Title Page
-
Site conducted
-
Inspection Date
-
S Reference
-
Communications Provider
-
Installation Partner
-
Region
-
City
-
GPS Location
-
Prepared by
-
CityFibre Holdings Ltd, 15 Bedford St, London, WC2E 9HE
FTTx Installation Inspection
-
What region does the engineer mainly cover?
-
Please select the engineer's name (If not listed, select other and provide the name in the notes)
-
Please select the engineers name (if not listed, select other and provide the name in the notes)
-
Please select the engineers name (if not listed, select other and provide the name in the notes)
-
Please select the engineers name (if not listed, select other and provide the name in the notes)
-
Date Installation Was Completed
-
In Progress or Retrospective
Secondary Node (Mark all NA if direct feed from network)
-
Engineer accreditations available and in date (NRSWA, Smart awards - OR accreditations)
-
Confirm action raised to Senior Operations Manager, Kellys Regional Operations Manager and CFSafety@kelly.co.uk
-
Correct PPE being worn for activity - including safety footwear, eye shields, gloves, Hi-viz jacket.
-
Confirm action raised to Senior Operations Manager, Kellys Regional Operations Manager and CFSafety@kelly.co.uk
-
On arrival, no engineering waste left on-site at Secondary node?
-
Secondary node secure and defect free? (Including door seals)
-
No visible bare fibres from BFTs? Protective tubing installed over all fibres?
-
Fibre installed with no additional excess fibre when blown?
-
Fibre from BFT routed through cable management to allocated fibre port? No excessive bends in fibre causing potential damage and poor service - Tagged and labelled?
-
Fibre connected securely in allocated fibre port?
-
No Engineering waste left in bottom of SN cabinet?
Customer External
-
Correct PPE being worn for activity - including safety footwear, eye shields, gloves, Hi-viz jacket.
-
Confirm action raised to Senior Operations Manager, Kellys Regional Operations Manager and CFSafety@kelly.co.uk
-
(MDU IOD - check NA if pre wire) Bend radius of BFT in toby box to install specification? (13x the outside diameter of the BFT - 7mm = 91mm radius)
-
(MDU IOD - check NA if pre wire) Visually, reinstatement to required standard? (If retrospective check) A. BFT in soft to the required depth? (expose cable) Grass = 200mm, flower bed = 250mm B. BFT installed in tarmac / concrete / Mono block - reinstatement to required standard? (If in progress >100mm depth)
-
Confirm action raised to Senior Operations Manager, Kellys Regional Operations Manager and CFSafety@kelly.co.uk
-
(MDU IOD - check NA if pre wire) Facade wall box installed 2.4m above ground level in suitable location to serve all properties
-
Cable locator used on area prior to drilling - available and defect free?
-
Confirm action raised to Senior Operations Manager, Kellys Regional Operations Manager and CFSafety@kelly.co.uk
-
Drill available and defect free? Drilled at a 10 degree angle (Inside property to out)
-
Confirm action raised to Senior Operations Manager, Kellys Regional Operations Manager and CFSafety@kelly.co.uk
-
At Customer premise, external entry point to property sealed with silicone or chalk?
-
2 Fibre cable formed correctly on entry to the property? (Drip loop installed to prevent water ingress)
Customer Internal
-
Correct PPE being worn for activity - (Covid engineer policy - face mask, gloves) eye shields
-
Confirm action raised to Senior Operations Manager, Kellys Regional Operations Manager and CFSafety@kelly.co.uk
-
Internal wall box fitted - secured and level?
-
Excess 2 fibre cable coiled and secured to the correct standard as per customer excellence manual?
-
Excess fibre patch cord coiled and formed to required standard as per customer excellence manual?
-
LC connector fitted and secure in internal wall box?
-
Fibre patch cord fixed and secured leading to ONT location?
-
ONT fixed and secure to wall?
-
Fibre patch lead connected and secure in ONT?
-
If check in progress, a 'one click' cleaner used before connecting and fibre connector?
-
Services demonstrated to customer at end of completed install?
-
All engineering waste cleared from site? (Internal)
-
While working inside property customer confirms blue overshoes worn?
-
Customer satisfied with service received?
Secondary Node (Mark all NA if direct feed from network)
-
On arrival, no engineering waste left on-site at Secondary node?
-
Secondary node secure and defect free? (Including door seals)
-
No visible bare fibres from BFTs? Protective tubing installed over all fibres?
-
Fibre installed with no additional excess fibre when blown?
-
Fibre from BFT routed through cable management to allocated fibre port? No excessive bends in fibre causing potential damage and poor service - Tagged and labelled?
-
Fibre connected securely in allocated fibre port?
-
No Engineering waste left in bottom of SN cabinet?
Customer External
-
(MDU IOD - check NA if pre wire) Bend radius of BFT in toby box to install specification? (13x the outside diameter of the BFT - 7mm = 91mm radius)
-
(MDU IOD - check NA if pre wire) Visually, reinstatement to required standard? (If retrospective check) A. BFT in soft to the required depth? (expose cable) Grass = 200mm, flower bed = 250mm B. BFT installed in tarmac / concrete / Mono block - reinstatement to required standard? (If in progress >100mm depth)
-
Confirm action raised to Senior Operations Manager, Kellys Regional Operations Manager and CFSafety@kelly.co.uk
-
(MDU IOD - check NA if pre wire) Facade wall box installed 2.4m above ground level in suitable location to serve all properties
-
At Customer premise, external entry point to property sealed with silicone or chalk?
-
2 Fibre cable formed correctly on entry to the property? (Drip loop installed to prevent water ingress)
Customer Internal
-
Internal wall box fitted - secured and level?
-
Excess 2 fibre cable coiled and secured to the correct standard as per customer engineering manual?
-
Excess fibre patch cord coiled and formed to required standard as per customer excellence manual?
-
LC connector fitted and secure in internal wall box?
-
Fibre patch cord fixed and secured leading to ONT location?
-
ONT fixed and secure to wall?
-
Fibre patch lead connected and secure in ONT?
-
All engineering waste cleared from site? (Internal)
-
Customer satisfied with service received?