Information
-
CSA
- CSA 01
- CSA 02
- CSA 03
- CSA 03T
- CSA 03U
- CSA 04
- CSA 05
- CSA 06
- CSA 07
- CSA 07U
- CSA08
- CSA08U
- CSA 09
- CSA 09U
- CSA10
- CSA 10U
- CSA 11
-
Job ID
-
Job Source
-
Address
-
Audit date
-
Auditor
-
Auditee
Desktop checks
1.000 Design
-
1.001 All documentation lodged in iTools e.g. Scope, CDPs, RMA site plans, lay, hauling and grid plans. note costs to be in Chorus Shared drive except for RBI
-
1.002 iTools progress task dates updated
-
1.003 NetMap design not in conflict with other design work
-
1.007 Build standards applied in design, manhole and cable size, plant location and position
-
1.012 Work priced correctly using template, FS codes and quotes as applicable
-
1.022 Billed tasks actually done
-
1.024 Design summary recorded in the Feasibility Outcome field
-
1.025 Build category correctly identified and recorded
2.000 Handover and collateral delivered to Chorus
-
2.003 Timing correct for RFS and DDC. recommits meet business rules
-
2.004 Compliance certificates available (RMA, PTW, RON, TMP, electrical)
-
2.006 Work plan, H&S, technical procedure, PTTN accreditation approval, access card current
-
2.008 TLRD/NetMap updated, integrity checked and confirmed
-
2.011 Inventory database updated
-
2.019 All network items defined within the Chorus Network Specified Product (CNSP) process are used in the network. No non-approved items used
-
2.021 Cable Network Alteration (CNA) form completed and correct
-
2.022 Cable Plant Alteration (CPA) forms completed and correct
-
2.025 Addresses on As Builts match physical address
4.000 Codes
-
4.004 Correct statement of works codes used
55.000 Network Records
-
55.002 Correct standard has been used?
-
55.006 Recording made to the appropriate standards
-
55.007 All new trenches plotted consistent with the As Built lay plan
-
55.010 All network items labelled (UUB, T/E)?
-
55.011 Trench table contents are correct
-
55.012 Sufficient number of trench tables have been placed
Exchange checks
11.000 OFDF & Exchange Fibre
-
11.001 All optical cables 100% supported on horizontal and managed on vertical, no more than 400mm fibre cable to be unsupported
-
11.002 OFDF hardware secure: OFDF drawer - cable trough - guides - rack
-
11.003 Network labelling correct at OFDF and log completed
-
11.004 Optical cables and cords adequately managed within racks and shelves
-
11.005 OFDF single fibre organiser tray not overfilled (<1.5 m tails)
-
11.007 30mm bend radius unconditionally observed at all locations
-
11.008 Fibre pigtail label records 'from' OFDF ID and SFO number
-
11.009 Trunking manages fibre cords within maximum capacity limits, drop off position ok, flexitube anchored at equipment
-
11.010 Protective caps on all unterminated connectors
-
11.013 No fibre task waste, all optical (glass) ends safely contained
-
11.014 Access OFDF patch cords routed within mandrels. Excess length stored at AOFDF end
-
11.015 Access OFDF passive devices within OCM shelf, all unused ports capped
-
11.018 Access OFDF rack (GR3) :cables secured, breakout to OFDF shelves tidy
-
11.022 Patch cords on the POLT are installed and labelled
-
11.023 OCM shelf data card filled out correctly with drawer ID and fibre number
Field checks
13.000 Cable Haul
-
13.001 Correct cable installed as per project pack
-
13.003 Correct duct used, or changes recorded on As Builts
-
13.008 Correct method used to blow/suck
-
13.009 Communication method adequate (H & S of staff)
-
13.016 All cable ends sealed with heat shrink, coiled and secured ready for use
-
13.022 Fibre cable prepared for joint correctly in manhole (cable management tidy to cable loop brackets)
-
13.023 Manhole/joint chamber lids free of material, bung fitted in lifting hole, lid locked
-
13.025 RMA: Contaminated manhole water collected for disposal
15.000 Cable and Duct Lay
-
15.005 Route position correct according to plan
-
15.006 Correct cables identified and installed
-
