  • Audit Title: Apartment Inspection

  • Plot

  • Block

  • Level

  • Flat Ref

  • Flat Type

  • Kitchen Type

  • Wates / Greenwich Peninsula

  • Conducted on

  • Prepared by

Drawing ref:

  • Drawing:

2nd Fix:

Sanitary Ware.

  • 1: Check setting out positions for bathrooms\ensuites are to latest architects setting out drawings.

  • 2: Check bath handles are tight.

  • 3: Check baths are level and at correct height.

  • 4: Check bath wastes are connected and flood test to prove no leaks

  • 5: check pans and cisterns are securely fastened to floor and tight back to wall.

  • 6: Check there are no leaks to pan or cistern.

  • 7: Check basin is securely fixed to wall.

  • 8: Check basin is level and at correct height.

  • 9: All drainage waste pipes connected and falls checked.

  • 10: check basin waste and service pipework for leaks.

  • 11: check protection has been installed to all sanitary ware.

Kitchens.

  • 1: Check all waste pipework has correct fall.

  • 2: Check sink waste pipe is sound.

  • 3: Check washing machine waste has correct fall and is sound( This may be outside of the kitchen ).

  • 4: Check to ensure no leaks on service pipes.

  • 5: Check non return valves for washing machine/dishwasher are correct way round.

  • 6: Check washing machine/dishwasher valves have caps fitted.

  • 7: Check no clash of pipework below sink with bins or other fittings within cupboard.

Radiators.

  • 1: Check services installed to latest issue mechanical drawings.

  • 2: Check setting out positions bathrooms/ensuite are to latest architects setting out drawings.

  • 3: Check setting out position for kitchens are to latest kitchen specialist drawings.

  • 4: Check Manthorpe box is tight to wall and all screws are tight.

  • 5: Check all radiators are level.

  • 6: Check all radiators are to the correct height.

  • 7: Check radiators are located correctly on the wall brackets.

  • 8: Is heating system filled and vented with chemical treatment added.

  • 9: Check radiator valves are correct type (TRV / Lock Shield ) and flow is at the top of radiator.

  • 10: Check radiators have packaging left on for finals.

This inspection sheet confirms that the item or area detailed above is 100% completed in line with the current specification, drawings and pre agreed sample panels although still remaining Sub Contractors responsibility until practical completion has been achieved.

  • Inspected by sub-contractor.

  • Inspected by wates manager.

The templates available in our Public Library have been created by our customers and employees to help get you started using SafetyCulture's solutions. The templates are intended to be used as hypothetical examples only and should not be used as a substitute for professional advice. You should seek your own professional advice to determine if the use of a template is permissible in your workplace or jurisdiction. You should independently determine whether the template is suitable for your circumstances.