Document No.
-
Audit Title
-
Client / Site
-
Conducted on
-
Prepared by
-
Location
-
Have the correct bricks been delivered?
-
Has the Bricklayer loaded the job from random packs to ensure proper blending?
-
Has the correct joint finish been applied?
-
Flush jointing to Rendered areas? (No bulging past face of brick)
-
Has the back of parapet walls been finished to a uniform finish?
-
Are the correct brick ties in accordance with salt attack requirements? (Coastal)
-
Are brick ties being installed every 5th course, every stud & every 3rd course next to window/door openings & long runs?
-
Are brick ties installed to within 300mm of expansion joints?
-
Are all flashings in place below bottom plate & above all windows, doors and roof areas (e.g garage) with more than 3 courses of brickwork above?
-
Has alcor flashing been cut into reveals of all sliding doors?
-
Have adequate flashing been installed to balconies and parapet walls?
-
Add media
-
Are weep holes clear of mortar & installed every 5th brick? (1.2m centre max.)
-
Has the bricklayer left the window sill rubber in correct position?
-
Is there 10mm clearance between window and brick sills to top floor and 5mm to ground floor?
-
Are the cavity and brick ties being kept clear of mortar dags?
-
Are perps and bed joints uniform and within tolerances?
-
Are the perp and bed joints full of mortar to the face of rear brick?
-
Does brickwork conform with acceptable tolerances for line , level and plumb. Generally +/-5mm over 3 m?
-
Have steel lintels been installed correctly? (Note: end bearing and have temp.props to prevent sagging.) Mimimal clearance above windows 2mm-5mm?
-
Has brickwork been constructed in accordance with drawings?
-
Have windows & fence panels been hosed down daily?
-
Has the scaffold been left in tact and in a safe state?
-
Ensure site is left in a neat condition and rubbish placed in accessible piles away from entry and walkways, services, toilet and power supply?
-
Is the rubbish and discarded bricks been left in sorted neat piles
-
Add media
-
Check for footpath damage.
-
Add media