15.007 Cable ends sealed with heat shrink
-
15.008 Warning tape installed
-
15.015 Manhole/joint chamber lids free of material, bung fitted in lofting hole, lid locked
16.000 Micro Duct Directional Drill and Lay
-
16.006 Route position correct according to plan
-
16.007 Micro duct ends sealed with heatshrink
-
16.008 Micro duct end on customer boundary either buried or housed in approved enclosure (e.g. Pedestal)
-
16.010 Micro duct joints to standard - approved enclosure, correct connectors, earth continuity maintained, water tight etc
-
16.011 Micro duct joints at correct depth and not on a bend
-
16.012 Micro duct joints protected
-
16.017 Warning tape installed
-
16.026 Micro duct correctly labelled
17.000 Manhole, joint chamber and ducts (new and existing)
-
17.001 Manhole preparation, bedding, backfill compacted ok
-
17.002 Manhole sited correctly to plan and parallel to boundary line
-
17.003 Manhole correctly sized, as per Design Job Specification
-
17.004 Manhole frames flush to ground, no trip hazard
-
17.005 Manhole stripped of form work, no protruding nails left
-
17.006 Manhole throat (where fitted) correct diameter and does not obstruct access
-
17.008 Concrete panel joints sealed to prevent water ingress
-
17.009 Manhole floor level, sump hole fitted
-
17.010 All manhole duct entry grouted, duct reamed, sits flush to wall
-
17.011 Non-concrete joint chamber duct entry protrudes into chamber 50mm, reamed, sealed to wall
-
17.012 Manhole cable management brackets installed to accept arms
-
17.013 Manhole cable management arms installed as required
-
17.014 Manhole/joint chamber lids locked, in working order and rubber bung fitted
-
17.015 Duct entry positioned close to adjacent wall for easy cable management
-
17.016 Duct sealed where necessary to prevent ingress of water, moisture, gas, pests into buildings and cabinets
18.000 Manhole Cable Management
-
18.001All cables managed tidily on brackets and arms
-
18.002 Fibre cable prepared for joint correctly in manholes (cable management tidy to cable loop brackets)
-
18.003 Fibre cable protection when required - tread plate/split subduction/bandit tape
-
18.004 Fibre closure secured to manhole wall with bracket
19.000 Fibre Jointing and Closure
-
19.001 Joint closure secured on manufacturer's bracket
-
19.002 NetMap label on closure and each cable tail
-
19.003 Laser safety label (Starburst) visible outside and inside closure
-
19.005 Mechanical closure fittings correct (fitting, seal)
-
19.008 Unused tubes contained,managed, secured without stress
-
19.010 30mm bending radius unconditionally observed at all locations
-
19.012 Heat shrink splice protectors secured from movement
-
19.014 No fibre or task waste, all optical (glass) ends safely contained
25.000 Poles
-
25.001 All mechanical aids in good working order, regular checks
-
25.003 Pole in good condition, no splits or burrs
-
25.010 Pole safe to climb, hammer, probe, dig
-
25.012 Plant positioned correctly and safely,plant clearances correct
-
25.014 Unsafe poles labelled/marked up for replacement/7 days
-
25.015 Unsafe poles noted in Hazardous Pole Register
39.000 UFB FFP
-
38.001 Outer door lock works smoothly and door closes without jamming
-
38.002 Door stays in place and work well
-
38.003 Cabling run correctly
-
38.005 Terminal label on lid or plate on pole
-
38.006 Distribution frame: Data shard inside of drawer
-
38.008 All micro ducts earth terminated
-
38.009 All micro duct earths labelled
-
38.010 All duct seals in place for cable entry (100mm)
-
38.012 Locks and hinges ok
-
38.013 Door seals in good condition
-
38.017 All unused connectors capped
-
38.019 All micro ducts sealed
-
38.020 All micro ducts labelled
-
38.021 Fixed fibre strain relief installed
-
38.023 Fixed fibre sub-shelves. First distribution fibre over second roundel etc
-
38.024 Fibre entry to cabinet correct (32 mm duct)
-
38.027 Managed via mandrels/Velcro ties used
-
