicated across site?

  • Responsible Person

  • Attach links for Relevant Documents

  • Comments/Actions

  • Has a system been established to monitor weather forecast for site and communicate potential for Significant Rain Events?<br>- WeatherZone, Elders etc

  • Responsible Person

  • Attach links for Relevant Documents

  • Comments/Actions

  • Is Water Management included in Visual Management Boards to communicate Rainfall, Discharge Volume vs. Capability, Storage volumes, operating levels for wet season?

  • Responsible Person

  • Attach links for Relevant Documents

  • Comments/Actions

WSR Plan Implementation – Infrastructure

Dams/Levees

  • Are Pit Protection and Water Diversion Levees secure and adequate?<br>- Are they designed from Flood modeling data?

  • Select your level of control with the requirement.

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Comments/Actions

  • Photos

  • Responsible Person

  • Are operations plans for Regulated Dams reviewed and updated.

  • Responsible Person

  • Attach links for Relevant Documents

  • When was the last update?

  • Comments/Actions

  • Photos

  • Are dams at minimum (or maximum, as required) operating levels?<br>- Is the wet season operating level known and communicated?<br>- Noting the release or retention requirements of the business.

  • Select your level of control with the requirement.

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Comments/Actions

  • Photos

  • Responsible Person

  • Are dams including sediment dams de-silted where required?<br>In your response note the following:<br>- Last bathymetric survey date<br>- Does a PM02 exist<br>- What is the current PM02 clean out frequency?

  • Select your level of control with the requirement.

  • Attach links for Relevant Documents

  • When was the last update?

  • Comments/Actions

  • Photos

  • Location?
  • Comments/Actions

  • Photos

  • Responsible Person

  • Have integrity inspections been conducted on all water storage's?

  • Responsible Person

  • Attach links for Relevant Documents

  • When was the last update?

  • Comments/Actions

  • Photos

  • Are all actions from the regulated and non-regulated structures audits been assigned in SAP?

  • Responsible Person

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Have certified Erosion and Sedimentation Management plans been developed, installed and maintained?<br>This is not the EA referenced ESP.

  • Select your level of control with the requirement.

  • Attach links for Relevant Documents

  • When was the last update?

  • Comments/Actions

  • Photos

  • Location?
  • Comments/Actions

  • Photos

  • Location?
  • Responsible Person

Release Infrastructure

  • Are off-stream water release storages full and ready for release?<br>- How are you monitoring this?<br>- Do you know the required levels to work towards?

  • Select your level of control with the requirement.

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location
  • Comments/Actions

  • Photos

  • Location
  • Responsible Person

  • Is water release infrastructure tested and operational, along with associated water monitoring equipment to maximise release opportunities?<br>- Provide evidence

  • Select your level of control with the requirement.

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Comments/Actions

  • Photos

  • Location?
  • Responsible Person

  • Have all pumps, valves and release points been positively tested to confirm operability?<br>- Provide evidence

  • Select your level of control with the requirement.

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Comments/Actions

  • Photos

  • Location?
  • Responsible Person

  • Are key access tracks to all sampling sites and key water infrastructure in good condition?

  • Responsible Person

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?

Pipes and Pumps

  • Is piping infrastructure in good condition and positioned in place?<br>- Does the infrastructure align with the SOWP and Site Water Balance? <br>- Do you have drawings, terraexplorer or mine2map overlays of the piping systems to confirm adequate positioning?

  • Select your level of control with the requirement.

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Comments/Actions

  • Photos

  • Location?
  • Responsible Person

  • Is adequate pumping capacity available and positioned in place?<br>- Capacities, as per the SOWP?<br>- Updated to match current mine plans? <br>- Are the locations shown on a dynamic plan? Terraexplorer, mine2map etc

  • Select your level of control with the requirement.

