Title Page
-
Site conducted
-
Document No.
-
Conducted on
Permit Questions
-
WORKING AT HEIGHT PERMIT
SAFE HOME EVERY DAY -
Name
- Justin Wood
- Dean Aitken
- Adrian Kiwara
- Glen Simpson
- Simon Jowett
- Ben Earnshaw
- Other - please list below
- Rob Brady
- Leo Singh
-
Name
-
Select date
-
Job Details
-
Location
- A Block
- B Block
- Winding
- Twisting
- Blending
- Dyehouse
- Confin
- Despatch
- Services
- External
- Upstairs
-
Photo of job location
-
The following equipment will be used during the works and is in good working order and fit for purpose
- Step ladder
- Extension ladder
- Edge protection
- Mobile scaffold
- Elevated work platform
- Safety net
- Stationary scaffold
-
The following services have been isolated for the duration of the works
- Fire Protection
- Gas
- Electricity
- Compressed air
- Steam
- Hot or cold water
- N/A
-
The following control measures have been implemented for the duration of the works
- Barricades
- Signage
- Spotter
- N/A
-
The following environmental factors have been assessed and are suitable for the works
-
Other environmental factors
Risk Assessment - Risk assessment has been carried out and the following hazards identified
Access/Egress
-
Safe access for all employees in place
-
Firm level ground for scaffold/mobile access, ladder etc
-
Overhead services/obstructions have been identified
-
Ladders, roof and other meas of access in good condition
-
Systems for the safe removal of waste materials are in place
Fall Protection
-
Where appropriate, adequate guard rails are in place
-
An appropriate fall restraint system is in place
-
An appropriate anchor point has been selected
-
Safety net has been installed by a qualified person
-
Permit Approval
-
Select date
-
Add signature
Permit Sign Off
-
Permit Sign Off
-
Select date
-
Add signature