38.028 Two fibres per customer connection rule observed within an individual tray
-
38.029 No fibre or task waste, all optical (glass) ends safely contained
-
39.037 Connect, verify minimum bend radius maintained when drawers are opened and closed
39.000 Aerial Terminal/OFDC
-
39.001 Correct terminal used
-
39.002.Terminal mounted and secured correctly
-
39.004 Terminal lid secure
-
39.013 Network labelled in place to suit requirements
-
39.014 Terminal on correct pole face
-
39.015 Flexi pipe secured directly below terminal (galv saddles on wooden pole)
-
39.016 Flexi pipe secured directly below terminal (bandit tape on concrete pole)
-
39.017 20mm or 32mm conduit secured to pole (wooden -galvanised saddles for White PVC, plastic saddles for grey/beige 32mm HDPE pipe, secured with clouts or bandit straps, 600mm spacings
-
39.018 20mm or 32mm conduit secured to pole, spaced less than or equal to 1.5m (concrete bandit tape)
-
39.019 Protective cable casing installed as required, concrete or wood
-
39.020 Reduce joiner installed between flexi pipe and conduit
-
39.035 Tray labelled with fibre numbers and customer's address
41.000 BDD Terminal
-
41.001 Pit lids secure/locked, with bung fitted where appropriate
-
41.002 Pit installed correctly
42.000 Pedestal
-
42.001 Pedestal vertical, firm, at correct depth
-
42.008 Foam bung fitted/ in correct position
-
42.015 Micro duct sheath opening 50mm above bung
-
42.023 Network labelling in place to suit requirements
58.000 Fibre Access Terminal
-
58.027 Gel seal fully tightened
-
58.028 Customer 'lead in' felt tape 5mm from end - secured to bracket, 2 cable ties
68.000 Fibre Access Terminal
-
68.001 Entry tubes sealed
-
68.002 Two fibres per tray only
-
68.003 Lead cleaned and abraded
-
68.004 Rayblocks fitted to tubes (90mm) and shrunk down to seal cable into access tube (glue extruding)
-
68.005 Tube holder installed
-
68.007 Silica gel pack installed
-
68.008 Triangle symbols on dome and base match
-
68.009 All latches locked
-
68.010 O-ring installed
-
68.011 Fibre correctly managed within FAT and trays
-
68.013 Slack managed in fibre management coil (1.5 - 2m)
-
68.014 Swing arm and bracket in working order/or mounted on manufactured bracket
-
68.015 Lid locked and lock bung fitted
-
68.016 30mm bending radius unconditionally observed at all locations
-
68.018 Heat shrink splice protectors secured from movement
-
68.019 No fibre or task waste, all optical (glass) ends safely contained
-
68.020 FAT labelled correctly
-
68.021 Fibre strain relief installed correctly
69.000 Blown Fibre Boundary Connection
-
69.001 1-way connected correctly
-
69.002 1-way Ribbonet connector secure
-
69.003 Cover board installed prior to reinstatement
74.000 Hand Holes
-
74.001 Bedding done correctly and compacted
-
74.002 Hand hole locked, with lock facing the customer's boundary and openable
-
74.003 Starter pipe(s) installed to facilitate provisioning of NGA services
-
74.004 Hand hole flush with ground
-
74.005 Laterals sender hand hole from the side
-
74.006 Lateral labelled and sealed. End cap and heat shrink
-
74.007 Hand holes locked
-
74.008 Lid free from concrete/seal
-
74.009 Sited correctly (close to boundary, hard surface, foot traffic only)
-
74.010 Single way Ribbonet, one turn only, sealed with heat shrink
-
74.011 Maximum of four single way Ribbonets installed
75.000 Ground Level Closure
-
75.001 GLC vertical and firm
-
75.002 Lid secure
-
75.003 Lid labelled
-
75.004 Micro ducts labelled
-
75.005 Micro ducts 20mm above bracket
-
75.006 Micro ducts installed
-
75.008 Fibre strain relief installed
-
75.009 Gas blocker installed (GLC)
-
75.010 Continuity wires installed and labelled
-
75.011 Tray retention strap in place
-
75.016 Splice Trays installed and labelled correctly
77.000 Flash 9 installation
-
77.026 Fibre routed and laid up correctly in trays
78.000 Building Distributor
-
78.001 Correct reducers used and protection installed
-
78.002 BUDI vertical