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Comments/Actions

  • Photos

  • Location?
  • Responsible Person

  • Are pumps maintained, serviced, tested and in good condition?<br> - Do you have adequate PM02's in place?<br>- Provide evidence

  • Responsible Person

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Is there adequate fuel storage at critical pumping locations?<br> - Can the pumps run for at least 4 days, if required?<br>- If not, how long can they run? And does this allow for adequate time to get the pumps refuelled?

  • Responsible Person

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?

Drains and Culverts

  • Have all key culverts/drains been identified and inspected? <br>(As a minimum all culverts/drains on category 1 Haul roads must be considered)<br>- All sites should have a culvert and drains drawing/s, highlighting the critical culverts and drains. Preferrably in a readily accessible location i.e a layer in TerraExplorere or Mine2Map

  • Select your level of control with the requirement.

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Comments/Actions

  • Photos

  • Location?
  • Responsible Person

  • Are all key culverts in good condition and cleaned? <br>- Critical Culverts should have functional locations and PM02's for WSR

  • Select your level of control with the requirement.

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Comments/Actions

  • Photos

  • Location?
  • Responsible Person

  • Are all key drains in good condition and cleaned?<br>- Critical Drains should have functional locations and PM02's for WSR

  • Select your level of control with the requirement.

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Comments/Actions

  • Photos

  • Location?
  • Responsible Person

Roads

  • Have roads that can be utilised during or after rain events been identified and maintained for quick recovery?<br>- Mine2Map, TerraExplorer overlay?<br>- PM02 for WSR?

  • Select your level of control with the requirement.

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Comments/Actions

  • Photos

  • Location?
  • Responsible Person

  • Are bunds secure and adequate?<br>If requried, do bunds allow for adequate water flow?

  • Responsible Person

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Does the cross fall/ berm slots/culverts and drains for roads allow for efficient drainage of the road?

  • Responsible Person

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Is there easy access to gravel stocks to repair roads after rain events?

  • Responsible Person

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Are there sufficient ancillary resources available to allow for efficient recovery of key roads after a significant rainfall event?

  • Responsible Person

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?

WSR Plan Implementation – Resourcing

  • Are all Staff Rosters updated and communicated to all relevant staff? Including telemetry monitoring, pump crew and sampling rosters.

  • Responsible Person

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Are backup resources identified and available in the event of illness?

  • Responsible Person

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Do all relevant personnel have appropriate PPE for wet weather?

  • Responsible Person

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Is there sufficient safety and emergency equipment available (e.g., Hand-held radios, GPS, life vests, restraints, vehicle recovery equipment)?

  • Responsible Person

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Has all required training for environmental staff for wet season been identified?

  • Responsible Person

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Has all required training been completed, and are all Training and Competency Registers updated?

  • Responsible Person

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?

WSR Plan Implementation – Monitoring

  • Has the Envirosys database been checked to ensure operations and web-based access and procedures communicated to site?

  • Select your level of control with the requirement.

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Comments/Actions

  • Photos

  • Location?
  • Responsible Person

  • Are gauging station surveys completed and rating curve calibration completed?

  • Select your level of control with the requirement.

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Comments/Actions

  • Photos

  • Location?
  • Responsible Person

  • Are gauging station surveys completed and rating curve calibration completed?

  • Select your level of control with the requirement.

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Comments/Actions

  • Photos

  • Location?
  • Responsible Person

  • Has all telemetry and sampling equipment been calibrated?

  • Select your level of control with the requirement.

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos?

  • Location?
  • Comments/Actions

  • Photos?

  • Location?
  • Responsible Person

  • Are there enough sampling supplies for minimum 2 weeks sampling?

  • Responsible Person

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos?

  • Are the processes in place to order emergency supplies quickly?

  • Responsible Person

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Are all sampling staff/contractors familiar with sampling locations and procedures?

  • Responsible Person

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Are all sampling staff/contractors familiar with release criteria (as per Environmental Authority)?

  • Responsible Person

  • Attach links for Relevant Documents

  • Comments/Actions

  • Photos

  • Location?
  • Name and signature of inspector

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.