Information

  • Document No.

  • Audit Title: Apartment Inspection

  • Plot

  • Block

  • Level

  • Flat Ref

  • Flat Type

  • Kitchen Type

  • Wates / Greenwich Peninsula

  • Conducted on

  • Prepared by

STAGE ONE ( 1st fix )

ALL ROOMS

  • Sole plates to all internal partitions.

  • 3 walls to manifold and HIU.

  • Head track to all internal walls.

  • Flat extract duct and lagging.

  • Insulate, underfloor heating / pressure test.

  • Insulation and sand/cement screed.

  • Cure Screed.

STAGE ONE WCL HOLD POINT: Managers to Sign.

  • Plot Manager:

  • Senior Manager:

STAGE TWO ( 1st fix )

  • LTHW pipework to radiators.

  • Metal stud and board both sides ( inc hockey sticks and ply support )

  • 1st fix DHCWS high level from valves in corridor.

  • 1st fix sprinkler.

  • Install consumer unit.

  • Cable I.T. Power, Data, AV, Access and fire alarms.

  • Pressure test pipework domestics and heating INS.

  • Fire stopping.

STAGE TWO WCL HOLD POINT: Managers to Sign.

  • Plot Manager:

  • Senior Manager:

STAGE THREE ( 1st fix )

  • Complete boards to ceilings.

  • Dead test.

  • Tape and joint walls and ceilings.

BATHROOM

  • Pipe run outs.

  • Stud frame shower / vanity.

  • Fit bath.

  • Toilet, cistern and shower mixer.

  • Walk in wardrobes, shelving and hanger rail.

KITCHEN

  • Plumber 1st fix.

ALL ROOMS

  • Mist coat.

STAGE THREE WCL HOLD POINT: Managers to Sign.

  • Plot Manager:

  • Senior Manager:

STAGE FOUR ( 2nd fix )

BATHROOMS

  • Fittings to complete bath.

  • 2nd fix board, ducts and bath panel with framework.

  • Timber panelling.

  • Tile to bathrooms.

  • Cupboards and shelving.

  • Fix vanity top.

  • Shaving point and LED lights.

  • Floor tiles.

  • Sanitary ware.

  • Complete pipework from isolation valve to appliance.

  • Electrical 2nd fix.

  • Towel rails.

  • Testing.

  • Mastic.

  • Mirrored cabinet doors.

KITCHEN

  • Install kitchen.

  • Site template for work tops.

  • Carpentry 2nd fix including kitchen fittings.

  • Vinyl flooring.

  • Cut in plinths.

  • Fit work tops.

  • Tile kitchen.

  • Electrics 2nd fix.

  • Mastic.

  • Final connections.

  • Test.

  • White goods.

ALL ROOMS

  • Engineered timber flooring and protection.

  • Fix frames and hang doors then remove doors.

  • Skirting sand architraves.

  • Pre decorate inspection.

  • Decorate through except top coat.

  • Fix all face plates and sockets / light switches / luminaries.

  • Smoke heads and heat detectors and grills.

  • Live test.

  • Lighting on.

  • Decorating top coat.

  • Mech finals.

  • Carpentry finals and hang doors.

  • Carpet and underlay to bedrooms.

  • Walkin wardrobes and sliding doors.

  • Commissioning.

  • Builders clean.

  • Sub contractor inspection.

  • Sparkle clean.

This inspection sheet confirms that the item or area detailed above is 100% completed in line with the current specification, drawings and pre agreed sample panels although still remaining Sub Contractors responsibility until practical completion has been achieved.

  • Final Inspected by:

  • Approved by:

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.