-
78.003 BUDI lid secure
-
78.004 Incoming fibre secured to anchor point with foam and zip tie
-
78.005 Lid labelled
-
78.006 Micro ducts labelled
-
78.007 Micro ducts trimmed to the correct height, 220mm from base of cabinet
-
78.008 Micro ducts capped
-
78.009 Gas blocker installed
-
78.010 Continuity wires installed and labelled
-
78.011 GPX cabinet - Tray retention strap in place
-
78.012 ABF entry tubes sealed
-
78.013 Two fibres per tray only
-
78.014 Fibre routed
-
78.015 Slack managed in fibre management coil
-
78.016 30mm bending radius unconditionally observed at all locations
-
78.017 No fibre or task waste, all optical (glass) ends safely contained
-
78.018 Feeder/fibre cables labelled correctly
-
78.019 Terminal lid secure
-
78.020 Correct terminal used
-
78.021 Network labelling in place to suit requirements
-
78.022 Terminal label on lid
-
78.023 Splitter installed and labelled
-
78.024 Fibre management - Tray retention strap in place
-
78.025 Appropriate external pipe and fixings used
-
78.026 Reinstated in accordance to AS/NZ3000 standard
-
78.027 Riser cable/micro duct dimensioning in accordance with section 5.1.4 ND0574
-
78.028 End terminated into correct BUDI 2S
-
78.029 GPON feeder fibres to future PON splitters reserved in NetMap
-
78.030 MDU lead in cables and IBDN recorded in NetMap
-
78.031 All unused connectors capped
-
78.034 Micro duct management coil or bend back to prevent the EPFU creeping down the riser. Bend back and tie on away side
-
78.035 Labelled with correct network label
-
78.036 Outer door locks work smoothly and door closes without jamming
-
78.037 Feeder fibres installed on far left hand side
-
78.038 Distribution frame:Correct trays installed and labelled
-
78.039 Distribution frame: Data card inside drawer and labelled with the splitter, unit and level numbers
-
78.040 All micro duct connectors capped
-
78.041 All micro ducts labelled
-
78.042 All 5mm micro duct fibre strain relief installed
-
78.043 Correct number of mandrels used
-
78.044 Minimum bend radius maintained when drawers are opened and closed
-
78.045 Splitter installed and labelled, and splitter legs secured in parking bay
-
78.046 Verticassa cable secured to wall/tray in riser
-
78.047 Window cut does not exceed the breakout limit
-
78.048 Cable protection cover installed on unused window
-
78.049 Coil at base of the riser and top of the riser
-
78.050 If second Verticassa installed, must have gravity coil at end of first cable
-
78.051 If third Verticassacinstalled, must have gravity coil at end of second cable
-
78.052 Micro duct secured to wall/tray in riser
-
78.053 Tap off box secured to wall/tray in riser
-
78.054 All tubes jointed correctly where they exit the top off box to floors
-
78.055 Labelled correctly
-
78.059 Correct number and type of trays installed
Customer Premise checks
43.000 Aerial Service Lead
-
43.001 Correct service lead used
-
43.002 No In Span joints (single Ribbonet aerial)
-
43.003 Tension, sag correct
-
43.004 Correct fittings used and installed correctly (screw eyes, clamps, poles and buildings)
-
43.005 Lead-ins enter terminal correctly
-
43.006 White pipe only on poles, secured correctly
-
43.007 600mm saddle spacing (wooden poles) or 1500mm bandit spacing (concrete pole)
-
43.008 Roadway crossing at correct height
-
43.012 Correct building fittings used and installed correctly (screw eyes,clamp)
44.000 Service Lead
-
44.001 Service lead terminated correctly
-
44.002 20mm pipe connected at pedestal correctly (bend into pedestal)
-
44.003 20mm pipe connected at BDD correctly (50 mm into BDD pit, 450 mm depth)
-
44.007 Green 20mm pipe installed in trench
-
44.008 White pipe above ground level
-
44.009 Depth correct
-
44.010 Power/gas clearances correct
-
44.013 Pipe connected at ETP correctly (not glued)
-
44.017 Both ends of Ribbonet Correctly sealed during lead-in process
45.000 ETP
-
45.001 ETP physical alignment correct, all fittings secure, installation tidy
