Title Page

  • Store No.

  • Client - TESCO STORES LIMITED

  • Site / Store Name

  • Conducted on

  • Conducted by

  • Location
  • ATL Lead Installer - Name

  • All Other ATL Installers on Site - Names

Pre Start Compliance

  • Have ALL ATL Installers Signed in, Shown CSCS Cards and been site inducted.

  • Do ALL ATL installers have in date Tesco Academy training

  • Do the Installation team know what to do in the event if a fire & evacuation procedure

  • Is the Installation team aware of first aid and use of welfare facilities.<br>

  • Does each Installer know how to report an accident and who to inform.

  • Is there any requirement to change Safe System of Work from the Risk Assessment and Method Statement.

  • RAMS Installation Declaration been signed by Team Leader, Each Team Member and Site Manager - Provide Photo of Sheet

Site Compliance

  • Does each Installer have and a hard hat.<br>

  • Does the Installer have a Tesco / ATL branded hi-viz vest.

  • Is the correct safety footwear being worn by all Installers

  • Does each the Installer have the relevant eye/ear protection and safety gloves as outlined in the Risk Assessment

  • Is all PPE in good condition.

  • Is there a first aid box present on van and fully stocked.

Equipment & Safety

  • Are Barriers in Place and of the Correct Type i.e. ( Chapter 8 Clearpath) - Please provide Photo<br>

  • Has Disc cutter been inspected and associated tooling been inspected and free of faults / damage with correct guards in place

  • Is the disc cutter water reservoir filled and working correctly for dust suppression

  • Is there clear access and egress to and from the work area.

  • Have measures been taken to reduce trip hazards.

  • Is the general public adequately protect from works i.e. (is clear area from cutting)

IOW Instruction of Work

  • Has the GATEKEEPER IOW been provided and understood

  • Has the GATEKEEPER Cart Control Layout Plan Been Provided

  • Are there any Issues with the Route Highlighted (Blue) for the Signal Cable - NOTE: If Yes Highlight on Plan the Change of Route

  • Are there any Issues with Completing the Lock (Red) & Unlock (Green) Loop shown on the layout plan - NOTE: If Yes Highlight on Plan the Change of Route

QC Record of Works

  • Provide Photos of All Cables entering Buildings Internal & External

  • Provide Photos of All Signal Cable Routed Internally

  • Provide Photos of All Signal Cables Cuts Routed Externally

  • Provide Photos of All Lock & Unlock Loop Cuts

  • Provide Photos of All Signal Cable Routes with Completed Sealant Finish

  • Provide Photos of All Lock & Unlock Loops with Completed Sealant Finish

  • Have all works been completed to Agreed Standards

Completion Of Works

  • Provide Photo of Completed GATEKEEPER IOW

  • Provide Confirmation & Photo of System Operational 'Live Mode'

Any other comments or info

  • Provide any other Details as Required

Audit Sign Off

  • ATL Team Leader

  • Store / Site Duty Manger

undefined

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.