Information
-
Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Personnel
-
Select date
-
Add location
-
Initial inspection
-
Follow up inspection
Description of Inspection Location
Safety/housekeeping
-
Proper PPE- Gloves, Boots, Hardhat, Vest, Glasses
-
No cutting over foot or knee
-
Include hot work or dig permits, equipment inspections, etc.
Trench Work
-
Locates called in and completed?
-
Protective system used:
-
Was a visual soil test conducted?
-
Was a manual soil test conducted?
-
Are there surface encumbrances?
-
Water Conditions
-
Hazardous Atmosphere?
-
Surcharge Load?
-
Soil Type
-
Is trench exposed to vehicular exhaust?
-
Are employees exposed to vehicular traffic?
-
Are utilities protected?
-
Are ladders within 25' of workers?
-
Do ladders extend 3' above surface?
-
Are spoils kept 2' from the edge of trench?
-
Are employees excavation trained?
Products
-
Fiberglass Elbows
-
PVC, Rigid, etc
-
Carlon Duct Spacers
Before Work Starts
-
Detectable warning tape should be 6" wide and 4 mil thick
-
Inspection of materials for proper temperature prior to installation/application
-
Inspection of materials for damage
-
Foreman has confirmed all changes are up to date and drawings are current set
-
Review all drawings that pertain to work area, including: site electrical, landscape, and civils available for review
-
Prefab has been used as much as possible. (If not, please list ideas)
Installation
-
Ensure that duct spacers are installed every 5'-0"
-
Qwest Vault-4x6x7; with ground rods
-
RMC Installed 24" below grade
-
Service conductors not concrete encased shall have a warning tape
-
Detectable Warning Tape installed 12" below grade for Comm ducts
-
No more than (4) 90 degree bends for power
-
No more than 180 degree bends for comm
-
PVC marked every 10'
-
Verify no UF Cable in garages, battery room and elevator shafts
-
Electrical Handhole cover to be marked, need tools to open, or weigh 100 lbs
-
Concrete encased duct bank under parking garage only, crushed gravel everywhere else
-
Duct bank sloped .125"/ft
-
Manholes to have waterproof sealant installed to minimize seepage
-
Provide 1800 lb. mule tape in each conduit
-
Provide 4" clear space from edge of conduit to edge of concrete
-
Provide 250 Kcmil ground in duct bank (EM only)
-
Conduit min 30" below grade per sheet E5000
-
Conduit ends taped with jetline in them. (When pole bases are complete)
-
3/4" x 10' Ground rod driven, connected with bare #6 and stubbed through template. Rod to be driven below paving.
-
Ensure trench is backfilled in lifts and tamped following each lift. After 1st lift, install detectable burial tape. Soil compacted to 95%. Dirt must have moisture.
Storage/Protection
-
Store materials on dunnage and not in direct sunlight
Required Testing
-
After install, clean and swab ducts
Misc.
-
Photos attached? Required for initial inspections
-
BIM drawings attached?
-
Details attached?
-
All incomplete items moved to Quit log?
Comments
Photographs
-
Add media
-
Add media
Sketch
-
Add drawing
Berg signature
-
Add signature
Mortenson Signature
-
Add signature
Other Witnesses
-
Add signature
-
Add signature