  • Corrections:

Site location / Area trenched

  • Locates called in and completed

  • Foreman has confirmed all changes are up to date

  • Review all drawings that pertain to work area. All site electrical, landscape and civics available for review

  • Prefab has been used as much s possible. (If not, please list ideas)

Conduit min 30" below grade per sheet E5000

  • Pass

  • Fail

Conduits ends taped with jetline in them. When pole bases are complete

  • Pass

  • Fail

  • 3/4" x 10' ground rod driving, connected with bare #6 and stubbed through templet. Rod to be driving below paving

Ensure trench is back filled in lifts and tamped following each lift. After 1st lift install detectable burial tape. Soil compacted to 95%. Dirt must have moisture

  • Pass

  • Fail

Signature

  • QC:

  • Select date

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.