  • This checklist should be completed every shift. Aim to complete by 4am/pm. Please add comments and assign actions where you respond "No". Each crew should agree to have one Pit Patroller complete the checklist with support from the other Pit Patrollers. The checklist should be completed in the field over the shift. The completed checklist can be used at the shift handover.

  • Conducted on

  • Prepared by

  • Shift

Untitled Page

A - All Load Locations

  • Are Load locations constructed to the standard - check 1.8m windrow heights and appropriately sized, ideally a min of 90m x 70m max of 120m x 100m if achievable.

  • Are location refines inside physical boundaries - check for dig faces, batter trims, paddock dumps, windrows etc

  • Are all physical hazards in the location protected clearly by obstacles ie Lighting plants

  • Are all grader windrows and delineation in place for static roads running into and out of locations

B - All Dump Locations

  • Are Dump locations constructed to the standard - check 1.8m windrow heights, and appropriately sized ideally a min 90m x 70m, Max 120m x 100m if achievable.

  • Are Dump location refines within the physical boundary and dump refined smooth

  • Are all physical hazards in the dump location protected clearly by obstacles ie lighting plants

  • Are all Grader windrows and delineation in place for static roads running into and out of dumps.

  • Please note any Dumps that have excessive tray up times more than 10 sec

C - Static Courses and Intersections

  • Have you checked that there no one way roads within static courses and intersections

  • Are Static courses / intersections correctly demarcated

  • Are toe and crest markers in the correct location on ramps

  • Are Static courses and Intersections surveyed within physical boundaries

D - ROM and Crusher

  • Are the Taught courses at the crusher graded and free of ruts

  • Have you looked at the PLOD to see loading movements / material changes for the shift

  • Are the ROM / Finger paddock dumps tipped out to provide a safety buffer - no less than 3 rows at the bottom

  • Is there enough room at the bottom of the Rom's to reclaim material

  • Please note if the Tray up time at the Crusher is more than 10 sec

E - General Pit Areas

  • Is the MWSL appropriate for ground conditions

  • Have you looked at the PLOD for load and dump options for the shift

  • Have you checked for any underlining roads or locations that are no longer required

  • Have you checked after blasting or pit maintainence that material has not been pushed into the AT

  • Are AT access gates working correctly and have signage in place to restrict access

  • Are LASL appropriately speed limited and sized for conditions

  • Have you cleaned the cab and checked it has enough fuel for the next shift

  • Please list any major changes during the shift

COMMENTS

  • Please add any general comments that have not been covered above

DEVELOPMENT IMPROVEMENTS AND IDEAS

  • Have you identified a possible Major development improvement/suggestion that can be made

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.