Title Page
-
Client / Site:
-
Document No.
-
Plot:
-
Core:
-
Level:
- Ground
- Level 1
- Level 2
- Level 3
- Level 4
- Level 5
- Level 6
- Level 7
- Level 8
- Level 9
- Level 10
-
Apartment Reference:
-
Conducted on:
-
Prepared by:
General Information
General:
-
Apartment type:
-
Kitchen Type:
Electrical:
-
Electrical Drawing Number:
-
General Information / Comments:
-
Electrical 1st Fix Installation Completed By:
-
Electrical 1st Fix Inspected By:
Plumbing:
-
Mechanical Drawing Number:
-
General Information / Comments:
-
Plumbing 1st Fix Installation Completed By:
-
Plumbing 1st Fix Inspected By:
Ductwork:
-
Co-ordinated Mechanical Drawing Number:
-
Reflected Ceiling Plan Drawing Number:
-
General Information / Comments:
-
Ductwork 1st Fix Installation Completed By:
-
Ductwork 1st Fix Inspected By:
Electrical, Plumbing and Ductwork:
-
Signed Off By Site Manager:
Electrical
1st Fix Electrical Inspection
-
1: Services installed to latest issue electrical drawings?
-
2: Setting out positions for kitchens are to latest kitchen specialist drawings?
-
3: No switchgear within 300mm of a sink or hob / cooker?
-
4: Lighting and detectors set out to the latest architectural Reflected Ceiling Plan`s?
-
5: All TV, shaver and cooker points have 47mm deep back boxes installed?
-
6: All lighting wired in 3 plate?
-
7: ELV and LV run separately and a minimum of 150 mm apart?
-
8: All cables dressed neatly and tied horizontally and vertically at 600 mm minimum?
-
9: Cables cut to the same length in boxes and boxes no longer than 300mm?
-
10: All wiring within wall run is in safe zones?
-
11: No tie wrap is pulled to tight with ends cut off?
-
12: All ceilings drops are taped together and curled up above head height?
-
13: All cable descriptions identified in pen (SL, LOAD, FEED, ect.)?
-
14: Drawings marked up with End of Lines and 3 plate locations?
-
15: Drawings and sheets returned to supervisor?
-
16: All debris removed and placed in skip and all unused materials returned to stores?
Plumbing
1st Fix plumbing Inspection
1st Fix
-
1: Services installed to latest issue mechanical drawings?
-
2: Manifolds in HIU cupboard with 10 mm hep20 run outs have no joints in the ceiling?
-
3: 10 mm hep20 pipes suitably clipped and secure, horizontal every 300mm, vertical 2 No. caddy and talon clips?
-
4: All 10 mm hep20 pipework installed with 22 mm clips?
-
5: All pipework fully insulated?
-
6: All pipework within HIU cupboard is hep20?
-
7: Pipework for radiators come out through radiator noggin at the correct height (300 mm)?
-
8: All pipework penetrations through walls have sleeves made of the same type of material?
-
9: All 10 mm pipework at radiator is marked "Flow" or "Return"?
-
10: All pipework ends are covered?
-
11: All vertical drops within the walls have 3 No. aluminium bands for location purposes, on the outside of insulation?
-
12: Pressure test carried out and witnessed by B&C Manager and Main Contractor named below? Copy of the pressure test certificate on file?
-
Pressure Test Winessed by Main Contractor:
-
13: All debris removed and placed in skip and all unused materials returned to stores?
Soil Vent Pipes
-
1: All pipework fixed neatly and securely to provide correct falls?
-
2: Fire collars / wraps fitted and secure where applicable?
-
3: Pressure test carried out and witnessed by B&C Manager and Main Contractor named below? Copy of the pressure test certificate on file?
-
Pressure Test Winessed by Main Contractor:
-
4: All debris removed and placed in skip and all unused materials returned to stores?
Ductwork
1st Fix Ductwork Inspection
Ductwork Installation for MVHR
-
1: Ductwork set out to latest construction issued drawing?
-
2: Ductwork spigots set out to latest issue Reflected Ceiling Plan?
-
3: Fresh air supply ductwork fully insulated?
-
4: Exhaust air ductwork full insulated?
-
5: Ductwork clipping complies with DW144?
-
6: All fire collars installed on ductwork where it passes through 30 min corridor walls (As shown on fire strategy)?
-
7: Insulated spiral flex fitted to the 4 spigots within the MVHR cupboard with jubilee clips fitted to outer sleeve?
-
8: All flex outlets connected to ductwork with jubilee clips?
-
9: All flex outlets covered and taped tight to ductwork ready for 2nd fix?
-
10: Ductwork connected to fresh air grille / air brick?
-
11: Ductwork connected to exhaust air grill / air brick?
-
12: All debris removed and placed in skip and all unused materials returned to stores?
Ductwork Installation for MEV
-
1: Ductwork set out to latest construction issued drawing?
-
2: Ductwork spigots set out to latest issue Reflected Ceiling Plan?
-
3: Exhaust air ductwork full insulated?
-
4: Ductwork clipping complies with DW144?
-
5: All fire collars installed on ductwork where it passes through 30 min corridor walls (As shown on fire strategy)?
-
6: All flex outlets connected to ductwork with jubilee clips?
-
7: All flex outlets covered and taped tight to ductwork ready for 2nd fix?
-
8: Ductwork connected to exhaust air grill / air brick?
-
9: All debris removed and placed in skip and all unused materials returned to stores?
Installed Ductwork (Kitchen Extract / Cooker Hood Extract)
-
1: Ductwork set out to latest construction issued drawing?
-
2: Ductwork spigots set out to latest issue kitchen plan?
-
3: Ductwork clipping complies with DW144?
-
4: Flex outlet for cooker hood connected to ductwork spigot with jubilee clip?
-
5: Flex outlet for cooker hood covered and taped tight to ductwork ready for 2nd fix?
-
6: Ductwork connected to exhaust air grill / air brick?
-
7: All debris removed and placed in skip and all unused materials returned to stores?