-
45.005 20mm pipe to ETP is white or grey only (not green)
-
45.017 Ericsson S/NEG203200 ETP installed
-
45.021 White pipe or flexi duct fitted to building is secured correctly
-
45.022 50-20mm duct reducer fitted between 50mm underground green duct and 20mm above ground white pipe
-
45.023 Fixed fibre or ABF tube housed in 20mm white or grey pipe or UV stabilised flexi pipe where fibre exits through bottom of ETP
-
45.024 Correctly connected to hybrid cable at ETP
-
45.026 30mm bending radius unconditionally observed at all locations
-
45.027 Fibre splicing within design tolerance
-
45.028 Heat shrink splice protectors secured from movement
-
45.029 Fibre continuity confirmed
-
45.030 No fibre or task waste, all optical (glass) ends safely contained
-
45.031 Gas block connector installed on the micro duct and locked
-
45.034 Micro duct held in position with zip tie or integrated saddle within ETP
-
45.035 Laser label positioned externally on the lid, supplied screw installed in bottom and front of ETP
-
45.036 Cable entry to building sealed
-
45.037 Unused copper pairs capped with clearing connectors
-
45.038 Hybrid cable/pigtail enters ETP at correct position
-
45.039 Fibre managed correctly, length not excessive causing unnecessary bends or stress
-
45.040 Min 5mm hybrid cable sheath inside ETP
-
45.043 ETP installed, secured with 3 screws and installed to best suit the site
47.000 Business Premises
-
47.002 Equipment labelled and secure
-
47.006 Connectors cleaned and verified with fibre inspection probe
-
47.007 No fibre or task waste, all optical (glass) ends safely contained
General Workmanship checks
6.000 Work Areas and Safety
-
6.001 Personal and site safety procedures observed
-
6.002 Hazards identified and recorded. Worksite audit form completed, hazard notices in place
-
6.003 TMP provided
-
6.004 Services located
-
6.005 Power and gas clearances correct
-
6.006 Gas detector within current calibration certificate
-
6.007 Gas detector measures O2, flammable,carbon monoxide (and hydrogen sulphide in volcanic areas)
-
6.009 Joint chamber/manhole lids closed and secured
-
6.012 Temporary work clearly labelled and contains name, contact details, job ID of person involved
-
6.013 Latest version of relevant standards and practices documentation held by sub-contractor or field technician
-
6.014 Any defects to existing network outside of scope of project referred to be rectified in the future
72.000 Reinstatement
-
72.001 Property damage made good
-
72.002 Ground reinstatement complete around poles
-
72.003 Reinstatement/backfill satisfactory around buried service leads
-
72.005 Cabinet ground reinstatement complete
-
72.006 Concrete flush with footpath or surrounding ground, no trip hazard
-
72.007 Excess vegetation removed
-
72.008 Reinstatement complete around pedestal
-
72.009 Reinstatement complete around hand holes
-
78.011 Reinstatement appropriate around cable haul
-
72.019 Backfill completed every 150mm
-
72.020 Surplus soil removed
-
72.021 Reseal completed - footpath/vehicle resurfaced
-
72.022 Grass reinstated and replanted
-
72.023 Ground reinstatement completed around manholes
73.000 Site tidy
-
73.001 Site tidy, no task waste - Poles
-
73.002 Site tidy, no task waste - Cabinet internal
-
73.003 Site tidy, no task waste - Aerial terminal
-
73.004 Site tidy, no task waste - Pillar terminal
-
73.005 Site tidy, no task waste - BDD terminal
-
73.006 Site tidy, no task waste - PDS terminal
-
73.007 Site tidy, no task waste - Aerial service lead
-
73.008 Site tidy, no task waste - Service lead
-
73.009 Site tidy, no task waste- ETP
-
73.010 Site tidy, no task waste - Customer premises
-
73.011 Site tidy, no task waste - Business premises
-
73.012 Site tidy, no task waste - Cabinet external
-
73.013 Site tidy, no task waste - Hand holes
-
73.014 Site tidy, no task waste - Cable haul
-
73.020 Site tidy, no task waste - Manholes