Information
-
AREA Task Conducted -
-
WestConnex M4E - Parramatta Rd Civil
-
WORKPLACE INSPECTION NO 6: TRENCHING AND EXCAVATION
-
Conducted on
-
Parramatta Road - Area - Activity - Task
Area Supervisor:-
-
- Daniel Taylor
- Simon Baldwin
- MIchael Paton
- Ben Ashcroft
- David Wilson
- Brandon Leong
- Dave King
- Peter Masiororski
- Ben Forbes
- Vaughan Kimmins
- Mitch Stevens
- Bob Isaac
- John Kim
- Joe Vu
- Danielia Cullura
Lead Inspector:-
-
- Daniel Taylor
- Simon Baldwin
- MIchael Paton
- Ben Ashcroft
- David Wilson
- Brandon Leong
- Dave King
- Peter Masiororski
- Ben Forbes
- Vaughan Kimmins
- Mitch Stevens
- Bob Isaac
- John Kim
- Joe Vu
- Danielia Cullura
Other members of the inspection team?
-
- Daniel Taylor
- Simon Baldwin
- MIchael Paton
- Ben Ashcroft
- David Wilson
- Brandon Leong
- Dave King
- Peter Masiororski
- Ben Forbes
- Vaughan Kimmins
- Mitch Stevens
- Bob Isaac
- John Kim
- Joe Vu
- Danielia Cullura
-
Another auditor
-
Is there a valid Work Permit and approved SWMS in place for the work being performed?
-
What Services are have been identified?
- Electrical Cables (11kV or Higher)
- Communications / Fibre Optic / Telephone
- Gas Pipes
- Electrical Cables (less than 11kV)
- Air / Water Pipes
- Fuel / Oil
- Sewer / Drains
-
Have the services locations and their depth or height (as applicable) also been identified on plans and drawings ?
-
Types of Assets and Limits of Underground Approach
-
Table of Safe Approach distances
-
Take a photo of the service locations marked on the ground.
-
Are we maintaining the required approach distance to the services
-
Have all redundant Services been marked?
-
Have all associated nearby pits been opened, and checked to identify services?
-
Has an emergency evacuation/rescue plan been developed and in place if the trench is deeper than 1.5m?
-
If the trench is deeper than 1.5 m deep is it battered, benched or shored or inspected by a geotechnical engineer?
-
Has suitable barricading been identified in the SWMS? Is it erected in accordance with SWMS?
-
What type of barricading has been erected?
- Water filled Jersey
- Concrete
- Windrow
- Steel Permitier fencs
- Crowd Control
- Flagging
- Other
-
Are there vehicles operating in the area?
-
Have barriers been established to prevent vehicles form entering the zone of influence?
-
Are there controls measures in place to prevent vehicle fumes from entering the trench?
-
Is warning signage displayed in prominent locations?
-
Is the barricading and signage in good condition?
-
Take a photo
-
For trenches deeper than 1.5 meters, is there a means of access/egress every 9 meters?
-
Is the trench spoil located as per the SWMS? (at least equal to depth)
-
Is there materials located within the 'zone of influence'?
-
Are workers required to cross the trench/es?
-
Are properly designed walkways or bridges with guard rails and kickboards provided? Are the trench/es near roadways or paths? Are they open at night? Are there flashing lights / reflective tape to mark the trench/es?
-
If spotters are used for adjacent to services are they positioned in safe location
-
Is the trench/es inspected by a competent person prior to commencing work or after an adverse weather event?
Action required?
-
Action
-
Allocated to
-
Action due
-
Lead Inspector to sign
-
Other members of the inspection team to sign:
-